This document is a Request for Information (RFI) containing 73 questions and answers related to a VA construction project for Sterile Processing Services at the Sioux Falls Health Care facility. The RFI addresses technical, logistical, and procedural details for potential contractors, including:

Key project requirements include SDVOSB (Service-Disabled Veteran-Owned Small Business) set-aside procurement, with past performance projects valued between $10-20 million, and a Notice to Proceed date of October 1, 2025. Technical specifications cover electrical systems, lighting controls, data infrastructure, fire alarm devices, and construction logistics. Notable requirements include AISC-certified steel fabricators, specific conduit and cable tray specifications, badge requirements for workers, and a submittal platform for project documentation. The project involves approximately 8,500 square feet of new construction and 2,300 square feet of renovation adjacent to the operating room in Building 5, with careful coordination needed for utility systems and minimal disruption to hospital operations.

View the file

Other files

File Type Posted
S06 - Amend 0010 - RFP - 36C77624R0115 - SPS - Sioux Falls_rev.docx DOCX document
S06 - Amend 0010 - RFP - 36C77624R0115 - SPS - Sioux Falls.docx DOCX document
S06 - Amend 0009 - Att 12 - DWG EP111 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 07 - List of DWG Sheets - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 03 - DWG AC101 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 10 - Ele Sch - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 16 - DWG ES401 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 04 - DWG AD111 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 08 - DWG CD101 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 01 - Sign-In Sheet - Ele Site Visit- 05142025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 19 - DWG MV600 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 20 - DWG GI001 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 13 - DWG ES099 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 06 - DWG GC111 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 17 - DWG ES500 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 09 - Add Ele Questions and Responses - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 15 - DWG ES400 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 11 - DWG EP101 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 18 - DWG ES501 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 02 - Narrative to KTRs - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 14 - DWG ES100 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0009 - Att 05 - DWG AE111 - Rvd - SPS - Sioux Falls.pdf PDF
S06 - Amend 0008 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
36C77624R0115 0007.pdf PDF
Amend 0007 - Att 01 - RFI Attachments.pdf PDF
S06 - Amend 0006 - Att 01- RFP - Sign-In Sheet - Site Visit - 04082025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0006 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0006 - Att 02 - Wage Rates - 03142025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0005 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0004 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0003 - RFP - Sign-in Sheet - Site Visit - 03252025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0003 - RFP - Site Visit Presentation - SPS - Sioux Falls.pdf PDF
S06 - Amend 0003 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - 36C77624R0115 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-05 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-02 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-08 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-03 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-09 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-07 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-11 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-10 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-01 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-06 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amend 0002 - RFP - Att 01-04 - DWG - 03242025 - SPS - Sioux Falls.pdf PDF
S06 - Amendment 0001 - SPS - Sioux Falls.pdf PDF
RFP - Att 02 - 02142025 - Specs - Vol I - SPS - Sioux Falls.pdf PDF
36C77624R0115_1.docx DOCX document
RFP - Att 01-01 - DWG - 02142025 - SPS - Sioux Falls.pdf PDF
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ/RFP: 363C77624R0115

Request for Information Project: Sterile Processing Services – Construction

VA Sioux Falls Health Care – Sioux Falls, S.D.

RFQ: 36C77624R0115

04/29/2025

NO. QUESTION GOVERNMENT RESPONSE

1. Is this project tax exempt and if so will a certificate be issued?

The VA provides state specific notes after the federal, state, and local tax clause, 52.229-3, in all construction solicitations. This note is on page 54 of the RFP. In short, the VA has reviewed South Dakota tax law and does not find advantages; therefore, you must include federal, state, and local tax into material purchases. This project is not tax exempt. A certificate will not be issued.

2. How will payment be managed for materials stored off-site or on-site before installation?

A. Will full or partial payment be made?

B. Is proof of payment for the materials required?

For example, if a significant portion of the structural steel is fabricated and stored off-site, can it be billed before delivery, or must the contractor/supplier cover these costs until the material arrives on-site? Please provide a clear yes or no answer rather than simply referencing VAAR 852.232-70, as this states that the payment for stored materials as at the CO's discretion.

