FOVA 174962, 175150, 174966, 194838, 194841
Updates from Amendment 1 Attachment 1
FOVA 174962 & 175150:
1. Specification Section 012700, 3.1, A.1. – Add the following sentence to the end of the paragraph:
“This item is exclusive of Contract Line Items C-T which are priced separately. Note: Contract Line Item I, Patching of Plaster Walls and Ceilings at Building 987, statement the item does not include the patching required to complete work shown in the Drawings, which shall be included in Contract Line Item 1 still applies.”
2. Specification Section 012700, 3.1, B.1. . – Add the following sentence to the end of the paragraph:
“This item is exclusive of Contract Line Items L-M which are priced separately.
1.3. Specification Section 012700, 3.1, E.1 – Change to:
“This item consists of removal of pre-existing paint, paint splatters, and coatings, and biological growth existing at the time of contract award, from stone surfaces and sills.”
2.4. Specification Section 011100, 1.2, B. – Change 2. to 3. and add the following:
“2. The Work includes the exterior rehabilitation of Buildings 989 and 993 per the 9 sheet drawing set and photos provided in this package for each separate building. Both buildings are historic former U.S. Army barracks and have the same footprint and construction as Building
987. The appropriate specification paragraphs and drawing notes from Rehabilitation of Buildings 987 and 404 for US Forest Service also apply to Buildings 989 and 993. Only the exterior of Buildings 989 and 993 are being rehabilitated under this contract and the work primarily consists of exterior painting, repairs of siding, gutter repair and roof repair. No accessibility work is being completed under this contract”
3.5. Specification Section 012700, 3.1 – Change the following:
O. Contract Line Item No. 0015 – change to O. Contract Line Item No. 0019 P. Contract Line Item No. 0016 – change to P. Contract Line Item No. 0020 Q. Contract Line Item No. 0017 – change to Q. Contract Line Item No. 0021 R. Contract Line Item No. 0018 – change to R. Contract Line Item No. 0022 S. Contract Line Item No. 0019 – change to S. Contract Line Item No. 0023 T. Contract Line Item No. 0020 – change to T. Contract Line Item No. 0024 U. Contract Line Item No. 0021 – change to U. Contract Line Item No. 0025 V. Contract Line Item No. 0022 – change to U. Contract Line Item No. 0026 W. Contract Line Item No. 0023 – change to W. Contract Line Item No. 0027 X. Contract Line Item No. 0024 – change to X. Contract Line Item No. 0028 Y. Contract Line Item No. 0025 – change to Y. Contract Line Item No. 0029 Z. Contract Line Item No. 0026 – change to Z. Contract Line Item No. 0030
FOVA 174966 Upgrade Utilities Phase 1:
1. Specification Section 011100, 1.4,C.,1 – Delete. Note: Rehabilitation of Building 987 and 404 are included in this contract.
2. Specification Section 011100, 1.10, B – Change Appendix K to Appendix A.
Formatted: Normal, Indent: Left: 0.25", Hanging: 0.5", No bullets or numbering
Formatted: Indent: Left: 0.25", No bullets or numbering
3. Specification Section 012700 – Delete in entirety and add attached revision.
FOVA 194838 - OPTIONS Rehabilitate Building 989 Exterior
1. Bid Schedule Description of Contract Line Items: Use the following descriptions for
Contract Line Items 31 through 37.
N. Contract Line Item No. 0031: Rehabilitation of Building 989 Exterior.
1. This item consists of exterior rehabilitation as shown on the 989 drawings. No accessibility work is being completed under this contract. This item is exclusive of contract line items O-T which are priced separately.
1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation.
2. Payment will be made at the contract lump sum price.
O. Contract Line Item No. 0032: Repairs to Exterior Wood Cladding at Building 989.
1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs.
P. Contract Line Item No. 0033: Replacement of Deteriorated Wood Framing at Building 989.
1. This item consists of replacement of deteriorated wood framing that is uncovered during construction.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement.
Q. Contract Line Item No. 0034: Paint Removal at Stone Masonry at Building 989.
1. This item consists of removal of paint, paint splatters, and coatings, and biological growth existing at the time of contract award, from stone surfaces and sills.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal.
R. Contract Line Item No. 0035: Repointing of Stone Masonry at Building 989.
1. This item consists of repointing of stone masonry at Building 989.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing.
S. Contract Line Item No. 0036: Metal Gutter Liner Replacement at Building 989.
1. This item consists of replacement of the existing sheet metal gutter liner at Building 989, where the existing is severely deteriorated.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement.
T. Contract Line Item No. 0037: Metal Gutter Liner Patching at Building 989.
1. This item consists of patching the existing sheet metal gutter liner.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of patching.
FOVA 194841 - OPTIONS Rehabilitate Building 993 Exterior
1. Bid Schedule Description of Contract Line Items: Use the following descriptions for
Contract Line Items 38 through 44.
