This is a Utility Work Schedule for the Collins Street Phase 1 project, involving Tampa Electric Company (TEC) and the City of Plant City, dated February 2021. The document details a comprehensive utility relocation and installation plan, including activities such as installing underground and overhead electrical facilities, concrete poles, conduits, transformers, and pedestals along various station/offset points. The schedule outlines 31 specific utility work activities, with most tasks requiring right-of-way staking prior to construction and having zero consecutive calendar days during construction.

The document includes critical special notations highlighting TEC's operational requirements, such as a mandatory 21-calendar-day notice for scheduling any project-related work, safety protocols for line crews, normal work hours (Monday through Friday, 8 a.m. to 5 p.m.), and observed holidays. TEC stipulates that the relocation schedule becomes void if construction does not begin within 12 months of the signature date, and they require the latest plan set reflecting current field conditions. An emergency contact number (877-588-1010) is provided, along with project management and distribution facilities contact information for coordination purposes.

View the file

Other files

File Type Posted
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#6_Revision).pdf PDF
[Z]_Approved_Products_List-July2024.pdf PDF
[C]_General_Specifications_10-29-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[A]_Project_Specifications-Index_10-29-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#4_Revision).pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#2_Revision).pdf PDF
2025-02-07_-_Collins_Street_Complete_Street_Improvements_-_Phase_1_Contract.pdf PDF
[O]_611_Collins_Street_Site_Exhibit_7-2-25.pdf PDF
[M]_Plans_1.28.22_-_Collins_St_Watermain_7-2-25.pdf PDF
[L]_2025.02.11_-_Collins_Street_Landscape_SS_7-2-25.pdf PDF
[K]_2025.02.10_Collins_Lighting_Phase1_Signed_7-2-25.pdf PDF
[J]_2025.02.10_Collins_Signals_S&S_7-2-25.pdf PDF
[I]_2025.02.10_Collins_SPM_Phase1_Signed_7-2-25.pdf PDF
[H]_2025.02.10_Collins_Rdwy_Phase1_Signed_7-2-25.pdf PDF
[G]_Project_Exhibits-Index_7-2-25.pdf PDF
[E]_Watermain_Replacement_Technical_Specification_7-2-25.pdf PDF
[D]_General_Requirements_7-2-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[B]_Scope_of_Work_7-2-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Outside_Consultant_List_REV12-20-24.pdf PDF
RW_Use_Permit_Application_Form.pdf PDF
CSX_RR_TROE_Locations.pdf PDF
UWS_Charter.pdf PDF
NOA_-_PWS_General_Permit.pdf PDF
UWS_Frontier.pdf PDF
H4185018_Collins_Street_Core_Report_S&S.pdf PDF
H4185018_Collins_St_Mast_Arms_S&S.pdf PDF
Soil_&_Groundwater_Management_Plan.pdf PDF
ERP_Exemption.pdf PDF
Traffic_Cabinet_-_Special_Requirements.pdf PDF
Bid_Form_-_Watermain_Replacement.xlsx XLSX spreadsheet
Worksheet_for_Construction_Agreement_11-8-24.docx DOCX document
Bid_Form_-_Road_&_Drainage.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name:

Collins Street Phase 1

Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 OH 13.2KV 513+00-

29R

516+17- 29R

EXISTING TO

REMAIN N/A N/A 0 0

2 45’ CONCRETE POLE 516+17-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 1 0

3 45’ CONCRETE POLE 516+38-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 1 0

