This document contains a price schedule for a federal construction contract opportunity. The contract involves constructing a new single-story Marine Corps Reserve Center facility, vehicle maintenance facility, and organic storage shed at Camp Fretterd, Maryland to support functions at the Marine Corps Reserve Center. The price schedule outlines various contract line items (CLINs) for the base construction work and five options, including epoxy flooring, overhead coiling doors, paved parking, an organic storage shed, and a compressed air drop. It requests unit pricing for each CLIN and provides budget amounts for future furniture, fixtures, equipment, audiovisual equipment, and handling/administrative rates to coordinate their procurement and installation. Offerors must provide pricing for all CLINs by September 16, 2021. The contract duration is 958 calendar days and the Navy may award any or all options within 365 days of award.

View the file

Other files

File Type Posted
P303 AMENDMENT 0007.pdf PDF
10 51 13.pdf PDF
P303 AMENDMENT 0006.pdf PDF
P303 Amendment 0005.pdf PDF
BLDG-P303-1624797_C_A-002.pdf PDF
P303 Revised Price Schedule 1NOV2021.doc DOC document
BLDG-P303-1624797_C_A-200.pdf PDF
1624807Amendment4SPECS.pdf PDF
08 71 00.pdf PDF
BLDG-P303-1624797_A_A-601 Revised.pdf PDF
BLDG-P303-1624797_A_A-303.pdf PDF
32 31 13.pdf PDF
1624807Amendment4DWG.pdf PDF
1624807Amendment4.docx DOCX document
BLDG-P303-1624797_A_A-631.pdf PDF
07 05 23.pdf PDF
08 71 00C.pdf PDF
Revision Description (10-26-2021).docx DOCX document
P303 Amendment 0004.pdf PDF
P303-AMENDMENT 0003.pdf PDF
FFE FINAL - Building A.pdf PDF
SID Package - Building B.pdf PDF
SID Package - Building A.pdf PDF
BLDG-P303-1624797_A_A-601.pdf PDF
P303 Amendment 0002.pdf PDF
P303 Site Visit Sign-In Sheet.pdf PDF
C-508.pdf PDF
C-501.pdf PDF
E-601.pdf PDF
ST101.pdf PDF
CS400.pdf PDF
26 20 00.pdf PDF
32 15 00.pdf PDF
P303 Amendment 0001.pdf PDF
40 95 00.pdf PDF
CS410.pdf PDF
COMBINED CIVIL DRAWINGS 2 of 2.pdf PDF
COMBINED CIVIL DRAWINGS 1 of 2.pdf PDF
ATTACHMENT E - SAFETY DATA SHEET.docx DOCX document
BLDG A COMBINED DRAWING.pdf PDF
P303 Final Volume 3 Specs.pdf PDF
1624807DWGBLDGC1of1.pdf PDF
SF1442 - N40080-21-R-6986.pdf PDF
ATTACHMENT D - CONSTRUCTION EXPERIENCE PROJECT DATA SHEET.docx DOCX document
Visitor Access Request List.xlsx XLSX spreadsheet
Small Business Subcontracting Plan.doc DOC document
P303 Final Volume 1 Specs.pdf PDF
BLDG B Combined Drawings.pdf PDF
SITE-VISIT PARKING AREA.png PNG image
ATTACHMENT F - SMALL BUSINESS PAST PERFORMANCE.docx DOCX document
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

N40080-21-R-6986 16 September 2021

P-303, MARINE CORPS RESERVE CENTER

CAMP FRETTERD, REISTERSTOWN, MARYLAND

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used with the contract.

Provide the Contract Line Item Number (CLIN) lump sum price for the following Items:

CLIN 0001 – BASE PRICE: P303 – Price includes the following:

SUB-CLIN
DESCRIPTION
TOTAL PRICE FOR SUB-CLIN
0001AA
Price for the entire work for constructing new Marine Corps Reserve Center and cybersecurity (BLDG – A), complete in accordance with the drawings and specifications but not including the work indicated or specified to be provided under any other Bid Item.
0001AB
Price for is entire work associated with constructing new Vehicle Maintenance Facility, and cybersecurity (BLDG – B)., complete in accordance with the drawings and specifications but not including the work indicated or specified to be provided under any other Bid Item.
0001AC
Price for is entire work associated with SITE PLAN, which includes all site and utilities, security structures, fire protection water storage and pump enclosure in accordance with the plans and specifications, but excluding work described in or specified to be provided under any of the other bid items or options.
$________________

TOTAL PRICE FOR CLIN 0001: (0001AA-0001AC)

CLIN 0002 – OPTION 1: Price is for Epoxy flooring in Drill Hall as designed on Drawing A3/A_I-104. Epoxy flooring color and material shall be as scheduled in the finish legend plans and specifications, in accordance with the plans and specifications.

TOTAL PRICE FOR CLIN 0002

CLIN 0003 – OPTION 2: Price is to use overhead coiling doors; this option will add folding doors at vehicle maintenance bays, in accordance with the plans and specifications.

TOTAL PRICE FOR CLIN 0003

CLIN 0004 – OPTION 3: Price is to change all tactical parking from gravel (or similar) to pavement (concrete/asphalt). Concrete curbs and gutters to remain.

TOTAL PRICE FOR CLIN 0004

CLIN 0005 – OPTION 4: Price is work associated with constructing new Organic Storage Shed (BLDG – C).

TOTAL PRICE FOR CLIN 0005

CLIN 0006 – OPTION 5: Price is to identify the Lubrication/Fluid Distribution System. Add a new compressed air drop at column line C along the East wall in its place. The Lubrication /Fluid Distribution System is shown on drawings B_P-102, B_P-301 and B_P-402.

TOTAL PRICE FOR CLIN 0006

TOTAL PRICE FOR CLINs 0001-0006

CLIN 0007 – PLANNED MODIFICATION 1: FF&E for new Marine Corps Reserve Center, Base Price and the establishment of a Handling & Administrative Rate (HAR) for any possible future work associated with FF&E / Collateral Equipment.

(1) FF&E COLLATERAL EQUIPMENT

(BUDGET ONLY)

$641,527

(2) HANDLING & ADMINISTRATIVE

RATE (HAR - NTE 5%)

% X $641,527 = _________

TOTAL FF&E AMOUNT:

(1) + (2) = (3)

CLIN 0008 – PLANNED MODIFICATION 2: FF&E for new Vehicle Maintenance Facility, Base Price and the establishment of a Handling & Administrative Rate (HAR) for any possible future work associated with FF&E / Collateral Equipment.

(1) FF&E COLLATERAL EQUIPMENT

$73,532

% X $73,532 = _________

TOTAL FF&E AMOUNT:

CLIN 0009 – PLANNED MODIFICATION 3: Audio/Visual (A/V) for new Marine Corps Reserve Center Base Price and the establishment of a Handling & Administrative Rate (HAR) for any possible future work associated with A/V / Collateral Equipment.

(1) A/V COLLATERAL EQUIPMENT

$82,374

% X $82,374 = _________

TOTAL A/V AMOUNT:

CLIN 0010 – PLANNED MODIFICATION 4: Audio/Visual (A/V) for new Vehicle Maintenance Facility Base Price and the establishment of a Handling & Administrative Rate (HAR) for any possible future work associated with A/V / Collateral Equipment.

(1) A/V COLLATERAL EQUIPMENT

$26,956

RATE (HAR - NTE 5%) % X $26,956 = _________

TOTAL A/V AMOUNT:

NOTES:

1. The Offeror shall provide a price for all CLINs on the Price Schedule. The Government will evaluate offers based on the total evaluated price, which is the sum of CLINs 0001-0006

2. The lump sum price above shall be deemed to include all costs required for the specified work, in accordance with the drawings and specifications, including all labor, materials, equipment, tools, management, supervision, and related items.

3. A firm fixed proposed price is required for CLINs 0001-0006. No provision is made for economic price adjustment.

4. Failure to enter a price for any of the CLINs will result in the proposal being rejected as unacceptable.

5. Options will be evaluated in accordance with FAR 52.217-5 Evaluation of Options. Evaluation of the Options will not obligate the Government to execute any or all of the Options.

6. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices, which are significantly overstated for other work.

7. The Offeror’s price is valid for 90 days from the receipt of proposals.

8. Total Contract duration is 958 calendar days after contract award.

9. The Government reserves the unilateral right to award any and/or all options, Options 1-5 (CLIN’s 0002-0006), to the Contractor at the proposed price at time of award or within 365 calendar days after the contract award. Should the Government choose to exercise any and/or all options, the contract duration for construction will remain the same.

10. If the options are exercised after award, additional bonding and consent of surety will be required. Consequently, the Performance Bond shall reflect 100 percent of the aggregate amount of all items.

11. Contract Clause 52.211-18, Variation in Estimated Quantity, will be included in the contract.

FF&E NOTES:

These notes apply to Planned Modification, CLINs 0007, 0008, 0009 AND 0010.

1. The total estimated budget amount for FF&E and A/V has been identified, to provide offerors with the projected magnitude of effort for FF&E AND A/V. The FF&E AND A/V Budget Amount is only an estimated amount. The contractor shall determine the final budget amount for the FF&E AND A/V, during the post-award design phase of the FF&E AND A/V.

2. Offerors shall propose a Handling and Administration Rate (HAR) for the FF&E AND A/V not to exceed (NTE) 5%. The HAR fee should account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E AND A/V. The proposed HAR percentage will be incorporated into the contract/task order award and will not be adjusted regardless of fluctuations from the estimated budget amount for FF&E AND A/V. The proposed HAR is a fixed rate. The dollar amount of the HAR will change based on the actual, final amount for the FF&E AND A/V determined during the post-award design phase of the FF&E AND A/V.

3. If awarded, line item (1) under item 0007, 0008, 0009 and 0010 will be funded separately after completion of the FF&E AND A/V design review by the Government, acceptance of FF&E AND A/V package by the Government, and receipt of appropriate funding by the Government. The design effort and the development of the FF&E AND A/V packages are performed by the Contractor under the Base Bid.

4. The Government is not obligated to award the FF&E AND A/V Option. Should the Government choose to award the FF&E AND A/V; the Option will be awarded as a negotiated Modification to the contract. The contractor’s proposed HAR will be applied to all vendor/supplier costs for the FF&E AND A/V.

5. It is the contractor’s responsibility to purchase, deliver, and install the FF&E AND A/V without impacting the overall completion date of the project. The contractor’s schedule should assume the award of the FF&E AND A/V as a modification. No schedule extensions will be granted.

Name & Address of Firm Submitting Offer:

Signature: ___________________________________

Phone: ______________________________________

Email: ______________________________________

Fax: ________________________________________

ACKNOWLEDGEMENT OF AMENDMENT(S):___________________________