RFP_30227-00725_Amd_7.pdf
PDF 173 KB Posted
- Solicitation number
- RFP 30227-00725
- Issued by
- Davidson County, Tennessee
About this file
Amendment #7 to RFP #30227-00725
This document is Amendment #7 to a Request for Proposals issued by the State of Tennessee's Administrative Office of the Courts for a Statewide Court Case Management System (CMS) and eFiling Application. The amendment updates the schedule of events for the procurement, which seeks a comprehensive commercial off-the-shelf (COTS) Software as a Service (SaaS) solution to replace disparate case management systems across Tennessee's 95 counties and 32 judicial districts serving approximately 400 Trial Courts. The RFP was originally issued on July 31, 2025, with a response deadline of September 22, 2025 at 4:30 p.m. central time. Key milestones include a Pre-response Conference on August 6, 2025, two rounds of written questions and comments with deadlines of August 15 and September 5, 2025, respectively, with state responses on August 29 and September 12, 2025. Following response submission, the state will open and score cost proposals on September 23, 2025, complete technical evaluations by November 3, 2025, and conduct oral presentations for the top three ranked respondents from November 12–14, 2025. Negotiation is scheduled for November 26 through December 10, 2025, with a Notice of Intent to Award released on December 16, 2025 at 8:00 a.m. The protest period ends December 22, 2025, and the state will send the contract to the selected contractor on December 23, 2025, with a contractor signature deadline of January 31, 2026. The contract term is 120 months with potential 12-month renewal options.
The amendment does not provide pricing terms, set-aside designations, incumbent information, or specific funding amounts. All other terms and conditions of the original RFP remain in full force and effect per the amendment's language. This amendment became effective upon release on December 15, 2025.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP # 30227-00725 – Amendment # 7 Page 1 of 2
STATE OF TENNESSEE
ADMINISTRATIVE OFFICE OF THE COURTS
REQUEST FOR PROPOSALS # 30227-00725
AMENDMENT # 7
FOR STATEWIDE COURT CMS AND eFILING
APPLICATION
DATE: DECEMBER 15, 2025
RFP # 30227-00725 IS AMENDED AS FOLLOWS:
1. This RFP Schedule of Events updates and confirms scheduled RFP dates. Any event, time, or date containing revised or new text is highlighted.
EVENT
TIME
(central time zone)
DATE
1. RFP Issued
July 31, 2025
2. Disability Accommodation Request Deadline 3:30 p.m. August 5, 2025
3. Pre-response Conference 1:00 p.m. August 6, 2025
4. Notice of Intent to Respond Deadline
August 8, 2025
5. Written “Questions & Comments” Deadline 3:30 p.m. August 15, 2025
6. State Response to Written “Questions & Comments”
August 29, 2025
7. Written “Questions & Comments” Deadline (2nd round) 3:30 p.m. September 5, 2025
8. State Response to Written “Questions & Comments” (2nd round)
September 12, 2025
9. Response Deadline 4:30 p.m. September 22, 2025
10. State Opening & Scoring of Cost Proposals
September 23, 2025
11. State Completion of Technical Response Evaluations
November 3, 2025
12. State Schedules Respondent Oral
Presentations (Top 3 Ranked Respondents
Only)
November 4, 2025
13. Respondent Oral Presentations
November 12 – 14, 2025
14. Negotiation
November 26 – December 10,
15. State Notice of Intent to Award Released and RFP Files Opened for Public Inspection
8:00 a.m. December 16, 2025
RFP # 30227-00725 – Amendment # 7 Page 2 of 2
16. End of Protest Period
December 22, 2025
17. State sends contract to Contractor for signature
December 23, 2025
18. Contractor Signature Deadline . January 31, 2026
2. RFP Amendment Effective Date. The revisions set forth herein shall be effective upon release. All other terms and conditions of this RFP not expressly amended herein shall remain in full force and effect.