Amend 0006.pdf

PDF 113 KB Posted

Attached to
Buildings 15, 326, DD48, G770, NH180, NH200 Clean HVAC Systems
Solicitation number
N4008526R9042
Issued by

About this file

This is Amendment 0006 to a federal solicitation (N40085-26-R-9042) issued by NAVFAC Mid-Atlantic for clean HVAC systems work at Camp Lejeune, North Carolina. The amendment extends the proposal due date to 23 July 2026 at 1400 hours and increases the contract completion date from the original three months to 180 calendar days after award. The work encompasses duct cleaning and HVAC system maintenance across six buildings: Buildings 15, 326, DD48, G770, NH180, and NH200.

The amendment includes responses to 18 RFIs submitted by potential contractors. Key clarifications include: NH200 and G770 require AHU cleaning on a continuous day/evening schedule to minimize business downtime; contractors must incorporate expedited procurement costs for long-lead materials such as blower wheels into their proposals to meet the 180-day deadline; the disconnect supplying power to AHUs 2 and 5 requires replacement; contractors are responsible for developing their own plans for temporary cooling unit placement and determining electrical availability; and contractors may conduct additional site visits at their own expense to obtain specific equipment specifications and system design information. All available drawings have been provided to support proposal development. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

File Type Posted
FINAL Lejeune buildings 15 326 DD48 G770 NH200 and NH180 AHU cleaning SOW --10 AUG 2026.pdf PDF
Amend 0011.pdf PDF
326 Drawings.pdf PDF
FINAL Lejeune buildings 15 326 DD48 G770 NH200 and NH180 AHU cleaning SOW --4 AUG 2026.pdf PDF
Amendment 0010.pdf PDF
Amend 0009.pdf PDF
Amend 0008.pdf PDF
Amend 0007.pdf PDF
Amend 0005.pdf PDF
LEJU NH200 2009 MEDICAL CLINIC REPLACEMENT.pdf PDF
LEJU 00015 1997 MAJOR INTERIOR EXTERIOR REPAIRS.pdf PDF
LEJU NH180 2012 NATIONAL INTREPID CENTER OF EXCELLENCE.pdf PDF
LEJU 0G770 REPLACE HVAC BUILDING G-770.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
ufc_4_510_01_2023_c4.pdf PDF
MAXIMO Initial Equipment Inventory and Replacement.pdf PDF
FINAL Lejeune buildings 15 326 DD48 G770 NH200 and NH180 AHU cleaning SOW --5 Jun 2026.pdf PDF
Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
26-0709 CLEAN HVAC SYSTEMS - PROJECT DESCRIPTION.pdf PDF
UFGS 23 01 30.41.pdf PDF
ICRA 2.0 DHA Fillable Final (1).pdf PDF
26-0709 CLEAN HVAC SYSTEMS - ICRA 2.0 Clarifications.pdf PDF
Mech MACC RFP.pdf PDF
26-0709 CLEAN HVAC SYSTEMS - SUBMITTAL REGISTER.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
26-0709 CLEAN HVAC SYSTEMS - SOW.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 4

AMENDMENT NO. 0006 07/13/26 26-0709

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-26-R-9042

06/09/26

26-0709, Buildings 15, 326, DD48, G770, NH180, NH200 Clean HVAC Systems Amendment 0006, Respond to RFI's, Schedule a site visit & Extend Proposal Due Date.

The time and date for receipt of proposals is changed to 23 July 2026 at 1400.

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

N40085-26-R-9042 Amendment 0006

CONTINUATION SHEET

1. QUESTION: What percentage of the duct cleaning work will need to be completed after hours or on weekends (by building)?

ANSWER: NH200 and G770 have areas that will need to have the AHU’s cleaned on a continuous day/evening schedule to minimize business downtime.

2. QUESTION: Can the CCD be increased to 270 days after award?

ANSWER: The contract completion date will be increased to 180 calendar days after award. The Contractor shall incorporate into their proposal any costs necessary to expedite the procurement of long-lead materials in order to complete the statement of work within the 180-calendar day duration.