A definitive yes/no cannot be provided at this time because there are several caveats in the regulations that must be met and it is at the discretion of the governing

CO when invoices are submitted. That being said, structural steel is a long-lead qualifying item. Best suggestion is to carefully follow the reg.

Regulation posted below for all to review:

The VA is willing to consider material procured by the contractor and stored on the construction site or at a local approved location off site as long as all of the conditions of VAAR 852.232-70(d) are complied with by the contractor and all long lead time materials must be identified in the fully cost loaded baseline schedule. For the first payment to be made, the CO must be provided proof of the concurrence of their surety for off-site storage per VAAR 852.232-70(d)(5). Additional notes:

a. Overall, the approval of payment for stored materials is at the Contracting Officer’s discretion and determined on a case-by-case basis. Factors considered by the

Contracting Officer include, but are not limited to:

i. Contractor performance.

ii. Schedule date for installation.

iii. Type of Materials – must be major, high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, pre-cast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

b. The materials are in accordance with the contract requirements and/or approved samples and shop drawings. Material submittals must have been approved by the VA / COR before purchasing the materials and requesting payment.

c. The materials are not proprietary to a subcontractor and can be installed and warrantied by more than one (1) subcontractor.

d. The materials must be in original sealed packages or containers, marked with the name and brand, or trademark of manufacturer.

f. The materials are and will continue to be protected against improper handling, weather, theft, and other hazards.

g. The materials are not subjected to deterioration and will continue to not be subjected to deterioration.

h. The Contractor must maintain an inventory list of stored materials at all times, including after payment.

NO. QUESTION GOVERNMENT RESPONSE

The Government reserves the right to inspect the property and materials at any time, including prior to approving any payment applications that include stored materials.

i. All warranty periods in the contract start at the

Contracting Officer’s final acceptance of the installation.

Payment for stored materials does not signify the final acceptance or the start of any warranty periods.

j. A cost loaded schedule that clearly indicates all stored materials with the status as stored or installed.

k. A pay application that clearly indicates all stored materials with the status as stored or installed. Note:

Subsequent cost loaded schedules and schedules of value must track the schedule and schedule of values must clearly indicate when the stored materials are installed.

l. Contractor certification stating the documentation provided for stored materials is accurate and agrees that they are responsible for the materials until installed and accepted by the Government.

m. Contractor must confirm their agreement to these terms, or we can discuss further.

A. Will full or partial payment be made:

The Contractor shall include on the pay application only the invoiced cost of stored materials with ten (10) percent retainage deducted. Labor, retainage, overhead and profit, general conditions, etc., shall only be included on pay applications after installation of the materials.

B. Is proof of payment for the materials required:

Yes. It is through inventory taken by the COR when the material arrives at the storage location. This inventory is reviewed each month and the CO may require copies of invoices as well.

3. CQCM - Is the Contractor Quality Control Manager required to be onsite full time with no other duties?

Specification Section 01 45 00

- Paragraph 3.4.B. defines the requirement for the

CQC System Manager (QCM). This CQC System manager is on the site at all times during construction and is employed by the General Contractor. The

CQC System Manger is assigned as CQC System

Manager but has duties as project superintendent in addition to quality control. Identify in the plan an alternate to serve in the event of the CDQC System

Manager’s absence. The requirements for the alternate are the same as the CQC System Manager.

NO. QUESTION GOVERNMENT RESPONSE

4. SSHO – Is the Site Safety and Health Officer required to be onsite full time with no other duties?

Specification Section 01 35 26

- Paragraph 1.9.A states the Prime Contractor shall provide a Safety oversight team that includes a minimum of one (1) person at each project site, for each shift, to function as the Site Safety and Health

Officer (SSHO). The Prime Contractor shall provide a minimum of one “Full-Time” SSHO at each project site, for each shift (with no other duties).

5. Is there any clearly defined scope of work that falls under delegated design, requiring the contractor to handle the design and engineering? Delegated design can be challenging for general contractors, as it requires completing design and engineering before bidding to accurately estimate costs. If any items are considered delegated design, please either include them in the construction design package or provide a detailed list here.

