This is a WebAIM Short Form Task Group Instruction (TGI) for contractor work on USS RAFAEL PERALTA (DDG-115). The document outlines requirements for providing temporary utility service infrastructure on the naval vessel.

The work involves installing, maintaining, and removing temporary service ways and enclosures at four specific locations on the vessel: 04 Level Weather (Frames 145-150), 02 Level Weather (Frames 120-395), 01 Level Weather (Frames 15-350), and Main Deck Weather (Frames 425-435), spanning both port and starboard sides. The contractor must fabricate and install one temporary service way for utility service, one temporary enclosure with an openable top, and one temporary enclosure per the sketch guidance provided in Enclosure-01. The work includes maintenance of these installations (2 times total when requested by the Project Team) and removal upon request. All work on new and disturbed surfaces must comply with requirement 009-032. The work start date is 7/23/2026 with a completion date of 9/29/2026. Supporting services will be provided by SRF-JRMC, including crane and rigging services, electrical utility service, utility services (low pressure air, water, and steam supply), safety inspections, and QA inspections. The document references NAVSEA Standard Items (NSI FY-26), Local Standard Items (LI FY-26), and 29 CFR Part 1915.71 (Scaffolding or Staging) as applicable standards. The planner is M. Hayashi (Code 231B) and the Work Integration Manager is T. Yaginuma (Code 333).

View the file

Other files

File Type Posted
TGI_38K6113702A01_c0v0_REV2.pdf PDF
TGI_38K6144104A01_c0v0_REV2.pdf PDF
TGI_38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6171101A01_c0v0_REV2.pdf PDF
TGI_38K6113601A01_c0v0_REV2.pdf PDF
TGI_38K6112321A01_c0v0_REV2.pdf PDF
Solicitation Amendment N6264926RA0360005 SF 30.pdf PDF
TGI_38K6112304A01_c0v0_REV2.pdf PDF
TGI_38K6113701A01_c0v0_REV2.pdf PDF
TGI_38K6154101A01_c1v1_REV2.pdf PDF
TGI_38K6112320A01_c1v1_REV2.pdf PDF
TGI_38K6112001A01_c0v0_REV2.pdf PDF
TGI 38K6112318A01_c2v2_REV2.pdf PDF
TGI_38K6113701A01_c0v0_REV1.pdf PDF
TGI_38K6113801A01_c1v0_REV1.pdf PDF
TGI_38K6152101A02_c0v0_REV1.pdf PDF
TGI_38K6145601A01_c0v0_REV1.pdf PDF
TGI_38K6164401A01_c1v2_REV1.pdf PDF
Solicitation Amendment N6264926RA0360002 SF 30.pdf PDF
TGI_38K6112301A01_c0v0_REV1.pdf PDF
TGI_38K6112305A01_c1v0_REV1.pdf PDF
TGI_38K6112304A01_c0v0_REV1.pdf PDF
TGI_38K6112316A01_c0v0_REV1.pdf PDF
TGI_38K6171101A01_c0v0_REV1.pdf PDF
TGI_38K6169901A01_c0v0_REV1.pdf PDF
TGI_38K6154101A01_c1v1_REV1.pdf PDF
7027318_53711_-_0001_ G_-_0001.pdf PDF
MP LM19-K6112303-ES01NA54_r3.pdf PDF
TGI_38K6113801A01_c1v0.pdf PDF
TGI_38K6145601A01_c0v0.pdf PDF
TGI_38K6112318A01_c0v0.pdf PDF
TGI 38K6186301A01_c0v0.pdf PDF
TGI_38K6112320A01_c1v1.pdf PDF
TGI_38K6112305A01_c1v0.pdf PDF
TGI 38K6144104A01_c0v0.pdf PDF
Attachment III Request for Information Sheet (Fillable).pdf PDF
TGI_38K6151101A01_c0v0.pdf PDF
TGI_38K6113702A01_c0v0.pdf PDF
TGI_38K6113601A01_c0v0.pdf PDF
TGI_38K6113602A01_c0v0.pdf PDF
TGI_38K6112303A01_c0v0.pdf PDF
TGI 38K6169901A01_c0v0.pdf PDF
TGI_38K6112316A01_c0v0.pdf PDF
TGI_38K6112306A01_c0v1.pdf PDF
TGI_38K6112321A01_c0v0.pdf PDF
Attachment VII QSAP.pdf PDF
Exhibit A CDRL - GFM.pdf PDF
Attachment V Source of Repair Instruction.pdf PDF
TGI_38K6154103A02_c0v0.pdf PDF
TGI_38K6112301A01_c0v0.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

