Drawing A0.4

View the file

Other files for this federal contract opportunity

Other files attached to Mammoth Hotel Seismic Stabilization Phase 1, newest first.
File Type Posted
13744_SSK-12.pdf PDF
P16PS00611_Amendment_5.pdf PDF
AF2.2_-_SECOND_FLOOR_FINISH_PLAN.pdf PDF
ASK_007_thru_011.pdf PDF
MAMMOTH_SSK_FULL_SET_STRUCT.pdf PDF
060310_-_WOOD_CLEANING.pdf PDF
060312_SF_-_HISTORIC_WOOD_REPAIR.pdf PDF
230900_Instrumentation_and_Controls.pdf PDF
093013_sf_-_Ceramic_Tiling.pdf PDF
P16PS00611_Amendment_4.pdf PDF
P16PS00611_Amendment_3.pdf PDF
ASK_001_thru_006.pdf PDF
072100_SF_-_THERMAL_INSULATION.pdf PDF
Fire_Alarm_Revision_Sheets_FA1.0 _FA2.1 _FA3.1 _FA3.2 _FA4.0 _FA7.0.pdf PDF
Xanterra_-_Mammoth_Hotel_Limited_Hazardous_Materials_Inspection_Report.pdf PDF
Civil_Revisions_C1.0 _C1.1 _C1.2 _C1.3.pdf PDF
Amendment_2_P16PS00611.pdf PDF
Amendment_1_P16PS00611.pdf PDF
Attachment_1_Specifications_VOL_2.pdf PDF
Attachment_2_-_07_Drawings_M1.0_-_P4.0.pdf PDF
Attachment_2_-_09_Drawings_FP1.0_-_FP3.3.pdf PDF
Attachment_2_-_03_Drawings_AD2.0_-_A9.13.pdf PDF
Attachment_1_Specifications_VOL_1.pdf PDF
Attachment_3_Geotechnical_Report.pdf PDF
Attachment_2_-_04_Drawings_FS0.0_-_FS7.1.pdf PDF
Attachment_2_-_10_Drawings_FA1.0_-_FA7.0.pdf PDF
Attachment_5_General_Decision_Number_WY13.docx DOCX document
Attachment_2_-_06_Drawings_SD2.2_-_S5.7.pdf PDF
Attachment_4_Historic_Structures_Report.pdf PDF
P16PS00611_YELL_189105.pdf PDF
Attachment_2_-_02_Drawings_C1.0_-C9.7.pdf PDF
Attachment_2_-_01_Drawings_Cover_Sheet_-A0.5.pdf PDF
Attachment_2_-_08_Drawings_E1.0_-_E5.3.pdf PDF
Attachment_6_Proposal_Submission_Package.zip ZIP file
Attachment_2_-_05_Drawings_S0.1_-_SD2.1.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UP

UPUP

DN

6 72

D

B

A

3 4 5

C

E

F

PHASE II

PHASE I

PHASE II

PHASE I

MAMMOTH HOT

SPRINGS HOTEL

| PHASE 2 |

6 72

D

B

A

3 4 5

C

PHASE 2

PHASE 1

PHASE 2

PHASE 1

MAMMOTH HOT

SPRINGS HOTEL

| PHASE 2 |

PROVIDE TEMPORARY

BARRIER FROM JUNE 19,

2017 TO PROJECT

COMPLETION.

6 72

D

B

A

3 4 5

C

PHASE II

PHASE I

PHASE II

PHASE I

MAMMOTH HOT

SPRINGS HOTEL

| PHASE 2 |

LEGEND

DASHED LINE INDICATES PROJECT BOUNDARY OF

MAMMOTH HOTEL REHABILITATION PHASE I.

DASHED LINE INDICATES APPROXIMATE BOUNDARY OF

MAMMOTH HOTEL REHABILITATION PHASE II.

BENEFICIAL OCCUPANCY 19 JUNE, 2017 WITH SHARED

CONTRACTOR / CONCESSIONAIRE ACCESS UNTIL PROJECT

COMPLETION.

AREAS TO REACH SUBSTANTIAL COMPLETION WITH TURN

OVER TO GOVERNMENT FOR FULL USE NO LATER THAN 1

SEPTEMBER, 2017

6 72

D

B

A

3 4 5

C

E

F

A R C H I T E C T U R E

I N T E R I O R S

H I S T O R I C www.aearchitects.com

2 2 2 N O R T H H I G G I N S

M I S S O U L A, M T 5 9 8 0 2

P H. 4 0 6 . 7 2 1 . 5 6 4 3

F A X. 4 0 6 . 7 2 1 . 1 8 8 7

6 0 8 N O R T H 2 9 T H

B I L L I N G S, M T 5 9 1 0 1

P H. 4 0 6 . 2 4 8 . 2 6 3 3

F A X. 4 0 6 . 2 4 8 . 2 4 2 7

4 2 8 E A S T M E N D E N H A L L

B O Z E M A N, M T 5 9 7 1 5

P H. 4 0 6 . 4 5 3 . 7 3 1 0

PROJECT NO.

NPS PROJ NO.

REVISIONS

DRAWING NO.

PKG

NO.

PKG1

PKG2

PKG3

SHEET

OF

DESIGNED:

CADD:

TECH REVIEW:

DATE

TITLE OF SHEETDRAWING NO.

0 1 2 3 4 5 6 7 8 9 10 inches

189105

/1

/2

:4

:4

P

M

15021.00

6.10.2016

COMPLETION & ACCESS

MAMMOTH HOTEL SEISMIC

STABILIZATION & REHABILITATION

- PHASE I

YELLOWSTONE NATIONAL PARK, WYOMING

Checker

MM

DJ

6.10.2016

A0.4

C O

N

ST

R U

C T I O

N D

O C

U M

E N

T S

: 1/16" = 1'-0"A0.4A0.4

9 FIRST FLOOR PLAN

: 1/16" = 1'-0"A0.4A0.4

11 SECOND FLOOR PLAN

: 1/16" = 1'-0"A0.4A0.4

13 BASEMENT PLAN

NOTE

SEE SHEET A0.3 FOR EXTERIOR

STAGING AND ACCESS REQUIRMENTS.

NORTH NORTH

: 1/16" = 1'-0"A0.4A4.1

6 COMPLETION AND ACCESS ROOF PLAN

NORTH

NORTH

File details come from the government source that posted it. Updated .