Amend 1 - Attachment 1 - FOVA 174962

View the file

Other files

File Type Posted
0_-_Amend_6_-_P15PS00118_-_FOVA_174962_SF30.pdf PDF
2_-_Amend__6_FOVA_Section_028213-_ASBESTOS_spec_revised_FINAL.pdf PDF
1_-_Amend_6__FOVA_Section_02_8319__LEAD-BASED_PAINT_spec_FINAL.pdf PDF
3_-_Amend_6_FOVA_174962_Q-A_responses.pdf PDF
0_-_Amend_5_-_P15PS00118_-_FOVA_174962_SF30.pdf PDF
4_-_Amend_5_FOVA_Questions.pdf PDF
3_-_Amend_5_FOVA_Site_Visit_Sign_in_Sheets_3-25.pdf PDF
2_-_ACM_Quantity_Estimates_FOVA_174962_.pdf PDF
1_-_Final_ACM_HazMat_SurveySummary_FOVA_041414KMA.PDF PDF
2__-_Amendment_4_FOVA_Questions.pdf PDF
0_-_Amend_4_-_P15PS00118_-_FOVA_174962_SF30.pdf PDF
1_-_Amendment_4_Attachment_1_FOVA_174962_.pdf PDF
2__-_Amendment_3_FOVA_Questions_3-13-15.pdf PDF
1_-_Amend_3_Attachment_1_FOVA__174962.pdf PDF
Past_Performance_Questionnaire_x_(1).doc DOC document
0_-_Amend_3_-_P15PS00118_-_FOVA_174962_SF30.pdf PDF
3_-Amendment_3_FOVA_Questions_3-16-15.pdf PDF
3_-_Amend_2_Attachment_1_FOVA_174962_pre_bid_list_of_attendees.pdf PDF
6_-Sustainability_Checklist_LEED_2009_FOVA_9-24-14.pdf PDF
4_-_Amend_2_Attachment_2_FOVA_174962.pdf PDF
1_-_Amend_1_-_P15PS00118_-_FOVA_174962_SF30.pdf PDF
2_-_Amend_2_Revised_SF_1442.pdf PDF
0_-_Amend_2_-_P15PS00118_-_FOVA_174962_SF30.pdf PDF
5_-_Amend_2_FOVA_Questions_3-10-15.pdf PDF
Amend_1_-_Revised_Contract_Clauses_-_FOVA_174962.pdf PDF
Amend_1_-_Attachment_2_-_SECTION_01_27_00_Phase_1.pdf PDF
Drawings_No._389_126929.pdf PDF
Drawing_No._389_119939.pdf PDF
Hazmat_Survey_Compiled_-_FOVA_987-404.pdf PDF
FOVA__Proposal_Submission_Package_x.pdf PDF
Drawing_No._389_126282.pdf PDF
Project_Specs_Bldgs_987-404_for_USFS_Vol_2.pdf PDF
Supplemental_993_pics.pdf PDF
Drawing_No._389_105548_vol_1.pdf PDF
FOVA_Request_for_Proposal.pdf PDF
FOVA_Lead_Base_Paint_and_AHERA_Inspection__Amend_2_Clarification_to_report_questions.pdf PDF
Drawing_No._389_105548_vol_2.pdf PDF
Project_Specs_Rehabilitate_Utilities_and_Infrastructure_in_East_and_South_Vancouver_Barracks.pdf PDF
Drawing_No._389_80038A.pdf PDF
Wage_Rates_WA_-_2-12-2015.pdf PDF
Project_Specs_Bldgs_987-404_for_USFS_Vol_1.pdf PDF
Supplemental_989_pics.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment No. 1 25 February 2015

FOVA 174962, 175150, 174966, 194838, 194841

Rehabilitate Buildings and Phase 1 Utilities

Upload Drawings

1. Drawing No. 389/ 119939

2. Drawing No. 389 / 126929

Request for Proposal is replaced in its entirety

UPDATES TO CONTRSCT CLAUSES –

1. Section H, page 16, Delete Special Clause 1: Options for Additional Services

2. Section L. page 106. Factor 3 is broken down into four (4) areas to provide narrative.

3. Section L. page 106. “e. Price” moved to Volume II Business and Price Proposal, under No. 4 Contract Price Schedule.

4. Section L, page 107, Delete Safety, hazardous materials and addition past Performance

FOVA 174962 & 175150:

1. Specification Section 012700, 3.1, E.1 – Change to:

“This item consists of removal of pre-existing paint, paint splatters, and coatings, existing at the time of contract award, from stone surfaces and sills.”