This is a Design Bid Build procurement; the GC should execute 100% contract documents provided by the

Designer of Record.

6. Is the contractor responsible for hiring its own blast engineer for doors, glazing, and louvers? Does compliance with the blast requirements fall under

"delegated design"? If so, bidding general contractors would need to hire and pay for a blast engineer to complete this design before submitting their bids to fully understand the scope of the blast requirements.

However, completing a blast design before the bid deadline may not be feasible, as these designs typically take 4-6 weeks to develop and then 1-2 weeks to price depending on the extent of required blast and the firm.

Per A/E: Delegated Design for blast comes directly from the VA Master Specifications.

7. Can the drawings be re-issued to be the correct size and not 8.5x11's?

Amendment 0002 Updated DWGs

8. Where is the designated contractor parking area? No on-site contractor parking is allowed.

9. Where is the project laydown/storage yard? All laydown and storage areas must be confined to project work area inside construction fence.

10. Can the contractor hook into VA power for its construction trailer? Will it need to be metered?

No

11. Are there any badging requirements for construction workers? If so, what are they? Will every worker need to be badged or just team leaders/escorts? If the VA takes an unreasonable amount of time to process badges, can temporary daily or weekly badges be used until permanent badges are processed?

Yes, all workers will have to obtain a badge. It is recommended that badge requirements be submitted as part of the project submittals. Anyone not having a badge upon arrival to the campus will need to be escorted.

12. Is the contractor responsible for suppling a Submittal

Exchange type website?

Contractor to provide some form of submittal platform, similar to Submittal Exchange or approved equal, for use by all team members including (but not limited to):

Contractor, Sub-Contractor, Supplier, A/E, and VA team members. It shall be provided for the entire duration of the project.

NO. QUESTION GOVERNMENT RESPONSE

13. Are the steel fabricator and erector required to be

AISC certified? Or can this requirement be waived?

In our experience, this really limits the pool of steel fabricators/erectors and usually will add to the cost of the proposal.

Yes, per structural steel Specification Section 05 12 00, Section 1.5 QUALITY ASSURANCE the steel fabricator and erector shall be AISC certified.

14. For MH-20 electrical relocation - This will cause an outage for everything this manhole feeds. Will the contractor be responsible for providing back-up power to the areas effected? or can the areas effected be shut down for a period of time. If so, what is the duration they can be shut down for? If we are to provide backup power, please provide all areas affected and the loads associated so we can size power appropriately.

This is the hospital’s emergency power and will need to be fully maintained. No shutdowns will be allowed. You will be required to provide temp emergency power to each of the ATS's while the work is being completed. In terms of loads, size the temp power accordingly to what each ATS is rated for, which is listed in the drawing set.

15. Will the Schedule of Values and Pay Applications need to be cost loaded to match the project schedule?

Yes

16. Are there any seismic requirements for MEP systems?

If there are, have they been incorporated with the design already? or is the GC to hire a seismic engineer to tell us how to install?

The project’s seismic design criteria are Seismic Design

Category “A”, thus seismic bracing of MEP systems is not required by ASCE 7.

17. Is the Contractor's Scheduling Consultant as outlined in 01 32 16.15 (1.3) to be a 3rd party consultant? Or can this individual be employed by the GC?

Specification section 01 31 16.15

- Paragraph 1.2.C states the Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.

18. Are all of the competent Persons as outlined in 01 35

26 (C-H) to be employed by the GC or can subcontractor's personnel be used?

See Specification Section 01 35 26, Section 1.9, “SITE

SAFETY AND HEALTH OFFICER” (SSHO) AND

“COMPETENT PERSON” (CP).

19. Please confirm that specification 01 00 00 (1.6) E (2) does not indicate that materials cannot be stored onsite for more than 2 days prior to installation as other VA Campuses have tried to interpret it this way.

Materials stored within the laydown yard of the project will have no time restrictions placed on them. Materials located within any indoor space, approved by the COR, will only be allowed to be stored for no more than two

(2) days.

20. Please clarify the extent of the coordination drawings listed in 23 05 11 (1.4) H as it relates to existing piping.

23 05 11 Article 1.4.H requires coordination drawings for both new systems and existing systems in the same areas. There is new piping shown in areas throughout the project area, which is detailed on sheets MP091, MP101, MP111, and MP121. Any existing piping in these areas should also be included in the coordination shop drawings.

NO. QUESTION GOVERNMENT RESPONSE

21. There is a new telecom room that was just installed in another project located within the footprint of this work.

What is the intent for that room? Will the plans be redesigned to include it, will it need to be moved?

The IT room will need to be relocated to the new space as shown on the plans. A modification will be established during the construction to accommodate this change. Bid the project per plans and specs knowing more information will be forth coming.

22. RFP Section 2.8 Proposal Requirements Section C

Volume IL Technical Proposal Requirements

Subsection 2 Factor 2 Past Performance:

We think the Solicitation unduly restricts competition amongst SDVOSB businesses by placing high dollar value requirements on Experience and Past

Performance (at least one project with a construction value of at least $20,000,000).

Would your team please consider revising this minimum value to $4,000,000?

The scalable magnitude will be adjusted to reflect $10M.

The language will be adjusted from “shall” to “may” as the Government wants vendors to submit the projects and performance, they think best represent the totality of the project. These projects will be taken in whole upon analysis.

For example, a vendor might submit $4M, $10M, and

$15M projects that have decreasing degrees of complexity. This is useful in demonstrating all that the

Government is looking for; magnitude, scope, complexity, etc.

23. Factor 1 requires a "schedule shall assume a Notice to

Proceed date of April 01, 2025".... The Solicitation

Bid Date noted on amendment 00001 states April 18, 2025. Is it the VA's intent for our schedule to assume this start date pre-bid?

Notice to Proceed date will be reflected as 01 October

2025.

24. Factor 2 states "Projects shall have a minimum value of $20,000,000.00 and substantially complete in the past 4 years". Will the VA allow projects to be minimum $15,000,000.00?

Reference Question #22

25. The plans show what looks like a new oxygen line but the piping is not bold like the other lines.

Will there be a new 2” oxygen line?

The oxygen piping shown on PL100, PL101, PL111, along with all specified components and equipment, are included within the scope of the project.

NO. QUESTION GOVERNMENT RESPONSE

26. On Sheet QH101 the equipment schedule identifies equipment that is VA provided and contractor

Installed.

a) Confirm the VA has not included install with their contracts to purchase the equipment

b) If the VA has not contracted for installation, please provide the contact information for each of the companies / purchase agent.

a. Steris Corporation

b. Scranton Products

c. Cantel Medical

c) Provide cutsheets for each piece of equipment for VA supplied for GC installation.

a) Contractor is to install equipment as specified.

b) Contact Info:

a. Steris Corporation: Ryan Henke, 701.371.1780, ryan_henke@steris.com

b. Scranton Products: unknown

c. Cantel Medical (is now also Steris): Matt

Grummert, 402.310.2153, matt_grummert@steris.com

c) Cut sheets are included in the response to these questions.

27. Detail 4 on AE501 states to reference specification 08

56 53. This specification section was not included in the Bid Documents. Please provide the missing specification section.

See documents issued with these responses.

28. Note 8 / FP000, Note 8 / MV000, Note 8 / MP000, states to provide temporary connections to maintain existing systems in service during construction.

Please identify the systems that need to be maintained in service and where they are located.

This note pertains to all systems within the scope of the project. Reference Note 10 same sheets for additional information.

29. For building 24 there are electrical feeds that are to be relocated. Identify what areas they serve.

All feeders that are known are listed on the electrical site plan schedule and are based on information found on existing drawings. Further site investigation may be required if more feeders/raceway are discovered.

30. Can photos be provided of the inside of building 24 and of any panels / schedules of gear.

See documents issued with this response.

