UWS-TECO.pdf
PDF 80 KB Posted
- Attached to
- Collins Street Complete Street - Phase I
- Solicitation number
- 25-014EN-FC-IFB
- Issued by
- Hillsborough County, Florida
About this file
This is a Utility Work Schedule for the Collins Street Phase 1 project, involving Tampa Electric Company (TEC) and the City of Plant City, dated February 2021. The document details a comprehensive utility relocation and installation plan, including activities such as installing underground and overhead electrical facilities, concrete poles, conduits, transformers, and pedestals along various station/offset points. The schedule outlines 31 specific utility work activities, with most tasks requiring right-of-way staking prior to construction and having zero consecutive calendar days during construction.
The document includes critical special notations highlighting TEC's operational requirements, such as a mandatory 21-calendar-day notice for scheduling any project-related work, safety protocols for line crews, normal work hours (Monday through Friday, 8 a.m. to 5 p.m.), and observed holidays. TEC stipulates that the relocation schedule becomes void if construction does not begin within 12 months of the signature date, and they require the latest plan set reflecting current field conditions. An emergency contact number (877-588-1010) is provided, along with project management and distribution facilities contact information for coordination purposes.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name:
Collins Street Phase 1
Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY
UTILITY WORK SCHEDULE
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
1 OH 13.2KV 513+00-
29R
516+17- 29R
EXISTING TO
REMAIN N/A N/A 0 0
2 45’ CONCRETE POLE 516+17-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 1 0
3 45’ CONCRETE POLE 516+38-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 1 0
4 UG 13.2KV IN 6”
CONDUIT
516+17- 29R
519+25-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 3 0
5 UG 13.2KV IN 6”
CONDUIT
519+25- 29R
EAST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
6 EMPTY 4” CONDUIT
FOR FUTURE USE 519+17
INSTALL CROSSING
FROM EAST TO
WEST OUT OF
CONSTR
R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
7 EMPTY 4” CONDUIT
FOR FUTURE USE 520+25
INSTALL CROSSING
FROM EAST TO
WEST OUT OF
CONSTR
R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
8 UG 13.2KV IN 6”
CONDUIT
EAST
OUT OF
CONSTR
520+21-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY
UTILITY WORK SCHEDULE
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
9 UG 13.2KV IN 6”
CONDUIT
520+21- 29R
521+55-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
10 UG 13.2KV IN 6”
CONDUIT
521+55- 29R
EAST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
11 EMPTY 4” CONDUIT
FOR FUTURE USE 521+52
INSTALL CROSSING
FROM EAST TO
WEST OUT OF
CONSTR
R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
12 EMPTY 4” CONDUIT
FOR FUTURE USE 521+61
INSTALL CROSSING
FROM EAST TO
WEST OUT OF
CONSTR
R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
13 UG 7.6KV IN 2-2”
CONDUIT
EAST
OUT OF
CONSTR
521+63-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
14 UG 7.6KV IN 2-2”
CONDUIT
521+63- 29R
524+24-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 3 0
15 UG 7.6KV IN 2-2”
CONDUIT
524+24- 29R
EAST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY
UTILITY WORK SCHEDULE
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
16 UG PEDESTAL 522+75-
35L INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 1 0
17 UG 24OV IN 4”
CONDUIT
522+75- 35L
522+75-
60R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 1 0
18 UG TRA NSFORMER 522+75-
60R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
19 UG TRANSFORMER 522+75-
70R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
20 UG 13.2KV IN 6”
CONDUIT
521+55- 29R
522+75-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
21 UG 13.2KV IN 6”
CONDUIT
522+75- 29R
524+24-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 3 0
22 UG 13.2KV IN 6”
CONDUIT
524+24- 29R
WEST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
23 UG 13.2KV IN 6”
CONDUIT
524+24- 29R
EAST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
24 UG 240V IN 4”
CONDUIT 524+527
EAST
TO
WEST
INSTALLATION R/W STAKED BY
OTHERS
Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY
UTILITY WORK SCHEDULE
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
OUT OF
CONSTR
25 UG 7.6KV IN 2”
CONDUIT
522+75- 70R
524+30-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 3 0
26 UG 7.6KV IN 2”
CONDUIT
524+30- 29R
EAST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
27 UG 7.6KV IN 2”
CONDUIT
525+22- 29R
WEST
OUT OF
CONSTR
INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
28 UG 13.2KV IN 6”
CONDUIT
524+30- 29R
525+80-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 2 0
29 45’ CONCRETE POLE 525+80-
29R INSTALLATION R/W STAKED BY
OTHERS
PRIOR TO
CONSTR 1 0
30 OH 13.2KV 525+80-
29R
NORTH
OUT OF
CONSTR
EXISTING TO
REMAIN N/A PRIOR TO
CONSTR 0 0
31 OH 240V AND 13.2KV 516+38
L/R
525+80 L/R
ALL OH FACILITIES
TO BE REMOVED
ALL
INSTALLATIONS
ARE ENERGIZED
PRIOR 10 0
Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY
UTILITY WORK SCHEDULE
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
SPECIAL NOTATIONS
1. TEC (TAMPA ELECTRIC COMPANY) REQUIRES A MINIMUM OF 21 CALENDAR DAYS TO SCHEDULE ANY TEC WORK RELATED TO THIS PROJECT, INCLUDING BUT NOT LIMITED TO "DURING CONSTRUCTION" WORK IDENTIFIED IN THIS RELOCATION SCHEDULE, REQUESTS FOR THE INSTALLATION OF LINE COVER, REQUESTS FOR OVERHEAD/UNDERGROUND ELECTRIC OUTAGE(S), REQUESTS FOR TEC POLE HOLDING, AND/OR REQUESTS TO PROTECT ANY TEC FACILITIES WITH SAID REQUESTS BEING INITIATED BY CITY OF PLANT CITY, THE CITY OF PLANT CITY CONTRACTOR AND/OR THEIR SUBCONTRACTOR. THIS NOTICE INCLUDES POLE REMOVAL ONCE A JOINT USER HAS VACATED THE FACILITY AND PROPERLY NOTICIFIED TEC FIELD REPRESENTATIVE TO ALLOW SCHEDULING OF ACTIVITY TO OCCUR.
2. FOR SAFETY REASONS, TEC LINE CREWS SHALL NOT WORK IN ADVERSE WEATHER CONDITIONS.
3. THE TEC LINE CREW AVAILABILITY SHALL BE AFFECTED AND/OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS. THIS LIMITATION WILL
BE DEPENDENT UPON THE SEVERITY OF THE EMERGENCY.
4. TEC AND/OR TEC'S SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TEC OBSERVED HOLIDAY'S WHICH INCLUDE NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE
DAY AND CHRISTMAS DAY.
5. TEC CAN NOT REMOVE ANY TEC POLES THAT HAVE EXISTING JOINT USERS STILL ATTACHED. SUBSEQUENTLY, ALL JOINT USERS SUCH AS FRONTIER, BRIGHT HOUSE, TRAFFIC, ETC. MUST BE REMOVED AND TEC ADVISED AND ALLOWED TIME TO SCHEDULE REMOVAL OF THE POLE ITSELF.
6. IF A NEW TEC ELECTRIC SERVICE MUST BE ESTABLISHED, PLEASE EMAIL TEC @ CSADMIN@TECOENERGY.COM AND REQUEST THE "PROCEDURE FOR ESTABLISHING A NEW ELECTRIC SERVICE". ALSO INCLUDED IN THIS SAME TEC DOCUMENT IS THE PROCEDURE FOR THE REMOVAL OF AN EXISTING TEC ELECTRIC SERVICE.
7. THIS RELOCATION SCHEDULE WILL BE CONSIDERED VOID SHOULD THE CITY OF PLANT CITY NOT BEGIN CONSTRUCTION WITHIN 12 MONTHS FROM SIGNATURE DATE OF TEC REPRESENTATIVE. IF SCHEDULE SHOULD BECOME VOID, TEC WILL THEN REQUIRE THE LATEST SET OF PLANS THAT REFLECT CURRENT FIELD CONDITIONS AT
THAT TIME FOR REVIEW AND RE-WRITE OF SCHEDULE IF DEEMED NECESSARY BY TEC.
EMERGENCY NUMBER FOR NIGHTS, WEEKENDS & TECO HOLIDAYS - 877-588-1010
PROJECT MANAGEMENT: ARLEE JONES 407-670-8633
13KV DISTRIBUTION FACILITIES CONTACT: MIKE LOTT 813-630-7179