4 UG 13.2KV IN 6”

CONDUIT

516+17- 29R

519+25-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 3 0

5 UG 13.2KV IN 6”

CONDUIT

519+25- 29R

EAST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

6 EMPTY 4” CONDUIT

FOR FUTURE USE 519+17

INSTALL CROSSING

FROM EAST TO

WEST OUT OF

CONSTR

R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

7 EMPTY 4” CONDUIT

FOR FUTURE USE 520+25

INSTALL CROSSING

FROM EAST TO

WEST OUT OF

CONSTR

R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

8 UG 13.2KV IN 6”

CONDUIT

EAST

OUT OF

CONSTR

520+21-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

9 UG 13.2KV IN 6”

CONDUIT

520+21- 29R

521+55-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

10 UG 13.2KV IN 6”

CONDUIT

521+55- 29R

EAST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

11 EMPTY 4” CONDUIT

FOR FUTURE USE 521+52

INSTALL CROSSING

FROM EAST TO

WEST OUT OF

CONSTR

R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

12 EMPTY 4” CONDUIT

FOR FUTURE USE 521+61

INSTALL CROSSING

FROM EAST TO

WEST OUT OF

CONSTR

R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

13 UG 7.6KV IN 2-2”

CONDUIT

EAST

OUT OF

CONSTR

521+63-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

14 UG 7.6KV IN 2-2”

CONDUIT

521+63- 29R

524+24-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 3 0

15 UG 7.6KV IN 2-2”

CONDUIT

524+24- 29R

EAST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

16 UG PEDESTAL 522+75-

35L INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 1 0

17 UG 24OV IN 4”

CONDUIT

522+75- 35L

522+75-

60R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 1 0

18 UG TRA NSFORMER 522+75-

60R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

19 UG TRANSFORMER 522+75-

70R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

20 UG 13.2KV IN 6”

CONDUIT

521+55- 29R

522+75-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

21 UG 13.2KV IN 6”

CONDUIT

522+75- 29R

524+24-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 3 0

22 UG 13.2KV IN 6”

CONDUIT

524+24- 29R

WEST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

23 UG 13.2KV IN 6”

CONDUIT

524+24- 29R

EAST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

24 UG 240V IN 4”

CONDUIT 524+527

EAST

TO

WEST

INSTALLATION R/W STAKED BY

OTHERS

Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

OUT OF

CONSTR

25 UG 7.6KV IN 2”

CONDUIT

522+75- 70R

524+30-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 3 0

26 UG 7.6KV IN 2”

CONDUIT

524+30- 29R

EAST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

27 UG 7.6KV IN 2”

CONDUIT

525+22- 29R

WEST

OUT OF

CONSTR

INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

28 UG 13.2KV IN 6”

CONDUIT

524+30- 29R

525+80-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 2 0

29 45’ CONCRETE POLE 525+80-

29R INSTALLATION R/W STAKED BY

OTHERS

PRIOR TO

CONSTR 1 0

30 OH 13.2KV 525+80-

29R

NORTH

OUT OF

CONSTR

EXISTING TO

REMAIN N/A PRIOR TO

CONSTR 0 0

31 OH 240V AND 13.2KV 516+38

L/R

525+80 L/R

ALL OH FACILITIES

TO BE REMOVED

ALL

INSTALLATIONS

ARE ENERGIZED

PRIOR 10 0

Utility Company: TAMPA ELECTRIC COMPANY Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

SPECIAL NOTATIONS

1. TEC (TAMPA ELECTRIC COMPANY) REQUIRES A MINIMUM OF 21 CALENDAR DAYS TO SCHEDULE ANY TEC WORK RELATED TO THIS PROJECT, INCLUDING BUT NOT LIMITED TO "DURING CONSTRUCTION" WORK IDENTIFIED IN THIS RELOCATION SCHEDULE, REQUESTS FOR THE INSTALLATION OF LINE COVER, REQUESTS FOR OVERHEAD/UNDERGROUND ELECTRIC OUTAGE(S), REQUESTS FOR TEC POLE HOLDING, AND/OR REQUESTS TO PROTECT ANY TEC FACILITIES WITH SAID REQUESTS BEING INITIATED BY CITY OF PLANT CITY, THE CITY OF PLANT CITY CONTRACTOR AND/OR THEIR SUBCONTRACTOR. THIS NOTICE INCLUDES POLE REMOVAL ONCE A JOINT USER HAS VACATED THE FACILITY AND PROPERLY NOTICIFIED TEC FIELD REPRESENTATIVE TO ALLOW SCHEDULING OF ACTIVITY TO OCCUR.

2. FOR SAFETY REASONS, TEC LINE CREWS SHALL NOT WORK IN ADVERSE WEATHER CONDITIONS.

3. THE TEC LINE CREW AVAILABILITY SHALL BE AFFECTED AND/OR LIMITED DUE TO OUR REQUIRED RESPONSE TO EMERGENCY CONDITIONS. THIS LIMITATION WILL

BE DEPENDENT UPON THE SEVERITY OF THE EMERGENCY.

4. TEC AND/OR TEC'S SUBCONTRACTORS NORMAL WORK SCHEDULE IS MONDAY THROUGH FRIDAY FROM 8 A.M. TO 5 P.M., EXCLUDING TEC OBSERVED HOLIDAY'S WHICH INCLUDE NEW YEARS DAY, GOOD FRIDAY, MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, CHRISTMAS EVE

DAY AND CHRISTMAS DAY.

5. TEC CAN NOT REMOVE ANY TEC POLES THAT HAVE EXISTING JOINT USERS STILL ATTACHED. SUBSEQUENTLY, ALL JOINT USERS SUCH AS FRONTIER, BRIGHT HOUSE, TRAFFIC, ETC. MUST BE REMOVED AND TEC ADVISED AND ALLOWED TIME TO SCHEDULE REMOVAL OF THE POLE ITSELF.

6. IF A NEW TEC ELECTRIC SERVICE MUST BE ESTABLISHED, PLEASE EMAIL TEC @ CSADMIN@TECOENERGY.COM AND REQUEST THE "PROCEDURE FOR ESTABLISHING A NEW ELECTRIC SERVICE". ALSO INCLUDED IN THIS SAME TEC DOCUMENT IS THE PROCEDURE FOR THE REMOVAL OF AN EXISTING TEC ELECTRIC SERVICE.

7. THIS RELOCATION SCHEDULE WILL BE CONSIDERED VOID SHOULD THE CITY OF PLANT CITY NOT BEGIN CONSTRUCTION WITHIN 12 MONTHS FROM SIGNATURE DATE OF TEC REPRESENTATIVE. IF SCHEDULE SHOULD BECOME VOID, TEC WILL THEN REQUIRE THE LATEST SET OF PLANS THAT REFLECT CURRENT FIELD CONDITIONS AT

THAT TIME FOR REVIEW AND RE-WRITE OF SCHEDULE IF DEEMED NECESSARY BY TEC.

EMERGENCY NUMBER FOR NIGHTS, WEEKENDS & TECO HOLIDAYS - 877-588-1010

PROJECT MANAGEMENT: ARLEE JONES 407-670-8633

13KV DISTRIBUTION FACILITIES CONTACT: MIKE LOTT 813-630-7179