31. Key Note FL12 on Sheets AE101 & AE111 key note

FL12 is for Virtual Windows. Sheet AE101 does not have any FL 12 notes for Virtual Windows, however

Electrical sheet EP101 has power in Corridor C43, G79-5 and D18.

- Advise if Virtual windows are required in C43, G79-

5 and D18 in locations shown on the electrical drawings?

- Provide the required size of the windows, i.e. detail

14 / AE212 is appears to be a different size from the other interior elevations (8, 13 & 15 / AE212).

Plans and Elevations have been revised. See revised sheets AE101 and AE212 issued with these responses.

mailto:ryan_henke@steris.com mailto:matt_grummert@steris.com

NO. QUESTION GOVERNMENT RESPONSE

32. Note 8 on AW101 states signage is owner provided.

Please confirm. If owner provided disregard questions

(a), (b) and (c)

a) The specification for signage is not included.

Please provide.

b) On sheet AW601 the following sign types are shown but are not specified for use in the sign schedule

- 99.2, 99.1, 2020.2, 1212.1 &1818.1

- Please advise if these sign types are used.

If so provide an updated sign schedule

c) On sheet AW601 signage schedule the top

Biohazard sign does not show a location.

Please provide

See documents issued with these responses. Signage to be provided, no specification provided. Unused sign types removed. Biohazard sign on sheet AW601 identified.

33. On sheet AW601 signage schedule the top Biohazard sign does not show a location. Please provide

Please Reference 16584-AW601

34. In specification section 09 06 00 Schedule for

Finishes it references Section 08 41 13 Aluminum-

Framed Entrances & Storefront. This specification section was not included in the project documents.

Please advise.

Please Reference 084113 Aluminum Storefronts

35. Confirm if a CSHT is required to make monthly site safety inspections per 01 35 26 – 1.1.B.

Specification section 01 35 26, Section 1.11 Inspections, Paragraph B, states “A Certified Safety Professional

(CSP) with specialized knowledge in construction safety or a certified Construction Safety and Health Technician

(CSHT) shall randomly conduct a monthly site safety inspection. The CSP or CSHT shall be one that is not a part of the immediate site project team. The individual can be a corporate safety professional or independently contracted who is not an immediate member of the construction project site team. The CSP or CSHT will provide their certificate number on the required report for verification as necessary.”

36. Sheet AF101 lists floor type SD-1, which is believed to be static dissipative flooring. The is not a specification requirement for this product. Please provide requirements.

Please Reference 16584-AF101

37. Specification 10 44 13 Fire Extinguisher Cabinets doesn’t identify what size of fire extinguisher the cabinet is to accept. Please provide

Please Reference 104413 Fire Extinguisher Cabinets

38. The drawings do not show a fire extinguisher cabinet at Room H1 - TR? Does the new TR require a fire extinguisher cabinet?

See documents issued with these responses.

NO. QUESTION GOVERNMENT RESPONSE

39. Sheet QH101 & QH411 Equipment Schedule does include the Acquisition Code for the following: Please advise

- A5108 – Sharps

- M2055- Wire Shelving 48” x 18”

- F0860 – Stainless Steel Table

- E2624 – Scope Block Holder

Revise acquisition code (AC) as follows;

A5108 – Sharps: AC – V C

M2055- Wire Shelving 48” x 18”: AC – V V

F0860 – Stainless Steel Table: AC – V V

E2624 – Scope Block Holder: AC- V C R

40. Sheet AF101 does not show any flooring install in

Corridor C43. Confirm no flooring work is required in this area.

See documents issued with these responses.

41. Reference Page 12 of 89 Factor 1, Project

Challenges/Phasing Schedule.

a) The project challenges call for a section on non-conforming material and time. Is the VA looking for a description of what to do when the wrong material is installed and if the contractor falls behind schedule? Please provide an example if this interpretation of non-conforming material and time is incorrect.

b) Please provide a new NTP date for the construction schedule

c) The offerors schedule needs to include project phasing. Please provide the VA’s desired phasing plan.

d) Please provide the number of days the VA will require for RFI’s, Submittals, and other pertinent documents.

A) Example: Project doors are ordered and delivered.

At the time of installation, it is discovered that the doors are damaged but had been delivered six months prior.

What do you do? How will this affect the schedule?

B) Reference Question #23

C) There is not a current phasing plan. It is up to the

Offeror to come up with one. We will review these as part of the decision on which team presents the best phasing plan. Per A/E: There is not much for phasing of the construction. The existing area of the building will be unoccupied during construction, except for areas on First

Level. The rest of the construction is an addition to the facility.

D) Per Specifications Section 01 33 23, Section 1.10 VA

REVIEW OF SUBMITTALS AND RFI’S. Paragraph D states, “VA review period is 21 calendar days for submittals.” Paragraph E states. “VA review period is 21 calendar days for RFI’s.”

42. Reference Page 13 of 89 “Factor 2, Past

Performance”.

a) There are few SDVOSBs under the 236220 –

NAICS code that have performed on projects with a minimum value of $20m. Keeping this requirement in place for past performance would severely limit the competition. Would the VA consider lowering the threshold to

$10m for examples of past performance?

Reference Question #22

NO. QUESTION GOVERNMENT RESPONSE

43. The limitations outlined on page 9 of the solicitation indicate that Volume I, Technical, which comprises both Factors 1 and 2, is limited to twenty (20) pages.

With CPARS reports typically around 3 pages in length per project, would the VA consider not counting CPARS and PPQs against the page limitation?

Correct, Past Performance does not count against page limitations.

44. Detail 04 / AE311 shows an under-slab drainage system. The system is not shown in the civil or plumbing drawings. If required, provide a plumbing drawing showing design including invert elevations and where it connects too.

Under slab drain tile is shown on PL100, designated at

“DT”.

45. Reference Detail 3 & 4 on AD101 - Remove Mineral

Coated Asbestos cement board panels. Ground to 5th floor

a) Please confirm the cement board is hazardous material.

b) Please provide Qty of asbestos cement board to be removed.

a) Please see notes on drawing 3/AD101, 4/AD101 and

1/AD111, for material.

b) Quantity take offs can be determined by reviewing;

Demolition plan AD101 and AD111 for width of area. See 5 & 6/AE201 for height of area.

46. Electrical—Regarding the existing feeders to be removed and replaced shown in the table on sheet ES-

100, several of these feeders have an unknown source location and termination location. These are listed as field verification required. At any point in the bid process will these locations be determined by the architect/ engineer, or will a site visit be available to try and determine these locations to correctly quantify these items?

On site field verification will be required.

47. Electrical—In regard to the existing feeders to be removed and replaced shown in the table on sheet ES-

100, if the unknown locations will not be verified prior to bid submission will there be any form of allowance allowed to cover the unpriceable work?

An allowance for risk is at the discretion of the vendor.

48. Electrical— Can the new lightning protection system that is connecting to the existing system be provided by our chosen vendor or is there a specific vendor the

VA would prefer?

Any licensed lightning protection vendor

49. 01 91 00 - section 3.01 lists a responsibility table.

Within this table it indicates the CxA is responsible for leading the effort to maintain the OPR/BOD documents on behalf of the Owner. This is not mentioned elsewhere in the 01 91 00 specification requirements. Since the project is already designed and commissioning isn't coming onboard until the construction process is it correct that the OPR/BOD requirements do not fall under the CxA's scope?

Follow responsibility matrix as shown in specification section 01 91 00, Section 3.1.

NO. QUESTION GOVERNMENT RESPONSE

50. Are there any anticipated phases for this project that would require areas to be functionally tested prior to full project completion?

No

51. 07 08 00 references functional systems performance testing for building enclosure - can you provide clarification of the extent and components to test for building envelope?

See specification 07 08 00, Section 1.1 Description, Paragraph A states; “The requirements of this Section apply to all sections of Division 07 and Division 08.

All components that are part of Division 07 and Division

08 that are a portion to the building envelope are part of the testing.

