[O]_611_Collins_Street_Site_Exhibit_7-2-25.pdf

PDF 347 KB Posted

Attached to
Collins Street Complete Street - Phase I
Solicitation number
25-014EN-FC-IFB
Issued by
Hillsborough County, Florida

About this file

This document is a site utilization plan for the Collins Street Phase I Improvements project by the City of Plant City's Engineering Department, located in Plant City, Florida. The document details the use of a ¾ acre property at 611 S. Collins Street, owned by the Community Redevelopment Agency (CRA), which will be made available to the contractor for project-related purposes including office space, parking, equipment and material storage during the project term. The site is restricted from storing contaminated or potentially contaminated soils and groundwater, with specific requirements for temporary facilities, including connecting office trailers to city water and sewer, installing a 6' high chain link fence with two 12' gates, and maintaining secondary fuel containment.

The document outlines strict conditions of use for the contractor, which include daily inspections for equipment leaks, immediate reporting and cleanup of any fluid leaks, weekly site inspections by the city, and complete responsibility for site maintenance and security throughout the project duration. The contractor must also provide a Spill Prevention and Response plan and restore the site to its pre-construction condition prior to final project completion. The site is located near a CSX Railroad and includes existing water main and sanitary sewer infrastructure. The project date is noted as 7/01/25, and the document emphasizes that no other CRA or City of Plant City properties will be available for contractor use.

View the file

Other files

File Type Posted
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#6_Revision).pdf PDF
[Z]_Approved_Products_List-July2024.pdf PDF
[C]_General_Specifications_10-29-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[A]_Project_Specifications-Index_10-29-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#4_Revision).pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#2_Revision).pdf PDF
2025-02-07_-_Collins_Street_Complete_Street_Improvements_-_Phase_1_Contract.pdf PDF
[O]_611_Collins_Street_Site_Exhibit_7-2-25.pdf PDF
[M]_Plans_1.28.22_-_Collins_St_Watermain_7-2-25.pdf PDF
[L]_2025.02.11_-_Collins_Street_Landscape_SS_7-2-25.pdf PDF
[K]_2025.02.10_Collins_Lighting_Phase1_Signed_7-2-25.pdf PDF
[J]_2025.02.10_Collins_Signals_S&S_7-2-25.pdf PDF
[I]_2025.02.10_Collins_SPM_Phase1_Signed_7-2-25.pdf PDF
[H]_2025.02.10_Collins_Rdwy_Phase1_Signed_7-2-25.pdf PDF
[G]_Project_Exhibits-Index_7-2-25.pdf PDF
[E]_Watermain_Replacement_Technical_Specification_7-2-25.pdf PDF
[D]_General_Requirements_7-2-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[B]_Scope_of_Work_7-2-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Outside_Consultant_List_REV12-20-24.pdf PDF
RW_Use_Permit_Application_Form.pdf PDF
CSX_RR_TROE_Locations.pdf PDF
UWS_Charter.pdf PDF
NOA_-_PWS_General_Permit.pdf PDF
UWS_Frontier.pdf PDF
H4185018_Collins_Street_Core_Report_S&S.pdf PDF
UWS-TECO.pdf PDF
H4185018_Collins_St_Mast_Arms_S&S.pdf PDF
Soil_&_Groundwater_Management_Plan.pdf PDF
ERP_Exemption.pdf PDF
Traffic_Cabinet_-_Special_Requirements.pdf PDF
Bid_Form_-_Watermain_Replacement.xlsx XLSX spreadsheet
Worksheet_for_Construction_Agreement_11-8-24.docx DOCX document
Bid_Form_-_Road_&_Drainage.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notes:

1) The property located at 611 S. Collins

Street is owned by the Community Redevelopment Agency of Plant City (CRA), and is made available to the Contractor for the purpose of office and sanitary facilities, parking, and equipment and material storage during the term of the project.

2) Contaminated or potentially contaminated soils and groundwater may not be stored at 611 S. Collins Street or any other location other than the Collins Street Right of Way, in the manner specified elsewhere in the contract documents.

3) No other properties owned by the CRA or the City of Plant City will be available for any use by Contractor.

4) Provide temporary 6’ high chain link fence with (2) 12’ gates where indicated.

5) Conditions of Use:

a. Office trailer and sanitary facilities must be connected to city potable water and sanitary sewer facilities.

Facilities are available adjacent to site. Contractor to apply for temporary service and pay applicable fees and charges.

b. Fuel storage must include secondary containment.

c. Contractor to perform at least daily inspections for vehicles and equipment leaking fluids of any manner, and for general housekeeping.

d. Contractor must report any leaked fluids, prevent further leaking, and provide cleanup & decontamination to the satisfaction of the City.

e. Site will be inspected at least weekly by City and/or City’s representative.

Contractor must correct any deleterious conditions immediately.

f. Contractor is responsible for site maintenance and security for the duration of the project.

g. Contractor to provide Spill Prevention and Response plan in accordance with Section 104.

h. Other conditions and requirements of the contract apply.

i. Restore site to pre-construction condition prior to final completion.

CITY OF PLANT CITY

ENGINEERING

302 W.REYNOLDS ST.

PLANT CITY, FL 33563

COLLINS STREET PHASE I

IMPROVEMENTS

DATE: 7/01/25

SCALE: NTS

611 Collins Street Site SHEET No

611 S. Collins Street

¾ acre site available for office, parking, and material & equipment storage.

No contaminated or potentially contaminated soils or water may be stored on the site.

Approximate project limits

CSX Railroad

Water Main

Sanitary Sewer

6’ Temporary Fence