21-JAN-2026 1552

20.15.6.0.9333 (July 2025) ICN: 38K6186301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY SERVICE SV A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86491

CU PHASE TITLE: F/O - PROVIDE KTR SERVICE WORK FOR TMPORARY UTILLITY SERVICE

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

EXSYL068

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

HAYASHI, MOTONORI 231B 3152436145 07-NOV-2025

APPROVED BY: CODE: PHONE: DATE:

TAKAGI, RYOUTA 231B 3152434502 07-NOV-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EXSY-L068

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

SAITO, KAZUNOBU VARIOUS U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

863A5101

1 SCOPE/PURPOSE:

1.1 Title: KTR Service Work for Temporary Utility Service; provide

1.2 Location of Work:

1.2.1 04 Level Weather, Frames between 145 and 150, Port and Starboard (Stbd)

1.2.2 02 Level Weather, Frames between 120 and 395, Port and Stbd

1.2.3 01 Level Weather, Frames between 15 and 350, Port and Stbd

1.2.4 Main Deck Weather, Frames between 425 and 435, Port and Stbd

1.3 Identification:

1.3.1 Quantity (One Lot), Temporary Service Way for Utility Service

TGI Short Form

21-JAN-2026 1552

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6186301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY SERVICE SV A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86491

CU PHASE TITLE: F/O - PROVIDE KTR SERVICE WORK FOR TMPORARY UTILLITY SERVICE

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

Remarks: See Sketch Enclosure-01 for location details.

1.3.2 Quantity (One Lot), Temporary Enclosure with Openable Top for Utility Service

Remarks: See Sketch Enclosure-01 for location details.

1.3.3 Quantity (One Lot), Temporary Enclosure for Utility Service

Remarks: See Sketch Enclosure-01 for location details.

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor Work start date:

1.7 Contractor Work completion date:

2 PROCEDURE:

2.1 Install each temporary service way listed in 1.3.1 in accordance with Ref. No. 3, using Enclosure-01 for guidance.

2.2 Fabricate and install each temporary enclosure listed in 1.3.2 and 1.3.3 in accordance with Ref. No. 3, using Enclosure-01 for guidance.

2.3 Maintain each temporary service way and temporary enclosure listed in 1.3.1 through 1.3.3 for a total 2 times when requested by Project Team in accordance with Ref. No. 3.

2.4 Remove each temporary service way and temporary enclosure listed in 1.3.1 through 1.3.3 in accordance with Ref. No. 3 when requested by Project Team.

2.5 Accomplish the requirements of 009-032 of Ref. No. One for each new and disturbed surface.

2.6 Notes:

2.6.1 Planner: Code 231B M. Hayashi, 243-6145

2.6.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.6.3 Exact installation, modification, and removal of area, detail, and date of temporary service way and temporary enclosure will be directed by the Project Team.

2.6.4 JCN EXSY-L068 is related to this TGI.

2.7 Government Furnished Material (GFM): None.

2.8 SRF-JRMC will provide the following service work: (TGI No. 38K6186301S02)

Kouichi.Yoshida.ja Typewritten Text 7/23/2026

Kouichi.Yoshida.ja Typewritten Text 9/29/2026

21-JAN-2026 1552

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6186301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY SERVICE SV A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86491

CU PHASE TITLE: F/O - PROVIDE KTR SERVICE WORK FOR TMPORARY UTILLITY SERVICE

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

2.8.1 [C740] Crane and crane rigger service.

2.8.2 [X99E] Utility service, electrical.

2.8.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.8.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.8.5 [C133] QA inspection for (G) symbol(s).

21-JAN-2026 1552

20.15.6.0.9333 (July 2025) (Continued) ICN: 38K6186301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY SERVICE SV A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-115 USS RAFAEL PERALTA K61 86491

CU PHASE TITLE: F/O - PROVIDE KTR SERVICE WORK FOR TMPORARY UTILLITY SERVICE

FOUO Pg 4 of 4

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

3 TM 29 CFR PART

1915.71 Scaffolding or Staging - N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 38K6186301A01-Sketch.pdf 06-NOV-2025 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38K6186301 KEY OP: A01

38K6186301A01 SKETCH

ENCLOSURE-01

Sheet 1 of 4

Sheet 2 of 4

Sheet 3 of 4

Sheet 4 of 4