52. 07 27 26 - section 3.3 discusses required testing for qualitative air leakage and AABA audit/testing. Is it the intent of the div. 07 contractor to perform/provide all of these? 07 08 00 does mention that the CxA may witness testing as required in division 07/08 so our assumption is that we can witness this testing and that the AABA testing is not under the CxA's requirements to provide. Similar question for other division 07/08 where the specifications call for testing.

See specification 07 80 00, Section 3.1.A. Section states;

“Commissioning of the building envelope systems will require inspection of individual elements of the envelope construction throughout the construction period. The

Contractor shall coordinate with the Commissioning

Agent in accordance with Section 01 91 00 and the

Commissioning plan to schedule envelope inspections as required to support the Commissioning Process.

53. For past performance, projects (maximum of 5 projects) must have a minimum value of $20,000,000 and have been substantially completed within the past

4 years. Can this minimum value be reduced to

$10,000,000?

Reference Question #22

54. Will Procore be acceptable for file sharing, for example, submittals, RFI’s, transmittals, etc.?

Procore is an acceptable file sharing software package to be used for this project.

55. Due to volatility in the market and lead times, please confirm if the government would consider providing a limited Noticed to Proceed to allow for material procurement of long lead items?

Once contract has been awarded and the COR concurs, a

Notice to Proceed can be provided to allow for material procurement of long lead items. However the period of performance starts the day the Notice to Proceed is provided.

56. Please confirm that this project is a competitive

Service-Disabled Veteran-Owned Small Business Set-

Aside project and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA

APPROVED Mentor-Protege partnership under the

SBA/VA Mentor-Protégé program in which the partnership has been approved prior to the bid date.

A. The procurement is a SDVOSB set-aside

B. The submitting vendor must be a SDVOSB registered in VetCert, see VAAR 819.7003

C. The submitting vendor on the SF1442 must be the same vendor identified on all bonds.

D. If the submitting vendor is a JV, a signed copy of the

JV agreement signed by the SBA must be submitted with the proposal that meets all the requirements, see

13 CRF 404.108

NO. QUESTION GOVERNMENT RESPONSE

57. Please confirm the mechanical and electrical systems that are being modified/altered as part of this contract do not directly impact on the OR suite. If the OR

Suite is directly impacted by these systems, please confirm what temporary measures are required to keep this OR suite active.

There are several utilities within the scope of the project

– steam, condensate, and oxygen to name a few – which will require system downtimes for utility tie-ins. The project documents require downtimes to (1) be minimized by prior installation of new systems up to the tie-in locations and (2) be coordinated with the VA prior to shutting down any system. All system outages therefore need to be well coordinated with the VA.

58. In reference to Door Hardware Set #7 indicated below are you looking for touchless wave plates when you state “Hands Free Actuator”?

Will the Hands-Free Actuator’s be in both sides of the doors or only 1 side?

Lastly, do you want the Hands-Free Actuator’s or standard push plates on Door Hardware Sets #1 and

#2 where there are automatic door operators?

Provide “Waive to Open” plates where “touchless” is indicated in specifications. Provide number indicated on plans. For locations where there are actuator(s) (PP) shown on plan. Provide the same actuator type on both sides of door.

At Door C51A, provide wall mounted standard push plate on both sides of door.

At Door C51B. Card Reader to unlock and activate Auto

Door Operator. No push plates.

Remainder of door hardware as specified.

59. EL101-I’m putting a snip below of the room in question. Room H19 shows a 3way dimmer, but there isn’t another 3 way in a different location for this.

How are the 3 lights in H19/H20 being controlled?

This dimmer should not be a three way dimmer. The dimmer in question is controlling the (3) F1 fixtures in

H19/H20. Refer to LD1 sequence for more information on the controls for these (3) fixtures.

NO. QUESTION GOVERNMENT RESPONSE

60. Is there a difference between LD-1 and LD-2?

LD2 should be removed from the sequence of operations schedule. No LD2s are located on floor plans.

61. ES-100 – We will need to know what size of conduits and conductors for Note 4 & 8 coming out of Note 18

(Manhole MH-08) to Building 5.

