UWS_Charter.pdf

PDF 128 KB Posted

Attached to
Collins Street Complete Street - Phase I
Solicitation number
25-014EN-FC-IFB
Issued by
Hillsborough County, Florida

About this file

This document is a Utility Work Schedule for the Collins Street Phase 1 project, involving Charter Communications and the City of Plant City, dated February 2021. The schedule details nine separate underground utility conduit installations and crossings, primarily consisting of 1-2" and 2-2" conduits at various station and offset locations along the project route. Each entry specifies the utility facility type, from/to stations, utility work activity description, dependent activities, TCP (Traffic Control Plan) phase, and consecutive calendar days required prior to and during construction.

The utility work activities are predominantly focused on proposed underground (U/G) crossings, drops, and distribution installations, with all activities requiring permit and right-of-way (R.O.W.) staking. Most activities are designated as "PRIOR" TCP phase, with minimal consecutive calendar days needed (ranging from 0-2 days prior to construction and 0-2 days during construction). The work involves precise geographic positioning, with stations ranging from 521+54 to 525+95, and utilizing both right (RT) and left (LT) offsets to precisely locate the proposed utility infrastructure modifications.

View the file

Other files

File Type Posted
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#6_Revision).pdf PDF
[Z]_Approved_Products_List-July2024.pdf PDF
[C]_General_Specifications_10-29-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[A]_Project_Specifications-Index_10-29-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#4_Revision).pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#2_Revision).pdf PDF
2025-02-07_-_Collins_Street_Complete_Street_Improvements_-_Phase_1_Contract.pdf PDF
[O]_611_Collins_Street_Site_Exhibit_7-2-25.pdf PDF
[M]_Plans_1.28.22_-_Collins_St_Watermain_7-2-25.pdf PDF
[L]_2025.02.11_-_Collins_Street_Landscape_SS_7-2-25.pdf PDF
[K]_2025.02.10_Collins_Lighting_Phase1_Signed_7-2-25.pdf PDF
[J]_2025.02.10_Collins_Signals_S&S_7-2-25.pdf PDF
[I]_2025.02.10_Collins_SPM_Phase1_Signed_7-2-25.pdf PDF
[H]_2025.02.10_Collins_Rdwy_Phase1_Signed_7-2-25.pdf PDF
[G]_Project_Exhibits-Index_7-2-25.pdf PDF
[E]_Watermain_Replacement_Technical_Specification_7-2-25.pdf PDF
[D]_General_Requirements_7-2-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[B]_Scope_of_Work_7-2-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Outside_Consultant_List_REV12-20-24.pdf PDF
RW_Use_Permit_Application_Form.pdf PDF
CSX_RR_TROE_Locations.pdf PDF
NOA_-_PWS_General_Permit.pdf PDF
UWS_Frontier.pdf PDF
H4185018_Collins_Street_Core_Report_S&S.pdf PDF
UWS-TECO.pdf PDF
H4185018_Collins_St_Mast_Arms_S&S.pdf PDF
Soil_&_Groundwater_Management_Plan.pdf PDF
ERP_Exemption.pdf PDF
Traffic_Cabinet_-_Special_Requirements.pdf PDF
Bid_Form_-_Watermain_Replacement.xlsx XLSX spreadsheet
Worksheet_for_Construction_Agreement_11-8-24.docx DOCX document
Bid_Form_-_Road_&_Drainage.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: Collins Street Phase 1 Utility Company: CHARTER COMMUNICATIONS Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1. 1-2” CONDUIT 521+54 521+58 U/G CROSSING TO

REMAIN N/A N/A 0 0

2. 1-2” CONDUIT 521+20

70RT

521+58

26RT

PROPOSED U/G DROP PERMIT, STAKING

R.O.W.

PRIOR 1 0

3. 2-2” CONDUIT 521+58

26RT

522+95

PROPOSED NEW U/G

PERMIT, STAKING

PRIOR 2 0

4.

1-2” CONDUIT 522+75

45LT

522+95

26RT PROPOSED U/G

SERVICE DROP

PERMIT, STAKING

R.O.W

PRIOR

2 0

5.

1-2” CONDUIT 522+95

522+60

61RT PROPOSED U/G

SERVICE DROP

PERMIT, STAKING

R.O.W

PRIOR

2 0

6. 2-2” CONDUIT

524+29

86 LT

PROPOSED U/G

DISTIBUTION

PERMIT, STAKING

R.O.W.

PRIOR 2 0

7. 1-2” CONDUIT

524+58

39RT

PROPOSED U/G

SERVICE DROP PERMIT, STAKING

PRIOR 2 0

8. 2-2” CONDUIT 524+29

525+78

DISTIBUTION

PERMIT, STAKING

PRIOR 2 2

Project Name: Collins Street Phase 1 Utility Company: CHARTER COMMUNICATIONS Plans Dated: Feb 2021 Governmental Agency CITY OF PLANT CITY

UTILITY WORK SCHEDULE

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

9.

2-2” CONDUIT 525+78

525+95

52RT

SERVICE DROP

PERMIT, STAKING

R.O.W.

PRIOR

2 0