U. Contract Line Item No. 0038: Rehabilitation of Building 993 Exterior.
1. This item consists of exterior rehabilitation as shown on the 993 drawings. No accessibility work is being completed under this contract. This item is exclusive of contract line items V-AA which are priced separately.
1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation.
2. Payment will be made at the contract lump sum price.
V. Contract Line Item No. 0039: Repairs to Exterior Wood Cladding at Building 993.
1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs.
W. Contract Line Item No. 0040: Replacement of Deteriorated Wood Framing at Building 993.
1. This item consists of replacement of deteriorated wood framing that is uncovered during construction.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement.
X. Contract Line Item No. 0041: Paint Removal at Stone Masonry at Building 993.
1. This item consists of removal of paint, paint splatters, and coatings, and biological growth existing at the time of contract award, from stone surfaces and sills.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal.
Y. Contract Line Item No. 0042: Repointing of Stone Masonry at Building 993.
1. This item consists of repointing of stone masonry at Building 993.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing.
Z. Contract Line Item No. 0043: Metal Gutter Liner Replacement at Building 993.
1. This item consists of replacement of the existing sheet metal gutter liner at Building 993, where the existing is severely deteriorated.
2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement.
AA. Contract Line Item No. 0044: Metal Gutter Liner Patching at Building 993.
1. This item consists of patching the existing sheet metal gutter liner.
2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of patching.
| 1. Bid Schedule Description of Contract Line Items: Use the following descriptions for Contract Line Items 31 through 37. |
| N. Contract Line Item No. 0031: Rehabilitation of Building 989 Exterior. |
| 1. This item consists of exterior rehabilitation as shown on the 989 drawings. No accessibility work is being completed under this contract. This item is exclusive of contract line items O-T which are priced separately. |
| 1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation. |
| 2. Payment will be made at the contract lump sum price. |
| O. Contract Line Item No. 0032: Repairs to Exterior Wood Cladding at Building 989. |
| 1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim. |
| 2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs. |
| P. Contract Line Item No. 0033: Replacement of Deteriorated Wood Framing at Building 989. |
| 1. This item consists of replacement of deteriorated wood framing that is uncovered during construction. |
| 2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement. |
| Q. Contract Line Item No. 0034: Paint Removal at Stone Masonry at Building 989. |
| 1. This item consists of removal of paint, paint splatters, and coatings, and biological growth existing at the time of contract award, from stone surfaces and sills. |
| 2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal. |
| R. Contract Line Item No. 0035: Repointing of Stone Masonry at Building 989. |
| 1. This item consists of repointing of stone masonry at Building 989. |
| 2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing. |
| S. Contract Line Item No. 0036: Metal Gutter Liner Replacement at Building 989. |
| 1. This item consists of replacement of the existing sheet metal gutter liner at Building 989, where the existing is severely deteriorated. |
| 2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement. |
| T. Contract Line Item No. 0037: Metal Gutter Liner Patching at Building 989. |
| 1. This item consists of patching the existing sheet metal gutter liner. |
| 2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of patching. |
| 1. Bid Schedule Description of Contract Line Items: Use the following descriptions for Contract Line Items 38 through 44. |
| U. Contract Line Item No. 0038: Rehabilitation of Building 993 Exterior. |
| 1. This item consists of exterior rehabilitation as shown on the 993 drawings. No accessibility work is being completed under this contract. This item is exclusive of contract line items V-AA which are priced separately. |
| 1. This item consists of architectural, structural, and accessibility improvements, exterior upgrades, for exterior rehabilitation. |
| 2. Payment will be made at the contract lump sum price. |
| V. Contract Line Item No. 0039: Repairs to Exterior Wood Cladding at Building 993. |
| 1. This item consists of repairs to exterior wood cladding, including siding, fascia, and trim. |
| 2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of cladding repairs. |
| W. Contract Line Item No. 0040: Replacement of Deteriorated Wood Framing at Building 993. |
| 1. This item consists of replacement of deteriorated wood framing that is uncovered during construction. |
| 2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of framing replacement. |
| X. Contract Line Item No. 0041: Paint Removal at Stone Masonry at Building 993. |
| 1. This item consists of removal of paint, paint splatters, and coatings, and biological growth existing at the time of contract award, from stone surfaces and sills. |
| 2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of paint removal. |
| Y. Contract Line Item No. 0042: Repointing of Stone Masonry at Building 993. |
| 1. This item consists of repointing of stone masonry at Building 993. |
| 2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of repointing. |
| Z. Contract Line Item No. 0043: Metal Gutter Liner Replacement at Building 993. |
| 1. This item consists of replacement of the existing sheet metal gutter liner at Building 993, where the existing is severely deteriorated. |
| 2. Measurement will be made on a lineal foot basis. Payment will be made at the contract unit price per lineal foot of gutter liner replacement. |
| AA. Contract Line Item No. 0044: Metal Gutter Liner Patching at Building 993. |
| 1. This item consists of patching the existing sheet metal gutter liner. |
| 2. Measurement will be made on a square foot basis. Payment will be made at the contract unit price per square foot of patching. |