All known conduits, conductors and cabling between building 24 to building 5 is listed in the schedule on ES-

100. Further field investigation maybe required as all conduits, cabling, and conductors listed are based on existing drawings from 2010 and earlier.

62. ES-100 – Will Note 7 manhole be the same size as new MH-20? If not, please specify size.

Until field verification of all existing cable and wiring can confirm NEC required sizing for new manhole, assuming the same size of new MH-20 is acceptable.

63. ES-100 – What goes underground between MH-20 and Note 7 manhole? Is this concrete encased?

During design IMEG was told there were conductors and control cabling from existing MH-20 to building 24.

However no existing drawings showed any of this information. Field verification will be required to confirm existing conductors and cabling. All conductors being reworked from MH-20 to new MH will be concrete encased.

64. ES-100 – What goes underground between Note 7 manhole and Bldg 24? Is this concrete encased?

See response to #63.

65. ES-100 – Where can we find the duct bank detail drawings?

Until further field verification can confirm sizes for all duct banks, refer to attached PDF showing a 6x2 duct bank for pricing purposes.

NO. QUESTION GOVERNMENT RESPONSE

66. What size data conduit stub-ups are required?

Specifications call for minimum size ¾” and 4-11/16” boxes but Cat6A is being utilized and the ¾” is too small when you get to (4) cables.

Provide 1” as noted in the drawings.

67. Do the data conduits need to be routed and attached to the cable tray or is stubbing above accessible ceiling acceptable?

Data cabling shall be routed and bonded to the cable tray

68. There are paging speakers shown on the drawings but there are no specifications that I could find in the front end.

Spec sections will be provided as part of an addendum.

NO. QUESTION GOVERNMENT RESPONSE

69. Conflicting information on the basket tray on the drawings. Plan sheet T101 show 12”x4” but the

Technology Equipment Schedule on T600 states 18” x 4”. Please advise on what size to use.

Provide 18”x4” per the Equipment Schedule

70. FA101- Are the fire alarm devices with a S a speaker only or does it represent a ceiling speaker/visual? Am

I safe to assume that if the symbol shows a number

(candela) by it then it’s a speaker/visual and if it does not have a number (candela) then it’s a speaker only?

Devices with no number are audio (voice) only. Symbols with a number subscript are audio and visual devices with that number as the candela rating. Devices with a

“CD” subscript requires candela rating to be selected by

NICET certified designer. (Note: NICET certified drawings are required for all submittals)

71. What does the ID represent on this symbol? It’s not on the symbols list.

ID = In Duct detector.

NO. QUESTION GOVERNMENT RESPONSE

72. The following questions relate to page EL101 and deal with lighting control:

A. Rooms H20A and H20B appear to have emergency lighting and feeds from panel

LN4, but they don’t have BCELTS for switching the load when needed. Are these able to share the BCELT from room H26 or do they need their own?

B. Same question for rooms H24 and H25

C. In the corridor just to the right of room H24 is an F8 fixture that has a 2 above it meaning it has an emergency feed. It also is supposed to come out of panel LN4. Is that light fixture supposed to have both power sources going to it?

D. In the upper right on this page is the key notes. Numbers 4 and 5 are identical. Is there a difference between the two?

E. On the far left side of the page just below the

C line on the drawing is a BCELT. There’s already a BCELT in this room at the bottom. Does it need both of them?

F. The outside wallpacks on this page are supposed to be turned on by a photoeye and turned off by a timeclock. Are the photoeye and timeclock existing or new?

A. A separate BCELTS will be required due to fixtures being on different switch legs.

B. A separate BCELTS will be required due to fixtures being on different switch legs.

C. Those fixtures are circuited to a panel that is already on the life safety branch. All lights and controls are on the same circuit(s), and do NOT require BCELTs or ALCR devises to function.

D. This is a duplicated note.

E. Yes, this BCELTS is needed.

F. Photosensor is integral to fixture. Contractor to provide new timeclock/contactor.

73. EL111-on the left side of the page is a 3 way switch.

I don’t see anything else for switching on this floor.

Where is the other side of that switch going to be at?

Second three way switch should be provided at entry from corridor C52.