3. QUESTION: The three-month contract duration is too short. The tight spaces in some mechanical rooms would not help. We will have to get the modular AHU apart to remove the cooling coil to install the drain pan. There is long lead time for blower wheel to get them made in the manufacturer. We suggest the duration to be 9 months.

ANSWER: The contract completion date will be increased to 180 calendar days after award. The Contractor shall incorporate into their proposal any costs necessary to expedite the procurement of long-lead materials in order to complete the statement of work within the 180-calendar day duration.

4. QUESTION: Is work to be performed during daytime, evening and weekend hours?

ANSWER: NH200 and G770 have areas that will need to have the AHU’s cleaned on a continuous day/evening schedule to minimize business downtime.

5. QUESTION: Affected Paragraph 2.1 I and J Replace the disconnect on AHU 2 and 5 What needs to be replaced, a disconnect for the pump motor or, a starter or a drive that fed the AHU?

ANSWER: The Disconnect supplying power to the AHU.

6. QUESTION: Due to the restriction of clearance space of some mechanical rooms, especially in Bldg. 15. The clearance beside the coil at AHU is less than the coil width that would not allow to slide the coil out of the AHU to replace the drain pan. We have to disconnect the duct and disassemble the modular AHU to get the coil out to install the drain pan. Please advise if that needs to be done or not in this scope of work.

ANSWER: Refer to Statement of work.

7. QUESTION: The current system design is unknown to see if the conditions can be met for the temporary cooling without impacting the users. The total number and size of rooms served from the AHU is unknown. The size and length of duct serving the occupied spaces is unknown. CFM’s required per space is unknown. Is there available space for size of the temporary units needed to maintain the requirements in the scope of work? Is electrical available for the temporary cooling units? Electrical detail requirements are unknown due to the above.

ANSWER: All available drawings have been provided. It is the contractors responsibility to develop a plan on where they can install the spot coolers and if they have enough electricity to power them.

8. QUESTION: Temporary Cooling units that can meet the requirements are more than likely too large to be installed inside the building and are skid mounted. Please review and advise. Are the units we’re using at the NH100 acceptable based on the downtime?

ANSWER: Contractor can make an additional site visit on their own to determine if space is available.

9. QUESTION: DD48 AHU-2 mfg./model/serial number? Cooling coil size width, height, fins/in, connection sizes, gpm, water temps, required EAT and LAT?

ANSWER: Contractor can make an additional site visit to determine this information.

10. QUESTION: G770 AHU-1 OA Damper Size? Actuator voltage?

ANSWER: Contractor can make an additional site visit to determine this information.

11. QUESTION: NH180 AHU-1 &2 mfg./model/serial number? OA damper size/voltage?

Cooling coil size width, height, fins/in, connection sizes, gpm, water temps, required EAT and

LAT?

ANSWER: Contractor can make an additional site visit to determine this information.

12. QUESTION: The current system design is unknown to see if the conditions can be met for the temporary cooling without impacting the users. The total number and size of rooms served from the AHU is unknown.

ANSWER: See attached drawings.

13. QUESTION: The size and length of duct serving the occupied spaces is unknown.

ANSWER: See attached drawings.

14. QUESTION: CFM’s required per space is unknown.

ANSWER: See attached drawings.

15. QUESTION: Is there available space for size of the temporary units needed to maintain the requirements in the scope of work.

ANSWER: Contractor can make an additional site visit to determine if space is available.

16. QUESTION: Is electrical available for the temporary cooling units? Electrical detail requirements are unknown due to the above.

ANSWER: Contractor needs an additional site visit to determine if electrical needs are available.

17. QUESTION: Temporary Cooling units that can meet the requirements are more than likely too large to be installed inside the building and are skid mounted. Please review and advise.

ANSWER: Contractor can make an additional site visit to determine what spot coolers they need to use.

18. All other terms and conditions remain unchanged.

File details come from the government source that posted it. Updated .