This is a Geotechnical Engineering Report prepared by Terracon Consultants, Inc. for the City of Plant City, Hillsborough County, Florida, focusing on roadway cores along Collins Street from Alsobrook Street to Martin Luther King Boulevard. The project involves conducting four core samples to assess the existing pavement conditions in preparation for a repaving project planned for 2020. The investigation was initiated based on a proposal dated February 2, 2018, and the field work included taking core samples using an electric drill with a 4-inch diameter diamond-tipped core barrel, with pavements subsequently patched using cold-mix asphalt.

The core sampling revealed varying asphalt layer thicknesses across the four locations, ranging from 2.5 to 4.25 inches, with some cores showing multiple lifts of asphalt. Of particular note, one core (C-4) included 3.25 inches of brick pavers beneath the asphalt layers. The top course of asphalt was likely an SP (surface) asphalt, with the lowest layer appearing to be a base course asphalt. No groundwater was encountered during the cores, and the investigation was limited to examining the roadway's surface composition. Terracon emphasized that variations may occur between core locations and recommended additional testing if significant differences are discovered during construction.

View the file

Other files

File Type Posted
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#6_Revision).pdf PDF
[Z]_Approved_Products_List-July2024.pdf PDF
[C]_General_Specifications_10-29-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[A]_Project_Specifications-Index_10-29-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#4_Revision).pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#2_Revision).pdf PDF
2025-02-07_-_Collins_Street_Complete_Street_Improvements_-_Phase_1_Contract.pdf PDF
[O]_611_Collins_Street_Site_Exhibit_7-2-25.pdf PDF
[M]_Plans_1.28.22_-_Collins_St_Watermain_7-2-25.pdf PDF
[L]_2025.02.11_-_Collins_Street_Landscape_SS_7-2-25.pdf PDF
[K]_2025.02.10_Collins_Lighting_Phase1_Signed_7-2-25.pdf PDF
[J]_2025.02.10_Collins_Signals_S&S_7-2-25.pdf PDF
[I]_2025.02.10_Collins_SPM_Phase1_Signed_7-2-25.pdf PDF
[H]_2025.02.10_Collins_Rdwy_Phase1_Signed_7-2-25.pdf PDF
[G]_Project_Exhibits-Index_7-2-25.pdf PDF
[E]_Watermain_Replacement_Technical_Specification_7-2-25.pdf PDF
[D]_General_Requirements_7-2-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[B]_Scope_of_Work_7-2-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Outside_Consultant_List_REV12-20-24.pdf PDF
RW_Use_Permit_Application_Form.pdf PDF
CSX_RR_TROE_Locations.pdf PDF
UWS_Charter.pdf PDF
NOA_-_PWS_General_Permit.pdf PDF
UWS_Frontier.pdf PDF
UWS-TECO.pdf PDF
H4185018_Collins_St_Mast_Arms_S&S.pdf PDF
Soil_&_Groundwater_Management_Plan.pdf PDF
ERP_Exemption.pdf PDF
Traffic_Cabinet_-_Special_Requirements.pdf PDF
Bid_Form_-_Watermain_Replacement.xlsx XLSX spreadsheet
Worksheet_for_Construction_Agreement_11-8-24.docx DOCX document
Bid_Form_-_Road_&_Drainage.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPORT COVER PAGE

Geotechnical Engineering Report

South Collins Street Cores Plant City, Hillsborough County, Florida

July 25, 2019 Terracon Project No. H4185018

Prepared for:

City of Plant City

Plant City, Florida

Prepared by:

Terracon Consultants, Inc.

Tampa, Florida

Terracon Consul tants, Inc. 5463 W. Waters Ave. , Suite 830 Tampa, FL 33634 P (813) 221-0050 F (813) 221-0051 terracon.com

REPORT COVER LETTER TO SIGN

July 25, 2019

City of Plant City 302 W Reynolds Street Plant City, Florida 33564

Attn: Ms. Tatyana Austin

Re: Geotechnical Engineering Report South Collins Street Cores Alsobrook St. to MLK Blvd Plant City, Hillsborough County, Florida Terracon Project No. H4185018

Dear Ms. Austin:

We have completed the Geotechnical Engineering services for the above referenced project. This study was performed in general accordance with Terracon Proposal No. PH4185018 dated February 2, 2018. This report presents the findings of the roadway cores for the proposed project.

We appreciate the opportunity to be of service to you on this project. If you have any questions concerning this report or if we may be of further service, please contact us.

Sincerely, Terracon Consultants, Inc.

Certificate of Authorization Number 8830

Stephen C. Knauss, P.E., D.GE Keith D. Bennett, P.E.

Senior Engineer Senior Geotechnical Engineer Florida Registration No.: 28202 Florida Registration No.: 33075

This report has been digitally signed and sealed by Stephen C. Knauss, P.E. on date adjacent to the seal.

Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies

Responsive ■ Resourceful ■ Reliable 1

REPORT TOPICS

INTRODUCTION

SITE CONDITIONS

PROJECT DESCRIPTION

GEOTECHNICAL CHARACTERIZATION

GENERAL COMMENTS

Note: This report was originally delivered in a web-based format. Orange Bold text in the report indicates a referenced section heading. The PDF version also includes hyperlinks which direct the reader to that section and clicking on the GeoReport logo will bring you back to this page. For more interactive features, please view your project online at client.terracon.com.

ATTACHMENTS

EXPLORATION AND TESTING PROCEDURES

PHOTOGRAPHY LOG

SITE LOCATION AND EXPLORATION PLANS

Note: Refer to each individual Attachment for a listing of contents.

Responsive ■ Resourceful ■ Reliable 1

INTRODUC TION

Geotechnical Engineering Report South Collins Street Cores Alsobrook St. to MLK Blvd

Plant City, Hillsborough County, Florida Terracon Project No. H4185018

July 25, 2019

INTRODUCTION

This report presents the results of our subsurface exploration services performed for the proposed repaving of Collins Street from Alsobrook St. to MLK Blvd in Plant City, Hillsborough County, Florida. The purpose of these services is to provide information and geotechnical engineering recommendations relative to:

■ Core results

The Scope of Services for this project included conducting roadway cores at four locations on Collins Street between Alsobrook Street and Dr. Martin Luther King Boulevard. Test procedures are provided in the Attachments.

Maps showing the site and boring locations are shown in the Site Location and Exploration Plan sections, respectively.

SITE CONDITIONS

The following description of site conditions is derived from our site visit in association with the field exploration and our review of publicly available geologic and topographic maps.

Item Description

Parcel Information

The project is located at Collins Street from Alsobrook St to MLK Blvd in Plant City, Hillsborough County, Florida.

This is approximately ½ mile Latitude/Longitude 28.011°/ -82.122° (approximate) See Site Location

Existing Improvements

Two and four-lane urban highway with asphalt paving and curbs and gutter and sidewalks

Existing Topography The elevation of the roadway varies from about +130 to +140 feet NAVD.

South Collins Street Cores ■ Plant City, Hillsborough County, Florida July 25, 2019 ■ Terracon Project No. H4185018

Responsive ■ Resourceful ■ Reliable 2

PROJECT DESCRIPTION

Our initial understanding of the project was provided in our proposal and was discussed during project planning. A period of collaboration has transpired since the project was initiated, and our final understanding of the project conditions is as follows:

Item Description Information Provided Information is provided by Kimley-horn in a series of emails.

Project Description Repaving of Collins Street Pavements Details of the proposed paving was not provided.

Estimated Start of Construction 2020

GEOTECHNICAL CHARACTERIZATION

Coring Results

The following table presents the results of the coring for each location.

Core Location Material Description C-1 3¼ inches asphalt in 3 lifts: 1¼ inches over ½ inches over 1½ inches C-2 3¾ inches asphalt in 3 lifts: 2 inches over ½-inches over 1¼ inches asphalt

C-3 Southbound Collins St 4¼ inches asphalt in 3 lifts: 1¼ inches over 1¼ inches over 1¾

C-4 Northbound Collins St. 2½-inches asphalt in 2 lifts: 1¼-inches over 1¼-inches over 3¼- inches of brick pavers. Note that the asphalt had large voids just above the brick.

The top course of asphalt was likely an SP asphalt and the lowest layer appears to be a base course asphalt.

Groundwater Conditions

The cores did not penetrate through the base material and groundwater was not encountered by any of these cores.

GENERAL COMMENTS

Our results are based on the roadway conditions in the area, and the data obtained from our site exploration. Variations will occur between core locations or due to the modifying effects of construction. The nature and extent of such variations may not become evident until during or

July 25, 2019 ■ Terracon Project No. H4185018

Responsive ■ Resourceful ■ Reliable 3 after construction. If variations appear, we can provide additional testing to better define the variations.

Our Scope of Services does not include either specifically or by implication any environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or prevention of pollutants, hazardous materials or conditions. If the owner is concerned about the potential for such contamination or pollution, other studies should be undertaken.

Responsive ■ Resourceful ■ Reliable

ATTACHMENTS

EXPLORATION AND TESTING PROCEDURES

Field Exploration

Number of Cores Planned Location

4 Collins Street

Core Layout: Unless otherwise noted, Terracon personnel provided the coring layout.

Coordinates were obtained with a handheld GPS unit (estimated horizontal accuracy of about ±10 feet). If a more precise coring layout is desired, we recommend the core locations be surveyed.

Subsurface Exploration Procedures: After the appropriate Temporary Traffic Control (TTC) was established, the coring was conducted with an electric drill and a 4-inch diameter diamond tipped core barrel. Pavements were patched with cold-mix asphalt.

PHOTOGRAPHY LOG

Core C-1

Core C-2

Core C-3

Core C-4

SITE LOCATION AND EXPLORATION PLANS

Contents:

Site Location Plan Exploration Plan

Note: All attachments are one page unless noted above.

SITE LOCATION

July 25, 2019 ■ Terracon Project No. H4185018

Note to Preparer: This is a large table with outside borders. Just click inside the table above this text box, then paste your GIS Toolbox image.

When paragraph markers are turned on you may notice a line of hidden text above and outside the table – please leave that alone. Limit editing to inside the table.

The line at the bottom about the general location is a separate table line. You can edit it as desired, but try to keep to a single line of text to avoid reformatting the page.

SITE LOCA TION

DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION PURPOSES MAP PROVIDED BY MICROSOFT BING MAPS

EXPLORATION PLAN

July 25, 2019 ■ Terracon Project No. H4185018

Note to Preparer: This is a large table with outside borders. Just click inside the table above this text box, then paste your GIS Toolbox image.

When paragraph markers are turned on you may notice a line of hidden text above and outside the table – please leave that alone. Limit editing to inside the table.

The line at the bottom about the general location is a separate table line. You can edit it as desired, but try to keep to a single line of text to avoid reformatting the page.

EXPLORATION P LAN

DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION PURPOSES MAP PROVIDED BY MICROSOFT BING MAPS

2019-07-25T14:52:32-0400
Bennett, Keith D
2019-07-25T16:16:52-0400
Knauss, Stephen C.
2019-07-25T16:16:52-0400
Knauss, Stephen C.

File details come from the government source that posted it. Updated .