2. Specification Section 011100, 1.2, B. – Change 2. to 3. and add the following:

“2. The Work includes the exterior rehabilitation of Buildings 989 and 993 per the 9 sheet drawing set and photos provided in this package for each separate building. Both buildings are historic former U.S. Army barracks and have the same footprint and construction as Building

987. The appropriate specification paragraphs and drawing notes from Rehabilitation of Buildings 987 and 404 for US Forest Service also apply to Buildings 989 and 993. Only the exterior of Buildings 989 and 993 are being rehabilitated under this contract.”

3. Specification Section 012700, 3.1 – Change the following:

O. Contract Line Item No. 0015 – change to O. Contract Line Item No. 0019 P. Contract Line Item No. 0016 – change to P. Contract Line Item No. 0020 Q. Contract Line Item No. 0017 – change to Q. Contract Line Item No. 0021 R. Contract Line Item No. 0018 – change to R. Contract Line Item No. 0022 S. Contract Line Item No. 0019 – change to S. Contract Line Item No. 0023 T. Contract Line Item No. 0020 – change to T. Contract Line Item No. 0024 U. Contract Line Item No. 0021 – change to U. Contract Line Item No. 0025

V. Contract Line Item No. 0022 – change to U. Contract Line Item No. 0026 W. Contract Line Item No. 0023 – change to W. Contract Line Item No. 0027 X. Contract Line Item No. 0024 – change to X. Contract Line Item No. 0028 Y. Contract Line Item No. 0025 – change to Y. Contract Line Item No. 0029 Z. Contract Line Item No. 0026 – change to Z. Contract Line Item No. 0030

FOVA 174966 Upgrade Utilities Phase 1:

1. Specification Section 011100, 1.4,C.,1 – Delete. Rehabilitation of Building 987 and 404 are included in this contract.

2. Specification Section 011100, 1.10, B – Change Appendix K to Appendix A.

3. Specification Section 012700 – Delete in entirety and add attached revision.

FOVA 194838 - OPTIONS Rehabilitate Building 989 Exterior:

1. Bid Schedule Description of Contract Line Items: Use the following descriptions for

Contract Line Items 31 through 37.

N. Contract Line Item No. 0031: Rehabilitation of Building 989.

1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation.

2. Payment will be made at the contract lump sum price.

O. Contract Line Item No. 0032: Repairs to Exterior Wood Cladding at Building 989.

1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim.

2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs.

P. Contract Line Item No. 0033: Replacement of Deteriorated Wood Framing at Building 989.

1. This item consists of replacement of deteriorated wood framing that is uncovered during construction.

2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement.

Q. Contract Line Item No. 0034: Paint Removal at Stone Masonry at Building 989.

1. This item consists of removal of paint, paint splatters, and coatings, existing at the time of contract award, from stone surfaces and sills.

2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal.

R. Contract Line Item No. 0035: Repointing of Stone Masonry at Building 989.

1. This item consists of repointing of stone masonry at Building 989.

2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing.

S. Contract Line Item No. 0036: Metal Gutter Liner Replacement at Building 989.

1. This item consists of replacement of the existing sheet metal gutter liner at Building 989, where the existing is severely deteriorated.

2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement.

T. Contract Line Item No. 0037: Metal Gutter Liner Patching at Building 989.

1. This item consists of patching the existing sheet metal gutter liner.

unit price per square foot of patching.

FOVA 194841 - OPTIONS Rehabilitate Building 993 Exterior

1. Bid Schedule Description of Contract Line Items: Use the following descriptions for

Contract Line Items 38 through 44.

U. Contract Line Item No. 0038: Rehabilitation of Building 993.

1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation.

2. Payment will be made at the contract lump sum price.

V. Contract Line Item No. 0039: Repairs to Exterior Wood Cladding at Building 993.

1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim.

2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs.

W. Contract Line Item No. 0040: Replacement of Deteriorated Wood Framing at Building 993.

1. This item consists of replacement of deteriorated wood framing that is uncovered during construction.

2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement.

X. Contract Line Item No. 0041: Paint Removal at Stone Masonry at Building 993.

1. This item consists of removal of paint, paint splatters, and coatings, existing at the time of contract award, from stone surfaces and sills.

unit price per square foot of paint removal.

Y. Contract Line Item No. 0042: Repointing of Stone Masonry at Building 993.

1. This item consists of repointing of stone masonry at Building 993.

2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing.

Z. Contract Line Item No. 0043: Metal Gutter Liner Replacement at Building 993.

1. This item consists of replacement of the existing sheet metal gutter liner at Building 993, where the existing is severely deteriorated.

2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement.

AA. Contract Line Item No. 0044: Metal Gutter Liner Patching at Building 993.

1. This item consists of patching the existing sheet metal gutter liner.

unit price per square foot of patching.

1. Bid Schedule Description of Contract Line Items: Use the following descriptions for Contract Line Items 31 through 37.
N. Contract Line Item No. 0031: Rehabilitation of Building 989.
1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation.
2. Payment will be made at the contract lump sum price.
O. Contract Line Item No. 0032: Repairs to Exterior Wood Cladding at Building 989.
1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs.
P. Contract Line Item No. 0033: Replacement of Deteriorated Wood Framing at Building 989.
1. This item consists of replacement of deteriorated wood framing that is uncovered during construction.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement.
Q. Contract Line Item No. 0034: Paint Removal at Stone Masonry at Building 989.
1. This item consists of removal of paint, paint splatters, and coatings, existing at the time of contract award, from stone surfaces and sills.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal.
R. Contract Line Item No. 0035: Repointing of Stone Masonry at Building 989.
1. This item consists of repointing of stone masonry at Building 989.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing.
S. Contract Line Item No. 0036: Metal Gutter Liner Replacement at Building 989.
1. This item consists of replacement of the existing sheet metal gutter liner at Building 989, where the existing is severely deteriorated.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement.
T. Contract Line Item No. 0037: Metal Gutter Liner Patching at Building 989.
1. This item consists of patching the existing sheet metal gutter liner.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of patching.
1. Bid Schedule Description of Contract Line Items: Use the following descriptions for Contract Line Items 38 through 44.
U. Contract Line Item No. 0038: Rehabilitation of Building 993.
1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation.
2. Payment will be made at the contract lump sum price.
V. Contract Line Item No. 0039: Repairs to Exterior Wood Cladding at Building 993.
1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs.
W. Contract Line Item No. 0040: Replacement of Deteriorated Wood Framing at Building 993.
1. This item consists of replacement of deteriorated wood framing that is uncovered during construction.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement.
X. Contract Line Item No. 0041: Paint Removal at Stone Masonry at Building 993.
1. This item consists of removal of paint, paint splatters, and coatings, existing at the time of contract award, from stone surfaces and sills.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal.
Y. Contract Line Item No. 0042: Repointing of Stone Masonry at Building 993.
1. This item consists of repointing of stone masonry at Building 993.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing.
Z. Contract Line Item No. 0043: Metal Gutter Liner Replacement at Building 993.
1. This item consists of replacement of the existing sheet metal gutter liner at Building 993, where the existing is severely deteriorated.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement.
AA. Contract Line Item No. 0044: Metal Gutter Liner Patching at Building 993.
1. This item consists of patching the existing sheet metal gutter liner.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of patching.