This document is a Request for Information (RFI) form dated 12 NOV 2003, designed to facilitate communication between contractors and the contracting agency regarding contract details and potential information needs. The form provides a structured template for submitting and tracking information requests, with sections for identifying the subject of the RFI, documenting potential cost and time impacts, and recording recommended responses and replies.

The RFI form includes important procedural notes, emphasizing that the system is intended solely for responding to contractor information requests and does not authorize work to proceed. Contractors are advised that if they consider an RFI response a changed condition, they must provide written notice to the Contracting Officer within 20 calendar days of the reply date. The form is specifically from NS Everett PWD/FEAD and includes distribution instructions for routing the document to the appropriate file and contract officer.

View the file

Other files

File Type Posted
SOW - Doc D4 - Electronic Operation and Maintenance Support Info.docx DOCX document
SOW - Doc B6 - Full Set - Control Asbuilts R1 - 2017 (AutoCAD).pdf PDF
SOW - Doc A6 - SECNAV 5512_1 April 2025.pdf PDF
SOW - DOC B16 - Natatorium Architectural Drawings.pdf PDF
SOW - Doc B3 - E-20R3 Panel Schedules - 2009 (AutoCAD).pdf PDF
SOW - DOC B12 - P-07 2nd Floor Plan South - Plumbing - 1996 (AutoCAD).pdf PDF
SOW - DOC B13 - P-09 Kitchen Plan - Second Floor Plumbing - 1996 (PDF Only).pdf PDF
SOW - DOC B10 - P-10 Kitchen Equipment Piping Diagrams - 1996 (PDF Only).pdf PDF
SOW - Doc D2 - D40 FIRE ALARM.docx DOCX document
SOW - DOC B15 - Commons Architectural Drawings.pdf PDF
SOW - Doc B8 - Fire Alarm Shop Drawings - Commons and Pool Combined (AutoCAD).pdf PDF
SOW - Doc B7 - FX102 Building 1950 Monaco FARS Final Design (PDF Only).pdf PDF
SOW - Doc B4 - E-21R5 Panel Schedules - 2015 (AutoCAD).pdf PDF
SOW - DOC B14 - E-18 Fire Alarm - Elevator Control - 1996 (PDF Only).pdf PDF
SOW - Doc A7 - NSE - REAL ID - Identification and Citizenship Requirement.pdf PDF
SOW - Doc B5 - E-19R2 One-line Diagram - 2008 (AutoCAD).pdf PDF
SOW - Doc A4 - Submittal - Transmittal Form - 2015 R2.pdf PDF
SOW - Doc A5 - Time Impact Analysis.pdf PDF
SOW - Doc D3 - D50 ELECTRICAL.docx DOCX document
SOW - Doc D1 - C30 INTERIOR FINISHES.docx DOCX document
SOW - DOC B11 - P-01 Plumbing Schedules - Plans and Details - 1996 (PDF Only).pdf PDF
SOW - Doc B1 - M-02R1 Mech Equipment Schedules Commons - 2017 (PDF Only).pdf PDF
SOW - Doc A1 - Pre Proposal Inquiry Form.pdf PDF
SOW - Doc B2 - M-01.01R2 Schedules Pool Addition - 2017 (AutoCAD).pdf PDF
SOW - Doc A9 - Contractor QC Report.pdf PDF
SOW - Doc A8 - DBIDS- Acceptable ID Documents.pdf PDF
SOW - Doc A12 - eCMS Section - UFGS 01 31 23.13 20.pdf PDF
SOW - DOC B9 - M-10R1 Mech Equipment Room 1st Floor Plan - 2017 (PDF Only).pdf PDF
SOW - Doc A11 - Monthly Waste Report - 2010-10.pdf PDF
SOW - Doc A10 - Contractor Production Report - 2017.pdf PDF
SOW - Doc A3 - Activity Hazard Analysis - COE 2016 R2.pdf PDF
SOW - Replace Fire Alarm Control Panel B1950.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION RFI NUMBER

CONTRACT NUMBER:

CONTRACT TITLE:

PRIME CONTRACTOR SUBCONTRACTOR / SUPPLIER

Request For Information Form – 12 NOV 2003

SUBJECT OF RFI:

DRAWINGS: DETAILS: SPECIFICATION CPM ACTIVITY #:

INFORMATION REQUESTED:

Date Response Required By: Date RFI Submitted: Signature:

CONTRACTOR RECOMMENDATION:

COST EFFECT: Increase: Decrease: None: Estimated Amount:

TIME IMPACT: Increase: Decrease: None: Estimated Calendar Days:

From: Date Received: Signature:

To: Date Returned:

RECOMMENDED RESPONSE:

From:

NS Everett PWD/FEAD

Reply Date: Signature:

To:

REPLY:

This response is for clarification only & results in no cost or time change to the contract.

This response requires a modification to the contract. A formal request for proposal will follow under separate correspondence. No work is authorized until the modification is signed by the Contracting Officer. Proposed Change number assigned is .

The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES

NOT authorize the contractor to proceed with work – to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days of reply date.

DISTRIBUTION: Original to File via REICC PL ET A/E PC # via AROICC/Contract Officer

CONTRACT NUMBER:
CONTRACT TITLE:
RFI NUMBER:
PRIME CONTRACTORRow1:
SUBCONTRACTOR SUPPLIERRow1:
SUBJECT OF RFI:
DRAWINGSRow1:
DETAILSRow1:
SPECIFICATIONRow1:
CPM ACTIVITY Row1:
INFORMATION REQUESTED:
CONTRACTOR RECOMMENDATION:
Decrease: Off
None: Off
Estimated Amount: Off
Decrease_2: Off
None_2: Off
Estimated Calendar Days: Off
From:
To:
RECOMMENDED RESPONSE:
To_2:
REPLY:
This response is for clarification only results in no cost or time change to the contract: Off
This response requires a modification to the contract A formal request for proposal will follow under separate correspondence No: Off
PL: Off
ET: Off
AE: Off
PC: Off
DISTRIBUTION Original to File via REICC PL ET AE PC:
Date2_af_date:
Date3_af_date:
Date5_af_date:
Date6_af_date:
Date8_af_date: