Technical Amendment 0008 is a contract document for the P-7889 Dental Clinic Replacement project at Marine Corps Recruit Depot Parris Island, South Carolina. The amendment provides revised drawing details for multiple architectural elements, specifically updating wall sections, exterior wall details, finish schedules, and equipment schedules. The updated drawings are dated 04/21/25 and affect drawings with NAVFAC drawing numbers 12908981, 12908983, 12908984, 12909010, 12909054, 12909055, and 12909057, which cover sheets including wall sections (A-311, A-313, A-314), exterior wall details (A-501), and finish and equipment schedules (A-660, A-661, A-680).

The revised drawings include detailed specifications for wall construction, materials, insulation, finishes, and equipment mounting requirements. Key technical updates involve wall section configurations, brick veneer details, roof insulation specifications, metal stud framing, air barrier applications, and equipment mounting instructions. The amendment provides comprehensive technical guidance for contractors, specifying precise construction methods, material types, and installation standards for various building components of the new dental clinic facility.

View the file

Other files

File Type Posted
AMD 0010 - WD SC20250008.pdf PDF
N4008525R2500 AMD 0010.pdf PDF
N4008525R2500 AMD 0009.pdf PDF
USMC ESS_Standard Equip List-v6.1.xlsx XLSX spreadsheet
N4008525R2500 AMD 0008.pdf PDF
N4008525R2500 AMD 0007.pdf PDF
N4008525R2500 AMD 0006.pdf PDF
AMD 0006 - Technical Amendment 0008.pdf PDF
AMD 0005 - Technical Amendment 0007 Continuation Sheet.pdf PDF
AMD 0005 - 21-54-23019_CP CPT-2-PPD.xls XLS spreadsheet
AMD 0005 - CPT-1_forAPILE.xls XLS spreadsheet
AMD 0005 - 21-54-23019_SP CPT-1-PPD.xls XLS spreadsheet
AMD 0005 - Technical Amendment 0007.pdf PDF
AMD 0005 - 21-54-23019_CP CPT-2-BSC.XLS XLS spreadsheet
AMD 0005 - 21-54-23019_SP CPT-1 - VsResults.xlsx XLSX spreadsheet
N4008525R2500 AMD 0005.pdf PDF
AMD 0005 - 21-54-23019_SP CPT-1-BSC.XLS XLS spreadsheet
AMD 0005 - 21-54-23019 P-7889 Dental Clinic Replacment - Full Report.pdf PDF
N4008525R2500 AMD 0004.pdf PDF
Geo Tech portion P-7889 MCRD PARRIS ISLAND CORRECTED FINAL BASIS OF DESIGN - 26 AUGUST 2024.pdf PDF
674002.PDF PDF
3 of 23 Foundation Plan Building P-88-A (602).pdf PDF
602001.PDF PDF
4 of 23 Foundation Details Building P-88-A (602).pdf PDF
602002.PDF PDF
674001.PDF PDF
602003.PDF PDF
674003.PDF PDF
Technical Amendment 0006 Continuation Sheet.pdf PDF
100 Corrected Final Haz Mat Report B602 and B674 Parris Island - March 2024.pdf PDF
N4008525R2500 AMD 0003.pdf PDF
P7889 VISIT SITE SIGN IN SHEET.pdf PDF
N4008525R2500 AMD 0002.pdf PDF
Technical Amendment 0003.pdf PDF
Technical Amendment 0002.pdf PDF
Attachment C - Price Proposal Form REVISED.docx DOCX document
N4008525R2500 AMD 0001.pdf PDF
Technical Amendment 0004.pdf PDF
Attachment H - Small Business Subcontracting Plan.docx DOCX document
1686626dwg04of14_LANDSCAPE.pdf PDF
1686626dwg11of14_ELECTRICAL.pdf PDF
Attachment D - Construction Experience Data Sheet.docx DOCX document
1686626dwg12of14_AUDIOVISUAL.pdf PDF
Attachment G - Small Business Participation Commitment Document (SBPCD).docx DOCX document
1686626dwg08of14_PLUMBING.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
1686626dwg07of14_GENERAL SERIES.pdf PDF
Attachment C - Price Proposal Form.docx DOCX document
1686626dwg10of14_GENERAL SERIES.pdf PDF
1686626dwg02of14_LIFESAFETY.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL AMENDMENT 0008

NAVFAC ATLANTIC

CONTINUATION SHEET

SECTION 00 01 15 LIST OF DRAWINGS

The following Ambulatory Care Center drawings are revised as of 04/21/25. These revised drawings accompany this amendment.

NAVFAC DWG NO. SHEET NO. TITLE

12908981 A-311 WALL SECTIONS

12908983 A-313 WALL SECTIONS

12908984 A-314 WALL SECTIONS

12909010 A-501 EXTERIOR WALL DETAILS

12909054 A-660 FINISH SCHEDULE

12909055 A-661 FINISH SCHEDULE

12909057 A-680 EQUIPMENT SCHEDULE

-- End of Technical Amendment 0008 --

MICHAEL

CHILDS

KEVIN

RE

S

E G

SI T

R

A

T

E T

A

I

ADE CR H

C

E T

T

B

FO LA A

M

A

FIRST FLOOR

0"

SECOND FLOOR

16' - 0"

C

M U

C O

U R

S E

S

2' - 8"

A-501

A3

R E

V E

A L

2'

8'

6'

HSS TUBE - SEE

STRUCTURAL

CONCEALED

LINTEL SYSTEM

METAL SOFFIT

SYSTEM

BRICK COLUMN

(BEYOND)

PREFINISHED

METAL CAP

SHEET METAL

FLASHING

BRICK

(BEYOND SLAB

TO

FOUNDATION)

STEEL BEAM -

SEE

STRUCTURAL

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

3'

/2

COLUMN

FOOTING

BEYOND

5/8" GYPSUM

SHEATHING

F

LA

T A

R C

H O

P E

N

IN

G

FIRST FLOOR

0"

TOP OF SLAB

32' - 0"

SECOND FLOOR

16' - 0"

M

(2

C M

U C

O U

R S

E S

(2

C M

U C

O U

R S

E S

A-502

A1

A-622

C1

A-622

A4

A-500

C1

1'

(1

C M

U C

O U

R S

E S

8'

3/

8" 5'

/8

R E

V E

A L

2'

PRE-FINISHED METAL GUTTER

PRE-FINISHED

METAL FASCIA

PRE-FINISHED

METAL SOFFIT

PANEL ON 7/8" HAT

CHANNELS

CONCRETE FILL

ON METAL DECK

STEEL BEAM

CONCRETE FILL

ON METAL DECK

FINISHED CEILING

(SEE FINISH

SCHEDULE)

STEEL HSS

TUBE - SEE

STRUCTURAL

3 5/8" METAL

STUDS

5/8" GYP. BOARD

8" CMU

R-6.5 RIGID INSULATION

BRICK VENEER

(BASE COLOR)

AIR BARRIER

MASONRY VENEER ANCHORS

FINISHED FLOOR

& BASE - SEE

SCHEDULE

FINISHED FLOOR

& BASE - SEE

SCHEDULE

MAX. U-VALUE WALL

ASSEMBLY = 0.123

16" RIB PATTERN, STANDING SEAM

METAL ROOF, OVER UNDERLAYMENT,

OVER R-25 RIGID INSULATION , OVER

METAL ROOF DECK, OVER COLD FORMED

STEEL RAFTERS

6 1/2"

2'

6' - 8 5/8" 1' - 4" 1' - 4"

COLUMN FOOTING

BEYOND

BRICK COLUMN

BEYOND

SITE SLAB SEE CIVIL

8' - 0 5/8"

1' - 2 1/8"

VAPOR BARRIER

POROUS FILL

METAL PANEL

CEILING

FIRST FLOOR

0"

TOP OF SLAB

32' - 0"

SECOND FLOOR

16' - 0"

A-612

C1

A-612

C1

A-501

C1

A-501

A1

(2

C M

U C

O U

R S

E S

(2

C M

U C

O U

R S

E S

PRE-FINISHED METAL GUTTER

PRE-FINISHED METAL

DOWNSPOUT (BEYOND)

PRE-FINISHED

METAL FASCIA

PRE-FINISHED

METAL SOFFIT

PANEL ON 7/8" HAT

CHANNELS

8" STUD WALL

R-6.5 RIGID

INSULATION

BRICK VENEER

(BEYOND)

ALUMINUM

ARCHED

CURTAIN WALL

CONCRETE FILL

ON METAL DECK

STEEL BEAM

FINISHED

CEILING

2 1/2" METAL

STUDS

5/8" GYP. BOARD

FINISHED FLOOR

& BASE

BATT INSULATION

CURTAIN WALL

SYSTEM BEYOND

SEE SHEET A-620

PNL1 PANEL SYSTEM

BEYOND SEE FINISH

SCHEDULE

METAL WALL PANEL

SYSTEM ON 7/8" HAT

CHANNELS

METAL SOFFIT SYSTEM

ALUMINUM CURTAIN

WALL SYSTEM

SITE SLAB - SEE CIVIL

FOUNDATIONS

SEE STRUCTURAL

ALUMINUM

CURTAIN

WALL SYSTEM

(BEYOND)

STEEL BEAM

ROOF INSULATION

MINIMUM R-VALUE

= 25.0

ROOFING MEMBRANE ON

5" RIGID INSULATION ON

CONCRETE FILL ON METAL

DECK

A-623

C1

A-623

C4

16" RIB PATTERN, STANDING SEAM

METAL ROOF, OVER UNDERLAYMENT,

OVER R-25 RIGID INSULATION , OVER

METAL ROOF DECK, OVER COLD FORMED

STEEL RAFTERS

AIR BARRIER

CEILING AS

SCHEDULED

CONT. STL ANGLE

2 1/2"x2 1/2"x1/4" STL.

ANGLES AT 16" O.C.

WELD TO BEAM

5'

10 3/4"

/2

8" STL STUD

FRAMING AT 16" O.C.

R-6.5 RIGID INSULATION

AIR BARRIER

ALUM.

CLOSURE W/

SEALANT &

BACKER ROD

3/4" P.T. PLYWOOD

5/8" GYPSUM SHEATHING

3 5/8" STL STUD

FRAMING AT 16" O.C.

BATT INSULATION

BATT INSULATION

ALUM. CLOSURE W/

SEALANT & BACKER ROD

PNL4 PANEL

PNL4 PANEL

AT BALCONY

BEYOND

WINDOW AT

BALCONY

BEYOND

A-613

C3

A-613

C1

R O

U G

H O

P E

N

IN

G

5'

5'

GYP.

PILASTER

BEYOND

VAPOR BARRIER

POROUS FILL

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

SCALE: 3/8"=1'-0"

2' 4' 6' 877

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024 Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/1

/2

:5

: 3

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

3/8" = 1'-0"

A-311

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

W A

L L

S E

C T

IO

N

S

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12908981

JCV JCV KMC

LEJ

SCALE: 3/8" = 1'-0"A4 REF: A-122, A-204, A-822

WALL SECTION - STAGING AREA (FLAT OPENING)

SCALE: 3/8" = 1'-0"A1 REF: A-301

WALL SECTION - SECONDARY ENTRY

SCALE: 3/8" = 1'-0"A3 REF: A-203, A-251

WALL SECTION - VESTIBULE

T

E C

H A

M E

N D

4/

/2

JC

V

KEVIN

RE

S

E G

SI T

R

A

T

E T

A

I

ADE CR H

C

E T

T

B

FO LA A

M

A

FIRST FLOOR

0"

TOP OF SLAB

32' - 0"

SECOND FLOOR

16' - 0"

10 3/4"

1' - 9 1/4"

6'

5'

5'

A-622

A4

A-622

A1

A-500

C1

PRE-FINISHED

METAL GUTTER

PRE-FINISHED METAL

FASCIA

PRE-FINISHED METAL

SOFFIT PANEL ON 7/8"

HAT CHANNELS

ALUMINUM CURTAIN

WALL SYSTEM

FINISHED CEILING

SEE SCHEDULE

FINISHED FLOOR

& BASE - SEE

SCHEDULE

8" CMU

R-6.5 RIGID INSULATION

AIR BARRIER

16" RIB PATTERN, STANDING SEAM

METAL ROOF, OVER UNDERLAYMENT,

OVER R-25 RIGID INSULATION , OVER

METAL ROOF DECK, OVER COLD

FORMED STEEL RAFTERS

CONCRETE FILL ON

METAL DECK

STEEL BEAM

ROOF INSULATION

MINIMUM R-VALUE

= 25.0

MEMBRANE

ROOFING ON 5"

RIGID INSULATION

ON CONCRETE FILL

ON METAL DECK

FINISHED CEILING

SEE SCHEDULE

SEE FLOOR

PLAN FOR

WALL TYPE

6 1/2"

8" CMU

CONT. STL

ANGLE

2 1/2"x2 1/2"x1/4" STL.

ANGLES AT 16" O.C.

WELD TO BEAM

6 1/2"

3"2 1/2" METAL

STUDS

5/8" GYP. BOARD

PNL4 PANEL

5'

2 1/2" METAL

STUDS

5/8" GYP. BOARD

PNL4 PANEL

PNL4 PANEL

AT BALCONY

BEYOND

WINDOW SYSTEM AT

BALCONY BEYOND

STRUCTURAL

FOOTING SEE

STRUCTURAL

BOND BEAM SEE

STRUCTURAL

10 1/8"

FIRST FLOOR

0"

SECOND FLOOR

16' - 0"

S P

R

IN

G L

IN

E

7'

2' - 8"

2'

5'

A-506

B2

6" METAL STUD

FRAMING

CONCEALED

LINTEL SYSTEM

INSULATED

METAL SOFFIT

SYSTEM

BRICK ARCH

(BEYOND)

PREFINISHED

METAL CAP

SHEET METAL

FLASHING

SITE SLAB SEE

CIVIL

STEEL BEAM -

SEE STRUCTURAL

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

5/8" GYPSUM

SHEATHING

STRUCTURAL

FOOTING SEE

STRUCTURAL

R E

V E

A L

2'

BENT PLATE SEE

STRUCTURAL

BRICK PILASTER

BEYOND

FIRST FLOOR

0"

SECOND FLOOR

16' - 0"

6" METAL STUD

FRAMING

METAL SOFFIT

SYSTEM

PREFINISHED

METAL CAP

SHEET METAL

FLASHING

STEEL BEAM

SEE STRUCTURAL

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

STEEL COLUMN

SEE STRUCTURAL

CONCRETE

PEDESTAL

R E

V E

A L

2'

2'

/8

3'

/4

BRICK VENEER

(BASE COLOR)

BRICK CORBEL (VERTICAL

RUNNING BOND ACCENT

COLOR)

5/8" GYPSUM SHEATHING

6" METAL STUDS

1' - 6" 1' - 6"

2' - 0"

1.27:12 1.27:12

1 1

J.4

J.4

2' - 0"

PRE-FINISHED METAL CAP

PRE-FINISHED METAL

FLASHING BELOW

2' - 0"

2'

PRE-FINISHED PARAPET CAP BELOW

2'

1.25:12 1.25:12

1.

:1

1.

:1

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

SCALE: 3/8"=1'-0"

2' 4' 6' 877

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024

Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/1

/2

:5

: 3

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

As indicated

A-313

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

W A

L L

S E

C T

IO

N

S

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12908983

JCV SW KMC

LEJ

SCALE: 3/8" = 1'-0"A1 REF: A-113, A-133, A-251

WALL SECTION

SCALE: 3/8" = 1'-0"A2 REF: A-122, A-822

WALL SECTION

SCALE: 3/8" = 1'-0"A4 REF: A-122

WALL SECTION

SCALE: 1/2" = 1'-0"C4 REF: A-161, A-313

STAGING PILASTER CAP

T

E C

H A

M E

N D

4/

/2

KEVIN

RE

S

E G

SI T

R

A

T

E T

A

I

ADE CR H

C

E T

T

B

FO LA A

M

A

FIRST FLOOR

0"

SECOND FLOOR

16' - 0"

C1

A-204

C1

A-204

8"

8'

M A

S O

N R

Y O

P E

N

IN

G

2'

4'

A-622

C1

A-622

C4

A-163

B3

6" METAL STUD

FRAMING WITH

BATT

INSULATION METAL SOFFIT

SYSTEM

STEEL BEAM

MEMBRANE ROOFING ON BUILT UP

RIGID INSULATION ON CONCRETE FILL

ON METAL DECK

STEEL BEAM

BRICK CORBEL

(VERTICAL

RUNNING BOND

ACCENT COLOR)

EXTERIOR

CEILING FAN

FINISHED

CEILING - SEE

FINISH SCHEDULE

2 1/2" METAL STUDS

5/8" GYP. BOARD

8" CMU

R-6.5 RIGID INSULATION

FACE BRICK (BASE COLOR)

AIR BARRIER

1/2" SOLID SURFACE

SILL

ALUMINUM

CURTAIN WALL

SYSTEM

FINISHED FLOOR

& BASE - SEE

SCHEDULE

MAX. U-VALUE WALL

ASSEMBLY = 0.123

CAVITY DRAINAGE

THRU WALL FLASHING

WEEPS AT 24" O.C.

MEMBRANE ROOFING CRICKET ON

BUILT UP RIGID INSULATION (BEYOND)

A-314

C3

GROUT FILLED

CAVITY

FIRST FLOOR

0"

SECOND FLOOR

16' - 0"

H.6

8"

FINISHED

CEILING - SEE

FINISH SCHEDULE

2 1/2" METAL STUDS

5/8" GYP. BOARD

FINISHED FLOOR

& BASE - SEE

SCHEDULE

8" CMU

R-6.5 RIGID

INSULATION

FACE BRICK

(BASE COLOR)

AIR BARRIER

CAVITY DRAINAGE

THRU WALL FLASHING

WEEPS AT 24" O.C.

METAL SOFFIT

SYSTEM

STEEL BEAM

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

R-6.5 RIGID

INSULATION

AIR BARRIER

EXTERIOR GYPSUM

SHEATHING

A-314

C4

6" METAL STUD

CONCRETE - SEE

STRUCTURAL

MAX. U-VALUE WALL

ASSEMBLY = 0.123

GROUT FILLED CAVITY

SECOND FLOOR

16' - 0"

H.6

M T

L T

R A

C K

T O

F O

LL

O

W S

LO

P

E O

F D

E C

K

IN

G

V A

R

IE

S

1/ 2"

FACE BRICK (BASE COLOR)

METAL SOFFIT

SYSTEM

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

6" METAL

RUNNER TRACK

CONCRETE - SEE

STRUCTURAL

8" CMU

R-6.5 RIGID

INSULATION

AIR BARRIER

BOLT IN PLASTIC

SLEEVE - SEE

STRUCTURAL BATT

INSULATION

6" METAL STUD

EXTERIOR

GYPSUM.

SHEATHING

AIR BARRIER

6" METAL

RUNNER TRACK

STEEL BEAM- SEE

STRUCTURAL

FASTENER FROM

RUNNER TRACK

INTO CMU BLOCK

FASTENER FROM

RUNNER TRACK

INTO DECKING

ABOVE

FIRST FLOOR

0"

SECOND FLOOR

16' - 0"

F

CONCRETE - SEE

STRUCTURAL

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

STEEL BEAM- SEE

STRUCTURAL

FINISHED

CEILING - SEE

FINISH SCHEDULE

FINISHED

CEILING - SEE

FINISH SCHEDULE

1 5/8" METAL STUDS

5/8" GYP. BOARD

FINISHED FLOOR

& BASE - SEE

SCHEDULE

CLASSROOMRECRUIT PUB

TLT. F

BOLT IN PLASTIC

SLEEVE - SEE

STRUCTURAL

STEEL PLATE

SEE STRUCTURAL

1 5/8" METAL STUDS

3 5/8" METAL FRAMING

WITH BATT INSULATION

FIRST FLOOR

0"

2.2

RECRUIT PUB

TLT. F

1' - 5 3/4"

FINISHED

CEILING - SEE

FINISH SCHEDULE

CONCRETE SEE

STRUCTURAL

BOND BEAM SEE

STRUCTURAL

8'

2'

FINISHED

CEILING - SEE

FINISH SCHEDULE

FINISHED FLOOR

& BASE - SEE

SCHEDULE

FINISHED FLOOR

& BASE - SEE

SCHEDULE

SECOND FLOOR

16' - 0"

6" METAL

RUNNER TRACK

BATT

INSULATION

6" METAL STUD

EXTERIOR

GYPSUM.

SHEATHING

AIR BARRIER

6" METAL

RUNNER TRACK

FASTENER FROM

RUNNER TRACK

INTO DECKING

ABOVE

STEEL BEAM SEE

STRUCTURAL

FACE BRICK (BASE COLOR)

MEMBRANE ROOFING

ON BUILT UP RIGID

INSULATION ON

CONCRETE FILL ON

METAL DECK

8" CMU

R-6.5 RIGID

INSULATION

STEEL BEAM- SEE

STRUCTURAL

METAL SOFFIT

SYSTEM

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

SCALE: 1 1/2"=1'-0"

6" 1' 1'-6" 877

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024

Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/1

/2

:5

: 4

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

As indicated

A-314

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

W A

L L

S E

C T

IO

N

S

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12908984

JCV JCV KMC

LEJ

SCALE: 3/8" = 1'-0"A2 REF: A-114

WALL SECTION

SCALE: 3/8" = 1'-0"A4 REF: A-113, A-115

WALL SECTION

SCALE: 1 1/2" = 1'-0"C4 REF: A-113, A-115

SECTION DETAIL

SCALE: 3/8"=1'-0"

2' 4' 6'

SCALE: 3/8" = 1'-0"A1 REF: A-113

WALL SECTION

SCALE: 3/8" = 1'-0"C1 REF: A-113

WALL SECTION

SCALE: 1 1/2" = 1'-0"C3 REF: A-114

SECTION DETAIL

T

E C

H A

M E

N D

4/

9/

JC

V

T

E C

H A

M E

N D

4/

/2

KEVIN

RE

S

E G

SI T

R

A

T

E T

A

I

ADE CR H

C

E T

T

B

FO LA A

M

A

SECOND FLOOR

16' - 0"

1'

/8

2'

2'

1'

1'

1'

3 5/8" METAL

STUD FRAMING

STEEL

BEAM

MEMBRANE ROOFING

ON TAPERED

INSULATION ON

CONCRETE FILL ON

METAL DECK

CONCRETE FILL

ON METAL DECK

FACE BRICK (BASE COLOR)

BRICK SOFFIT

(STACKED BOND ACCENT COLOR)

VERTICAL RUNNING BOND

(ACCENT COLOR)

3/4" EXT GRADE

PLYWOOD

EXTEND ROOF

MEMBRANE UP

BACKSIDE OF PARAPET

3 5/8" STEEL STUD

FRAMING AT 16" O.C.

COUNTER FLASHING

4"

3/ 4"

3/4" EXT GRADE

PLYWOOD

P.T. BLOCKING

METAL PARAPET CAP ON SELF

ADHERING UNDERLAYMENT

1' - 4" 1' - 4"

3'

/4

20 GA. STEEL

SUPPORT ANGLES AT

4'-0" O.C. EACH WAY

2" COLD ROLLED

STEEL SUPPORT

SYSTEM

3"x3"x6"

20 GA. STEEL

ANGLE

METAL CEILING

SYSTEM

HAT CHANNELS

STEEL

TUBE

3 5/8" STEEL

STUD FRAMING

AT 16" O.C.

FACE BRICK

(BASE COLOR)

1/2" HEADER COURSE PROJECTION

1/2" VERTICAL RUNNING BOND PROJECTION

FIBERGLASS MATT FACED

GYPSUM SHEATHING

WEEPS AT 24" O.C.

W/ VENTILATORS

CONT. 6" WIDE SELF

ADHERING

TRANSITION STRIP

CONT. 1" WIDE S.S.

FLASHING TERMINATION

BAR W/ SEALANT

CONT. THRU WALL

FLASHING

CONCEALED

LINTEL SYSTEM

10'-0" A.F.F.

3 5/8" STEEL STUD BRACING

SEE STRUCTURAL

6" STEEL STUD

BRACING @ 16" O.C.

WEEPS AT 24" O.C.

1' - 4" 1' - 4"

VERTICAL RUNNING BOND CORBEL

(ACCENT COLOR)

HEADER COURSE (ACCENT COLOR)

HEADER COURSE (ACCENT COLOR)

VERTICAL RUNNING BOND CORBEL

(ACCENT COLOR)

HEADER COURSE (ACCENT COLOR)

WEEPS AT 24" O.C.

W/ VENTILATORS

CONT. THRU WALL

FLASHING

HORIZONTAL CONTROL JOINT

HORIZONTAL CONTROL JOINT

MASONRY VENEER ANCHOR

MASONRY VENEER ANCHOR

3/4" P.T. PLYWOOD

R-6.5 RIGID

INSULATION

CAVITY DRAINAGE

THRU WALL FLASHING

WEEPS AT 24" O.C.

AIR BARRIER

ROWLOCK BRICK

(ACCENT COLOR)

MASONRY VENEER

ANCHOR

MEMBRANE

ROOFING ON RIGID

INSULATION

5 3/8"

19'-0"

AFF

8" M

IN

1' - 9 1/4"

COUNTER FLASHING

2'

R .O

CONCRETE FILL

ON METAL DECK

A-623

C4

3' x 3' SPLASH PAD CAP SHEET AT

EACH DOWNSPOUT

TOP OF SLAB

32' - 0"

MASONRY VENEER

ANCHOR

3/4" P.T. PLYWOOD

AIR BARRIER

PRE-FINISHED METAL

GUTTER, 7"W. x 8"D.

PRE-FINISHED METAL

FASCIA

PRE-FINISHED METAL SOFFIT

PANEL ON 7/8" HAT CHANNELS

STEEL BEAM SEE

STRUCTURAL

VERTICAL STEEL ANGLE

AT EACH RAFTER

CONCRETE FILL

ON METAL DECK

16" RIB PATTERN, STANDING SEAM

METAL ROOF, OVER UNDERLAYMENT,

OVER R-25 RIGID INSULATION

2 1/2" STL. STUD

FRAMING

FIBERGLASS MATT FACED

GYPSUM SHEATHING

R-6.5 RIGID INSULATION

FLASHING

3/4" EXT. GRADE PLYWOOD

1/2" EXT. GRADE PLYWOOD

METAL ROOF DECK

CONT. STL. BENT

RAFTER CLOSURE

CONT. 16 GA. STL.

BENT ROOF CLOSURE

AIR BARRIER EXTENDS UP AND

ENGAGES ROOF UNDERLAYMENT

STEEL STUD BRACE AT

EACH RAFTER

1' - 9 1/4"

1/2"

1/2"

1/2"

4 1/2"

11 1/2"

1"4"

/2

F

IE

L

D V

E R

IF

Y

3' - 0 3/4"

3" 5"

1'

5 3/8"

FILL VOID WITH

MINERAL WOOL

SEALANT CONT. AT

PERIMETER OF SLAB

VERTICAL RUNNING BOND CORBEL

(ACCENT COLOR)

HEADER COURSE (ACCENT COLOR)

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

SCALE: 1 1/2"=1'-0"

6" 1' 1'-6" 877

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024

Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/1

/2

:5

: 4

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

1 1/2" = 1'-0"

A-501

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

E X

T E

R

IO

R W

A L

L D

E T

A

IL

S

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12909010

JCV JCV KMC

LEJ

SCALE: 1 1/2" = 1'-0"A3 REF: A-201, A-311

EXTERIOR DETAIL

SCALE: 1 1/2" = 1'-0"A1 REF: A-311

EXTERIOR DETAIL

SCALE: 1 1/2" = 1'-0"C1 REF: A-311

EXTERIOR DETAIL

T

E C

H A

M E

N D

4/

/2

ROOM FINISH SCHEDULE GENERAL NOTES

A. MANUFACTURER REFERENCES NOTED PROVIDE BASIS OF DESIGN FOR

MATERIALS, COLORS, AND PATTERN ONLY. PRODUCTS BY OTHER

MANUFACTURERS MAY BE ACCEPTABLE SUBJECT TO PROVIDING AN

ACCEPTABLE MATCH AND EQUAL COMPLYING REQUIREMENTS OF THE

SPECIFICATIONS. STANDARD RUNNING LINE PRODUCTS ONLY, NO CUSTOMS.

B. THE FINISH SCHEDULE LISTS THE ROOMS IN THE PROJECT. IT LISTS ROOM

NUMBERS WHICH ARE SHOWN ON THE ARCHITECTURAL FLOOR PLANS

CONTAINED IN THE A-100 AND Q-100 SHEET SERIES.

C. SEE REFLECTED CEILING PLANS ON THE A-800 SERIES SHEETS FOR ALL

CEILING HEIGHTS AND CONFIGURATIONS.

D. WINDOW SILLS TO BE SS2 - SOLID SURFACE.

E. REFER TO PLANS FOR CUBICLE CURTAIN LOCATIONS.

ABBREVIATIONS LEGEND

AT ACOUSTICAL CEILING TILE

BR BUMPER RAIL

CC CUBICLE CURTAIN

CG CORNER GUARD

CP CARPET TILE

CR CORRIDOR RAIL

CT CERAMIC TILE

EM ENTRANCE MAT

EXP EXPOSED

FP FOLDING PARTITION

IR INTEGRAL RUBBER SHEET BASE

LG LIQUID GLAZE COAT

PL PLASTIC LAMINATE

PT PAINT

RB RUBBER BASE

RS RUBBER SHEET

SCCS STATIC CONTROL CONCRETE SEALER

SCONC SEALED CONCRETE

SS SOLID SURFACE

STRD STAIR TREAD

WP WALL PROTECTION

FINISH SCHEDULE REMARKS

NOTE 1 CT2 SHALL BE USED WITHIN SHOWER STALLS ONLY. CT1 SHALL

BE USED IN THE REMAINDER OF THE ROOM.

NOTE 2 PROVIDE SEALED CONCRETE FLOOR BELOW ENTRANCE MAT.

NOTE 3 PROVIDE WALL TILE WITH COORDINATING TRIM AT MOP SINK.

NOTE 4 PROVIDE CT3, WALL TILE APPLICATION BEHIND WATER

FOUNTAINS.

NOTE 5 SOLID SURFACE COUNTERTOP & APRON TO BE SS5 WITH

VITEROUS CHINA UNDERMOUNT SINK .

NOTE 6 SEALED CONCRETE TREADS AND LANDINGS. RB2 APPLIED AT

LANDINGS. DO NOT PAINT STAIR NOSINGS. PAINT HANDRAILS,

STRINGERS, RISERS AND UNDERSIDE OF STRUCTURE PT10.

PAINT LEVEL 2 CEILINGS PT11.

NOTE 7 FINISHES LISTED ARE FOR ELEVATOR PIT AND SHAFT. SEE

COLOR DESIGN LEGEND, MISC INTERIOR FINISHES ON A-665

FOR PUBLIC AND STAFF ELEVATOR CAB FINISHES.

NOTE 8 PAINT FACE AND UNDERSIDE OF SOFFITS PT15.

NOTE 9 PROVIDE WP1 RIGID SHEET 6' AFF ON ALL WALLS OF ALCOVE

WITH TOP CAP MOLDING, ALIGN WITH TOP OF CORNER GUARDS.

NOTE 10 PROVIDE STRD1 MATERIAL FOR THE TREAD. SEE COLOR DESIGN

LEGEND, MISC. INTERIOR FINISH #9 ON SHEET A-665 FOR

HANDRAIL SYSTEM.

NOTE 11 PROVIDE RUBBER SHEET INTEGRAL BASE (IR) AROUND ALL

EXPOSED FACES OF FLOOR MOUNTED CASEWORK AND

MILLWORK. TRIM (IR) TO HEIGHT OF CASEWORK TOE KICK

WHEN APPLICABLE.

NOTE 12 PROVIDE RUBBER BASE (AS SCHEDULED) AROUND ALL

EXPOSED FACES OF FLOOR MOUNTED CASEWORK AND

MILLWORK. TRIM BASE TO HEIGHT OF CASEWORK TOE KICK

WHEN APPLICABLE.

NOTE 13 CASEWORK TO BE PL1/SS3 WITH SOLID SURFACE COUNTERS

WHEN APPLICABLE.

NOTE 14 CASEWORK TO BE CRS METAL WITH STAINLESS STEEL

COUNTERS WHEN APPLICABLE.

NOTE 15 CASEWORK TO BE CRS METAL WITH SOLID SURFACE

COUNTERS.

NOTE 16 REFER TO AF111 THRU AF141 FOR FLOOR AND WALL FINISH

INFORMATION.

NOTE 17 REFER TO ELEVATION SHEETS A-410 THRU A-416 FOR CT3 & 4

APPLICATION INFORMATION.

NOTE 18 PROVIDE METAL COVE, CORNER, AND/OR WAINSCOT TRIM FOR

WALL TILE. REFERENCE MISC. INTERIOR FINISHES #18 ON SHEET

A-665.

NOTE 19 PREP SLAB PER MANUFACTURERS INSTRUCTIONS. INSTALL

DIVIDER STRIPS WHERE NOTED ON PLANS IN BETWEEN

TERRAZZO COLORS AND AT NOTED LOCATIONS. POLISH

TERRAZZO TO A 200 GRIT. SEAL PER MANUFACTURERS

INSTRUCTIONS.

NOTE 20 CASEWORK TO BE CRS METAL WITH RESIN COUNTERS WHEN

APPLICABLE.

NOTE 21 REFER TO INTERIOR ELEVATIONS ON A-250 THRU A-252 FOR

WALL TILE APPLICATION AT WATER FOUNTAINS.

NOTE 22 REFER TO FINISH PLANS (AF SERIES SHEETS) FOR PNL DETAILS

AND LOCATIONS.

NOTE 23 REFER TO SHEET A-665 FINISH LEGEND, MISC INTERIOR

FINISHES #11 FOR FOLDING PARTITION INFORMATION.

NOTE 24 PAINT ACCESS PANEL TO MATCH SURROUNDING WALL COLOR.

NOTE 25 APPLY PNL3 (DECORATIVE FILM) TO FACE OF ALL GLAZING

PANELS @ INTERIOR WINDOWS W11, W12, & W13. SEE

INTERIOR ELEVATIONS ON SHEETS A-250 & A-252 FOR WHICH

SIDE OF GLAZING TO APPLY FILM.

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024 Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/2

/2

:2

: 0

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

3/8" = 1'-0"

A-660

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

F

IN

IS

H

S C

H E

D U

L E

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12909054

CBH TC CBH

LEJ

FINISH SCHEDULE - FIRST FLOOR

ROOM NO ROOM NAME

FLOOR BASE WALL CEILING

REMARKSCOLOR COLOR

NORTH EAST SOUTH WEST

FINISHCOLOR COLOR COLOR COLOR

1GS1 STAIR SCONC,EM1 RB2 PT1 PT1 PT1 PT1 - - - 2,6

1H01 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H02 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H03 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H04 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H05 DTR-GEN RS1,2 IR1,2 PT9 PT7,9 PT7 PT7 AT1 11,16

1H06 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H07 DTR - GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H08 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H09 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H10 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H11 ST TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1H12 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1H13 COMM RM SCCS RB2 PT1 PT1 PT1 PT1 EXP

1H14 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H15 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H16 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H18 DTR-GEN RS1,2 IR1,2 PT7 PT7,8 PT8 PT7 AT1 11,16

1H19 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H20 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H21 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1H22 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1H23 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

1H24 JAN CL SCONC CT3 PT7 PT7 CT3 PT7,CT3 PT11 3,16,17

1H25 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1HC1 CORRIDOR RS1,3 IR1,3 PT6 PT1 PT1 PT1 AT1 16

1HC2 CORRIDOR RS1,2 IR1,2 PT4 PT1 PT1 PT1 AT1 16

1J01 CAD/CAM MILLING RS1 IR1 PT7 PT7 PT7 PT8 AT1 11,14,16

1J02 MAIN COMM RM SCCS RB2 PT1 PT1 PT1 PT1 EXP

1J03 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1J04 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1J05 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1J06 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1J07 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1J08 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT7 PT8 AT1 11,16

1J09 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1J10 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT7 PT8 AT1 11,16

1J11 CAD/CAM MILLING RS1 IR1 PT7 PT9 PT7 PT7 AT1 11,14,16

1J12 DTR-GEN RS1,2 IR1,2 PT7 PT8 PT7 PT7 AT1 11,16

1J13 CBCT RS1 IR1 PT1 PT4 PT1 PT1 AT1 15,16

1J15 MECH SCONC RB2 PT1 PT1 PT1 PT1 EXP

1JC1 CORRIDOR RS1,3 IR1,3 PT6 PT6 PT1 PT6 AT1 12,15,16

1JC2 CORRIDOR RS1,2,3 IR1,2,3 PT6 PT3 - - - PT2 AT1 16

1JC3 CORRIDOR RS1 IR1 PT1 PT1 PT1 PT1 AT1 16

1JC4 CORRIDOR RS1,2,3 IR1,2,3 PT6 PT2 - - - PT4 AT1 16

1K01 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1K02 JAN CL SCONC CT3 PT7 PT7 CT3 PT7,CT3 PT11 3,16,17

1K03 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K04 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1K05 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K06 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1K07 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7,9 AT1 11,16

1K08 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1K09 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K10 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1K11 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K12 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

1K15 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

1K16 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K17 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K18 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K19 DTR-GEN RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

1K20 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1KC1 CORRIDOR RS1,3 IR1,3 PT6 PT1 PT1 - - - AT1 16

1KC2 CORRIDOR RS1,2 IR1,2 PT3 PT3 PT1 PT3 AT1 16

1L01 OIC 2ND DET CP1 RB2 PT1 PT1 PT5 PT1 AT1

1L02 LPO AND SUPER GEN DEN CP1 RB2 PT1 PT1 PT5 PT1 AT1

1L03 LCPO 2ND DET CP1 RB2 PT1 PT1 PT5 PT1 AT1

1L04 ST TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1L05 SMALL TEAMS CP1 RB2 PT1,5 PT5 PT1,5 PT1 AT1 16

1LC1 CORRIDOR RS1,3 RB1 PT6 PT1,6 PT1 PT1,3,6 AT1 16

FINISH SCHEDULE - FIRST FLOOR

ROOM NO ROOM NAME

FLOOR BASE WALL CEILING

REMARKSCOLOR COLOR

NORTH EAST SOUTH WEST

FINISHCOLOR COLOR COLOR COLOR

1A01 MECH SCONC RB2 PT1 PT1 PT1 PT1 EXP

1A01A MAIN ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

1A01B MAIN ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

1B01 VESTIBULE EM1 RB1 PT1 PT1 PT1 PT1 PT11 2

1B02 LOBBY TZ1,2,3,4 RB1 PT1,CT3,

PNL4,5

PNL1,4 PT1,PNL1,4,5 PT1,2, PNL5 PT11,15 4,8,16,17,18,19,22

1B03 RECRUIT PUB TLT, F CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 5,17,18

1B04 RECRUIT PUB TLT, M CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 5,17,18

1B05 RECRUIT PUB TLT, M CT1 CT3 CT3 CT3 PT7,CT3 PT7 PT11 5,17,18

1B07 RECRUIT PUB TLT, F CT1 CT3 CT3 PT7 PT7,CT3 PT7,CT3 PT11 5,17,18

1BC1 CORRIDOR TZ2 RB1 PT1,6,CT3,PN

L4,5

CT3 - - - CT3 PT11 4,16,17,18,19,21,22

1BS3 STAIR STRD1 - - - PT13,PNL2,3 PNL1,4 - - - PT1,PNL5 - - - 10,25

1C01 CLASSROOM RS4,5 RB2 PT2 PT1,2 PT1 PT1,2 AT1 16

1C01A RECRUIT IP/CLIN SPT CP1 RB2 PT1 PT5 PT1 PT1 AT1

1C01F ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

1C02 ELEV MACH SCONC RB2 PT1 PT1 PT1 PT1 EXP

1C03A RECEP CP1 RB2 PT2 PT1 PT1 PT1 AT1

1C03B RECORDS CP1 RB2 PT2 PT1 PT1 - - - AT1

1C03C RECRUIT CONTR CP1 RB2 - - - PT1 PT1 PT1 AT1

1C03D CONSULT OFC CP1 RB2 PT1 PT2 PT1 PT1 AT1

1C04 PANO-CEPH RS1 IR1 PT1 PT1 PT1 PT4 AT1 15,16

1C05 PANO-CEPH RS1 IR1 PT1 PT4 PT1 PT1 AT1 15,16

1C06 PANO-CEPH RS1 IR1 PT1 PT4 PT1 PT1 AT1 15,16

1C07 LOBBY TZ1,2,3,4 RB1 PT1,2, PNL1 PT1,PNL1 PT1,PNL1,CT

PT1,PNL1 PT2,6,11, AT2 4,16,17,18,19,21,22

1CC1 CORRIDOR TZ2,4 RB1 PNL1 PNL1 - - - - - - PT2,11,AT2 16,19,22

1CC2 CORRIDOR RS1,2 IR1,2 - - - PT1 PT1 PT2 AT1 16

1CE1 ELEVATOR 1 SCONC - - - - - - - - - - - - - - - - - - 7

1CE2 ELEVATOR 2 SCONC - - - - - - - - - - - - - - - - - - 7

1D01 VESTIBULE EM1 RB1 PT1 PT1 PT1 PT1 PT11 2

1D02 RECORD ASSEMBLY /

WORK

CP1 RB2 PT1 PT2 PT1 PT1 AT1

1D03 LOBBY TZ1,2,3,4 RB1 PT1,PNL1,4,5 PT1,2,PNL4 PT1,PNL1,4,5 PNL1,3,4 PT11,15 8,16,17,19,22

1D05 AD TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1D06 EQ STOR RS1 RB2 PT1 PT1 PT1 PT1 AT1

1D07 JAN CL SCONC CT3 PT7,CT3 PT7 PT7 PT7,CT3 PT11 3,16,17

1D08 COMM RM SCCS RB2 PT1 PT1 PT1 PT1 EXP

1D10 DEPT HEAD GEN/ASSIST CP1 RB2 PT1 PT1 PT5 PT1 AT1

1D11 DEPT HEAD GEN

DENTISTRY

CP1 RB2 PT5 PT1 PT1 PT1 AT1

1D13 RAD OFC CP1 RB2 PT1 PT1 PT5 PT1 AT1

1D14 CREDENTIALING DENTISTS CP1 RB2 PT1,5 PT5 PT1,5 PT1 AT1

1D15 SOIL UTIL RS1 IR1 PT7 PT7 PT7 PT7 AT1 11,14

1D16 EQ STOR RS1 IR1 PT1 PT1 PT1 PT1 AT1

1D17 MED WASTE RS1 IR1 PT7 PT7 PT7 PT7 AT1

1D18 GAS STOR SCONC RB2 PT7 PT7 PT7 PT7 PT12

1DC1 CORRIDOR TZ1 RB1 PT1 PT1,PNL5 - - - PT1,PNL5 PT11 16,19,22

1F01 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

1F02 ELEV MACH SCONC RB2 PT1 PT1 PT1 PT1 EXP

1F03 SUPPLY STOR RS1 RB2 PT1 PT1 PT1 PT1 AT1

1F04 MECH SCONC RB2 PT1 PT1 PT1 PT1 EXP

1F05 RECYCLE SCONC RB2 PT7 PT7 PT7 PT7 AT1

1FC1 CORRIDOR RS1,2 IR1,2 PT1 PT1 PT1 PT1 AT1 16

1FC2 CORRIDOR RS1 IR1 PT1,WP1 PT1 PT1 PT1 AT1 9,16

1FE3 ELEVATOR 3 SCONC - - - - - - - - - - - - - - - - - - 7

1FS2 STAIR SCONC,EM1 RB2 PT1 PT1 PT1 PT1 - - - 2,6

1G01 CLINIC MGR CP1 RB2 PT1 PT1 PT1,2 PT2 AT1

1G02 OPS OFFICER CP1 RB2 PT1 PT1 PT1,2 PT2 AT1

1G03 DIR DENTAL SVCS CP1 RB2 PT2 PT1 PT1 PT1,2 AT1

1G04 SEL OFC CP1 RB2 PT2 PT1 PT1 PT1 AT1

1G05 TEAM COLLAB CP1 RB2 PT2 PT1 PT1 PT1 AT1

1G06 MANAGED CARE CP1 RB2 PT1 PT1 PT2 PT1 AT1

1G07 LPCO CLINIC CP1 RB2 PT1 PT1 PT2 PT1 AT1

1G10 LACT RM RS1 RB2 PT1 PT1 PT1 PT2 AT1 12,13

1G11 ST TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

1GC1 CORRIDOR CP1 RB1 PT2 PT1,2 PT1 PT1 AT1 16

1GC2 CORRIDOR CP1 RB1 PT2 PT1 PT1 PT1 AT1 16

1GC3 CORRIDOR RS1,2,3 RB1 PT6 PT4 PT1 PT1 AT1 16

1GC4 CORRIDOR RS1,2 RB1 PT1 PT1 PT1 PT1 AT1 16

T

E C

H A

M E

N D

4/

/2

JC

V

ROOM FINISH SCHEDULE GENERAL NOTES

A. MANUFACTURER REFERENCES NOTED PROVIDE BASIS OF DESIGN FOR

MATERIALS, COLORS, AND PATTERN ONLY. PRODUCTS BY OTHER

MANUFACTURERS MAY BE ACCEPTABLE SUBJECT TO PROVIDING AN

ACCEPTABLE MATCH AND EQUAL COMPLYING REQUIREMENTS OF THE

SPECIFICATIONS. STANDARD RUNNING LINE PRODUCTS ONLY, NO CUSTOMS.

B. THE FINISH SCHEDULE LISTS THE ROOMS IN THE PROJECT. IT LISTS ROOM

NUMBERS WHICH ARE SHOWN ON THE ARCHITECTURAL FLOOR PLANS

CONTAINED IN THE A-100 AND Q-100 SHEET SERIES.

C. SEE REFLECTED CEILING PLANS ON THE A-800 SERIES SHEETS FOR ALL

CEILING HEIGHTS AND CONFIGURATIONS.

D. WINDOW SILLS TO BE SS2 - SOLID SURFACE.

E. REFER TO PLANS FOR CUBICLE CURTAIN LOCATIONS.

ABBREVIATIONS LEGEND

AT ACOUSTICAL CEILING TILE

BR BUMPER RAIL

CC CUBICLE CURTAIN

CG CORNER GUARD

CP CARPET TILE

CR CORRIDOR RAIL

CT CERAMIC TILE

EM ENTRANCE MAT

EXP EXPOSED

FP FOLDING PARTITION

IR INTEGRAL RUBBER SHEET BASE

LG LIQUID GLAZE COAT

PL PLASTIC LAMINATE

PT PAINT

RB RUBBER BASE

RS RUBBER SHEET

SCCS STATIC CONTROL CONCRETE SEALER

SCONC SEALED CONCRETE

SS SOLID SURFACE

STRD STAIR TREAD

WP WALL PROTECTION

FINISH SCHEDULE REMARKS

NOTE 1 CT2 SHALL BE USED WITHIN SHOWER STALLS ONLY. CT1 SHALL

BE USED IN THE REMAINDER OF THE ROOM.

NOTE 2 PROVIDE SEALED CONCRETE FLOOR BELOW ENTRANCE MAT.

NOTE 3 PROVIDE WALL TILE WITH COORDINATING TRIM AT MOP SINK.

NOTE 4 PROVIDE CT3, WALL TILE APPLICATION BEHIND WATER

FOUNTAINS.

NOTE 5 SOLID SURFACE COUNTERTOP & APRON TO BE SS5 WITH

VITEROUS CHINA UNDERMOUNT SINK .

NOTE 6 SEALED CONCRETE TREADS AND LANDINGS. RB2 APPLIED AT

LANDINGS. DO NOT PAINT STAIR NOSINGS. PAINT HANDRAILS,

STRINGERS, RISERS AND UNDERSIDE OF STRUCTURE PT10.

PAINT LEVEL 2 CEILINGS PT11.

NOTE 7 FINISHES LISTED ARE FOR ELEVATOR PIT AND SHAFT. SEE

COLOR DESIGN LEGEND, MISC INTERIOR FINISHES ON A-665

FOR PUBLIC AND STAFF ELEVATOR CAB FINISHES.

NOTE 8 PAINT FACE AND UNDERSIDE OF SOFFITS PT15.

NOTE 9 PROVIDE WP1 RIGID SHEET 6' AFF ON ALL WALLS OF ALCOVE

WITH TOP CAP MOLDING, ALIGN WITH TOP OF CORNER GUARDS.

NOTE 10 PROVIDE STRD1 MATERIAL FOR THE TREAD. SEE COLOR DESIGN

LEGEND, MISC. INTERIOR FINISH #9 ON SHEET A-665 FOR

HANDRAIL SYSTEM.

NOTE 11 PROVIDE RUBBER SHEET INTEGRAL BASE (IR) AROUND ALL

EXPOSED FACES OF FLOOR MOUNTED CASEWORK AND

MILLWORK. TRIM (IR) TO HEIGHT OF CASEWORK TOE KICK

WHEN APPLICABLE.

NOTE 12 PROVIDE RUBBER BASE (AS SCHEDULED) AROUND ALL

EXPOSED FACES OF FLOOR MOUNTED CASEWORK AND

MILLWORK. TRIM BASE TO HEIGHT OF CASEWORK TOE KICK

WHEN APPLICABLE.

NOTE 13 CASEWORK TO BE PL1/SS3 WITH SOLID SURFACE COUNTERS

WHEN APPLICABLE.

NOTE 14 CASEWORK TO BE CRS METAL WITH STAINLESS STEEL

COUNTERS WHEN APPLICABLE.

NOTE 15 CASEWORK TO BE CRS METAL WITH SOLID SURFACE

COUNTERS.

NOTE 16 REFER TO AF111 THRU AF141 FOR FLOOR AND WALL FINISH

INFORMATION.

NOTE 17 REFER TO ELEVATION SHEETS A-410 THRU A-416 FOR CT3 & 4

APPLICATION INFORMATION.

NOTE 18 PROVIDE METAL COVE, CORNER, AND/OR WAINSCOT TRIM FOR

WALL TILE. REFERENCE MISC. INTERIOR FINISHES #18 ON SHEET

A-665.

NOTE 19 PREP SLAB PER MANUFACTURERS INSTRUCTIONS. INSTALL

DIVIDER STRIPS WHERE NOTED ON PLANS IN BETWEEN

TERRAZZO COLORS AND AT NOTED LOCATIONS. POLISH

TERRAZZO TO A 200 GRIT. SEAL PER MANUFACTURERS

INSTRUCTIONS.

NOTE 20 CASEWORK TO BE CRS METAL WITH RESIN COUNTERS WHEN

APPLICABLE.

NOTE 21 REFER TO INTERIOR ELEVATIONS ON A-250 THRU A-252 FOR

WALL TILE APPLICATION AT WATER FOUNTAINS.

NOTE 22 REFER TO FINISH PLANS (AF SERIES SHEETS) FOR PNL DETAILS

AND LOCATIONS.

NOTE 23 REFER TO SHEET A-665 FINISH LEGEND, MISC INTERIOR

FINISHES #11 FOR FOLDING PARTITION INFORMATION.

NOTE 24 PAINT ACCESS PANEL TO MATCH SURROUNDING WALL COLOR.

NOTE 25 APPLY PNL3 (DECORATIVE FILM) TO FACE OF ALL GLAZING

PANELS @ INTERIOR WINDOWS W11, W12, & W13. SEE

INTERIOR ELEVATIONS ON SHEETS A-250 & A-252 FOR WHICH

SIDE OF GLAZING TO APPLY FILM.

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024

Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/2

/2

:2

: 1

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

3/8" = 1'-0"

A-661

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

F

IN

IS

H

S C

H E

D U

L E

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12909055

CBH TC CBH

LEJ

FINISH SCHEDULE - SECOND FLOOR

ROOM NO ROOM NAME

FLOOR BASE WALL CEILING

REMARKSCOLOR COLOR

NORTH EAST SOUTH WEST

FINISHCOLOR COLOR COLOR COLOR

2H03 DTR-ENDO RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2H04 DTR-ENDO RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2H05 DTR-ENDO RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2H06 DTR-ENDO RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2H07 LPO ENDO/PERIO/INPROC CP1 RB2 PT1 PT5 PT1 PT1 AT1

2H08 CBCT RS1 RB2 PT1 PT1 PT1 PT1,2 AT1 15,16

2H10 DTR-COMP RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2H11 ENDO PROVIDERS CP1 RB2 PT1 PT5 PT1 PT1 AT1

2H12 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

2H15 COMM RM SCCS RB2 PT1 PT1 PT1 PT1 EXP

2H16 DTR-PERIO RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2H17 DTR-PERIO RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2H18 PERIO OFC CP1 RB2 PT1 PT1 PT1 PT5 AT1

2H19 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

2H20 STORAGE CP1 RB2 PT1 PT1 PT1 PT1 PT11

2HC1 CORRIDOR RS1,3 IR1,3 PT6 PT1 PT1 PT1 AT1 16

2HC2 CORRIDOR RS1,2 IR1,2 PT4 PT1 PT2 PT1 AT1 16

2J01 CLASSROOM,

TABLE/CHAIR

CP1 RB2 PT3 PT1,3 PT1 PT1,3 AT1 16,23

2J01A CONF RM CP1 RB2 PT3 PT1 PT1 FP AT1 16,23

2J03 COMM RM SCCS RB2 PT1 PT1 PT1 PT1 EXP

2J05 DTR-OS RS1 IR1 PT7 PT7 PT7,8 PT8 PT12 11,15,16

2J06 DTR-OS RS1 IR1 PT7,8 PT8 PT7,8 PT7 PT12 11,15,16

2J10 DTR-OS RS1 IR1 PT7 PT7 PT9 PT7 PT12 11,15,16

2J11 DTR-OS RS1 IR1 PT9 PT7 PT7 PT7 PT12 11,15,16

2J14 MED PREP RS1 IR1 PT1 PT1 PT1 PT1 AT1 11,15,16

2JC1 CORRIDOR RS1,3 IR1,3 PT6 PT5,6 PT5 PT5,6 AT1 15,16

2JC2 CORRIDOR RS1,2,3 IR1,2,3 - - - PT3 - - - PT5 AT1 16

2JC3 CORRIDOR RS1,2,3 IR1,2,3 - - - PT5 - - - PT4 AT1 16

2JC4 CORRIDOR RS1 IR1 PT1,WP1 PT1,WP1 PT1,WP1 PT1 AT1 9,16

2K01 AD TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

2K02 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

2K03 DTR- PROST RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2K04 DTR-COMP RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2K05 DTR- PROST RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2K06 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2K07 DTR- PROST RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2K08 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2K09 CAD/CAM ALC RS1 RB2 PT2 PT1 PT1 PT1 AT1

2K10 DTR-GEN RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

2K11 DTR- PROST RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2K12 TEAM COLLAB CP1 RB2 PT1 PT5 PT1 PT1 AT1

2K15 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

2K16 ORAL SURGEONS CP1 RB2 PT5 PT1 PT1 PT1 AT1

2K17 DEPT HEAD SPEC

DENTISTRY

CP1 RB2 PT1 PT1 PT1 PT5 AT1

2K19 PROSTH/PERIO

PROVIDERS

CP1 RB2 PT1 PT1 PT1 PT5 AT1

2K20 LPO PROSTH/OS CP1 RB2 PT1 PT1 PT1 PT5 AT1

2KC1 CORRIDOR RS1,3 IR1,3 PT6 PT1 PT1 - - - AT1 16

2KC2 CORRIDOR RS1,2 RB1 PT3 PT1 PT1 PT1 AT1 16,24

2L01 DENTAL LABORATORY RS1 IR1 PT9 PT7 PT7 PT7,9 AT1 11,14,16

2L02 5 AXIS MILLING RS1 IR1 PT1 PT1 PT1 PT1 AT1 11,14

2L03 LAB EQ STOR RS1 IR1 PT1 PT1 PT1 PT1 AT1

2L04 CERAMICS LAB RS1 IR1 PT7 PT7 PT7 PT7 AT1 20

2L05 JAN CL SCONC CT3 PT7 CT3 PT7,CT3 PT7 PT11 3,16

2LC1 CORRIDOR RS1,3 RB1 PT1 PT1 PT1,3 PT3 AT1 16

FINISH SCHEDULE - SECOND FLOOR

ROOM NO ROOM NAME

FLOOR BASE WALL CEILING

REMARKSCOLOR COLOR

NORTH EAST SOUTH WEST

FINISHCOLOR COLOR COLOR COLOR

2A02 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

2A03 JAN CL SCONC RB2 PT1 PT1 PT1 PT1 PT11

2A04 MECH SCONC RB2 PT1 PT1 PT1 PT1 EXP

2A05 F LOCKERS CT1 CT3 PT7 PT7 PT7 PT7 PT12

2A05A F TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 5,17,18

2A05B F SHOWER CT1,2 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT12 1,17,18

2A05C SCRUB ALC CT1 CT3 PT7 PT7 PT7 PT7 PT12

2A06 SCRUB ALC CT1 CT3 PT7 PT7 PT7 PT7 PT12

2A07 LOCKER VESTIBULE CT1 CT3 PT7 PT7 PT7 PT7 PT12

2A08 M TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT12 5,17,18

2AC1 CORRIDOR RS1 RB1 PT1 PT1 PT1 PT2 AT1 16

2AS1 STAIR SCONC RB2 PT1 PT1 PT1 PT1 PT11 6

2B01 M LOCKERS CT1 CT3 PT7 PT7 PT7 PT7 PT12

2B01A M SHOWER CT1,2 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT12 1,17,18

2B02 DTR-OH RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11

2B03 DTR-OH RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11

2B04 DTR-OH RS1,2 IR1,2 PT7 PT7,8 PT8 PT7 AT1 11,16

2B05 DTR-OH RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11

2B06 JAN CL SCONC CT3 PT7 PT7,CT3 CT3 PT7 PT11 3,16,17

2B07 TEAM COLLAB CP1 RB2 PT1 PT5 PT1 PT1 AT1

2BS3 STAIR STRD1 RB1 PT13, PNL3 PNL1,3 - - - PT1 PT11 10,25

2C01 DTR-OS RS1 IR1 PT7 PT7 PT7 PT8 PT12 11,15

2C02 DTR-OS RS1 IR1 PT7 PT8 PT7 PT7 PT12 11,15

2C04 WORKROOM PREP RS1 IR1 PT7 PT7 PT7 PT7 AT1 11,14

2C05 DTR-OS RS1 IR1 PT9 PT7 PT7 PT7 PT12 11,15

2C06 DTR-OS RS1 IR1 PT7 PT7 PT9 PT7 PT12 11,15

2C08 DTR-OS RS1 IR1 PT7 PT7 PT8 PT7 PT12 11,15

2C09 RECOVERY RS1 RB2 PT9 PT7 PT7 PT7 AT1

2C10 LOBBY TZ1,2,4 RB1 PT1,CT3,PNL

PT1,PNL1,3 PT1,PNL1 PT1,PNL1,3 PT11 16,19,21,22,25

2C15 PT TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

2CC1 CORRIDOR RS1 IR1 PT1,WP1 PT1,WP1 PT1,WP1 PT1,WP1 PT11,AT1 9,16

2CC2 CORRIDOR RS1 IR1 PT1,WP1 PT1,WP1 PT1,WP1 PT1 PT11,AT1 9,16

2CC3 CORRIDOR TZ1,2,4 RB1 PT1 PT1 - - - PT1 PT11 16,19,22

2CC4 CORRIDOR TZ1,2,4 RB1 PT1 PT1 - - - PT1,PNL1 PT11 16,19,22

2CE1 ELEVATOR 1 SCONC - - - - - - - - - - - - - - - - - - 7

2CE2 ELEVATOR 2 SCONC - - - - - - - - - - - - - - - - - - 7

2D01 STER STOR RS1 IR1 PT7 PT7 PT7 PT7 PT12 11,14

2D02 STERILIZATION RS1 IR1 PT7 PT7 PT7 PT7 PT12 11,14

2D03 DECON RS1 IR1 PT7 PT7 PT7 PT7 PT12 11,14

2D05 CMS CUB CP1 RB2 PT1 PT2 PT1 PT1 AT1

2D06 DENTAL MECH SCONC RB2 PT1 PT1 PT1 PT1 EXP

2D07 COMM RM SCCS RB2 PT1 PT1 PT1 PT1 EXP

2DC1 CORRIDOR RS1 IR1 - - - PT1 PT1 PT1 AT1 16

2F01 SL LINEN RS1 IR1 PT1 PT1 PT1 PT1 AT1

2F02 SOIL UTIL RS1 IR1 PT7 PT7 PT7 PT7 AT1 11,14

2F03 ELEC SCONC RB2 PT1 PT1 PT1 PT1 EXP

2F04 RECYCLE SCONC RB2 PT7 PT7 PT7 PT7 AT1

2F05 MECH SCONC RB2 PT1 PT1 PT1 PT1 EXP

2F06 SPECIALTY SUPP STOR RS1 RB2 PT1 PT1 PT1 PT1 AT1

2F07 ST TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

2F08 BIOMED RS1 IR1 PT1 PT1 PT2 PT1 AT1 16

2FC1 CORRIDOR RS1,2 RB1 PT2 PT1 PT1 - - - AT1 16

2FC2 CORRIDOR RS1 RB1 PT1,WP1 PT1 PT1 PT1 AT1 16

2FE3 ELEVATOR 3 SCONC - - - - - - - - - - - - - - - - - - 7

2FS2 STAIR SCONC RB2 PT1 PT1 PT1 PT1 PT11 6

2G01 ST TLT CT1 CT3 CT3,4 CT3,4 CT3,4 CT3,4 PT11 17,18

2G02 LOUNGE RS1 RB2 PT2 PT1 PT1 PT1 AT1 12,13

2G03 TEAM WORK CP1 RB2 PT1 PT1 PT1 PT2 AT1

2GC1 CORRIDOR RS1,2 RB1 PT1 PT1,WP1 PT1,WP1 PT1,WP1 AT1 9,16

2GC2 CORRIDOR RS1,2,3 RB1 PT1 PT4 PT1 PT1 AT1 16

2H01 DTR-ENDO RS1,2 IR1,2 PT9 PT7 PT7 PT7 AT1 11,16

2H02 DTR-ENDO RS1,2 IR1,2 PT7 PT7 PT8 PT7 AT1 11,16

T

E C

H A

M E

N D

4/

/2

JC

KEVIN

RE

S

E G

SI T

R

A

T

E T

A

I

ADE CR H

C

E T

T

B

FO LA A

M

A

A

B

C

D

1 2 3 4

1 2 3 4

A

B

C

D

SCALE:

PROJECT NO:

CONSTR CONTR NO:

NAVFAC DRAWING NO:

SHEET: OF

FIRE PROTECTION

CHIEF ENG/ARCH

BRANCH MGR

PM/DM

DES DRW CHK

SATISFACTORY TO DATE

ACTIVITY

FOR COMMANDER NAVFAC

APPROVED

A/E INFO

SEAL

S Y

M D

E S

C R

IP

T

IO

N

D A

T E

A P

P R

08/19/2024

P A

R R

IS

I S

L A

N D

S

C M

C R

D

P A

R R

IS

I S

L A

N D

N A

V A

L S

T A

T

IO

N

N O

R F

O L

K

V A

D E

P A

R T

M E

N T

O F

T H

E N

A V

Y N

A V

A L

F A

C

IL

IT

IE

S E

N G

IN

E

E R

IN

G

S Y

S T

E M

S C

O M

M A

N D

M

ID

L A

N T

D C

C O

R E

MT / SVR

EJA

DSN

Approved by Jason J. Root, NAVFAC / MFPO VIA SAT-TO Memo Dated 08/08/2024

Tracey Bond, Defense Health Agency VIA SAT-TO Memo Dated 08/19/2024

/2

/2

:2

: 1

P M

C

U s e rs \j u lia n

.v id a \D o c u m e n ts

\2

.0

A ju l ia n .v id a

.r v t

A-680

P-7889

D E

N T

A L

C L

IN

IC

R E

P L

A C

E M

E N

T

E Q

U

IP

M E

N T

S C

H E

D U

L E

N A

V A

L F

A C

IL

IT

IE

S

E N

G

IN

E E

R

IN

G C

O M

M A

N D

M

ID

-A T

L A

N T

IC

12909057

JCV JCV KMC

LEJ

EQUPMENT SCHEDULE

JSN DESCRIPTION LOG CAT REMARKS

CW090 Cabinet, Floor Standing, 5 SH, 2 GDO, ST, 95x36x16 A A4

CW100 Cabinet, Floor Standing, 5 SH, 2 GDO, ST, 95x48x16 A A4

D0680 Console, Accessory/Side, Dental Operatory A A4

D0682 Cabinet, Dispensing, Dental Operatory, Wall MNTD A A4

D0685 Cabinet, Storage, Dental Operatory, Wall MNTD A A4

D0755 Tank Assembly, Boilout/Curing, Double A A4

D0760 Guard, Casting Machine, 13" High x 18" Diameter A

D0900 Workstation, Dental Lab, Receiving A

D0904 Workstation, Dental Lab, Tech, Single Station A

D0925A Hood, Fume, Floor Standing, Walk-in A

D0930 Workstation, Dental Lab, Casting A

D0942 Workstation, Dental Lab, Microblasting A

D6150 Light, Dental, Operating, Dual, Ceiling Mounted A A16

D6155 Light, Dental, Operating, Ceiling, Column A A17

D7090 Utility Center, Dental, Floor Mounted A

D7090R Utility Center, Dental, Recessed A

D8650 Chute, Waste, Plaster, Counter Mounted A

D9055 Valve, Control, Water A

D9056 Valve, Air, Needle Control A

D9057 Valve, Gas, Needle Control A

D9280 Legs, Rail, Apron A

F3105 Safe, F/S , Class 5 A

M2010 Cabinet, Storage, Acid, Undercounter A

P2000 Eyewash, Wall Mounted, Hands-Free A A1

P2450 Valve, Mixing, Thermostatic A

P2451 Valve, Mixing, Thermostatic, Eyewash A

P3000 Lavatory, Vitreous China, Straight Back A A1

P3070 Lavatory, Vitreous China, Under counter Mtd A

P3070S Lavatory, Vitreous China, Under counter Mtd w/ Auto infared sensor faucet A

P3100 Lavatory, Vitreous China, Slab Type A A1

P4700 Sink, Mop, Molded Stone A A9

P5040 Shower, Single, Hand-Held A A1

P5210 Shower, Safety, Freestanding, With Eye/Face Wash A

P6500 Sink, Service, Cast Iron A A1

P6950 Sink, Scrub, With Knee Valve A A1

P7650 Trap, Plaster, Small A

P8150 Urinal, Wall Hung (H/C Mount Height) A A1

P8150H Urinal, Wall Hung (H/C Mount Height) A A1

P8710 Utility Center, Plumbing Connections (includes cover) A

P8711 Connection Box, Icemaker A

P9050 Toilet, Wall Hung, Siphon Jet A A1

P9050H Toilet, Wall Hung, Siphon Jet - ABA A A1

S0237 Sterilizer,ELEC,VAC,2DO,RCSD 1WLL, 20 x 20 x 38 Chmbr A

S0290 Rack, 2SH, 20 x 20 x 38 Chmbr A

S0295 Loading Car & Transfer Carriage, 20 x 20 x 38 Cham A

S0960E Washer/Disinfector,Elec,2Dr,Rcsd 1Wall 26 x 24 x 24 Chmbr A

S0965 Washer/Disinfector, Dental A

S1900A Window, Pass-Thru, Automated A

S1900E Window, Pass-Thru, Automated A

UL225 Snorkel Exhaust A CHECK

UR221 Fountain, Water, CRS, Wall Mounted, 2 Level, Bottle Fill Station A A1

UR223 Bottle Filling Station, Indoor, Wall Mount A

US960 Chemistry Delivery System A

X3150 Rack, Apron/Gloves, Wall Mounted A A1; A2

EQUPMENT SCHEDULE

JSN DESCRIPTION LOG CAT REMARKS

A1067 Mirror, Float Glass, ADA Accessible A A1, A3

A1080 Mirror, Posture, Wall Mounted A A1, A3

A1195P Counter, Cleanup, 3 Sinks, Adj Height, 97.5in, R to L A

A4995 Table, Diaper Changing, Wall Mounted A A1; A2

A5017 Bench, Dressing Room, Fixed, 24"H X 48"W A A11

A5030 Bench, Stall, Shower, Built In A A8

A5080 Dispenser, Paper Towel, SS, Surface Mounted A

A5082 Dispenser, Paper Towel, Sensor, Hands Free A

A5090 Disposal, Sanitary Napkin, SS, Surface Mounted A A1, A3

A5110 Grab Bar, 1-1/4" Dia., SS, 2 Wall, Shower Use A A1, A7

A5116 Grab Bar, 1-1/4" Dia., SS, 2 Wall, W/C Accessible A A1, A7

A5119 Grab Bar, Ss, 1-1/4 Dia 42 Inch Straight A A1, A7

A5135 Shelf, Utility W/ Mop/Broom Holders, SS, Surf Mntd A A1; A2

A5145 Hook, Garment, Double, SS, Surface Mounted A A6

A5160 Shelf, 8" Depth, SS, Surface Mounted A A1; A2

A5170 Rod, Shower Curtain, 1"Diameter A A5

A5180 Track, Cubicle, Surface Mounted, With Curtain A A15

A5200 Dispenser, Toilet Tissue, SS, 2-Roll, Surface Mntd A A1, A3

A5205V Bar, Towel, 1" Diameter, SS, Surface Mounted A A1, A3

A5210A Bracket, Television, Flat, Wall Mounted, 86" A A1, A10

A5210C Bracket, Television, Ceiling Mounted for flat screens A A18

A6030 Machine, Vending D

A6105 Counter, Reception Control, Built-In A

A6309 Shades, Window A

A6309A Shades, Window, Blackout A

C01D0 Cabinet, U/C/B, 4 Drawer, 36x18x22 A

C02D0B Cabinet, U/C/B, 4 Drawer, 32x24x22 A A4

C03H0 Cabinet, U/C/B, 2 Half Drawers, 3 DR, 36x30x22 A A4

C03J0 Cabinet, U/C/B, 8 Half Drawers, 36 x 30 x 22 A A4

C03P0 Cabinet, Sink, U-C-B, 2 Door, 30in W A A4

C03P0B Cabinet, Sink, U-C-B, 2 Door, 32 x 30 x 22 A A4

C04E0B Cabinet, U/C/B, 1 Shelf, 1 Drawer, 2 DO, 36x30x22 A A4

C04F0 Cabinet, U/C/B, 1 Shelf, 2 Half DR, 2 DO, 36x36x22 A A4

C04H0 Cabinet, U/C/B, 2 Half Drawer, 3 Drawer, 36x36x22 A A4

C04J0 Cabinet, U/C/B, 8 Half Drawer, 36x36x22 A A4

C04L0 Cabinet, U/C/B, 1 DR, 3 Half DR, 1 Door, 36x36x22 A A4

C04P0 Cabinet, Sink, U/C/B, 2 Door, 36x36x22 A A4

C04P0B Cabinet, Sink, U/C/B, 2 Door, 32x36x22 A A4

C05H0 Cabinet, U/C/B, 2 Half Drawer, 3 Drawer, 36x48x22 A A4

C05P0 Cabinet, Sink, U/C/B, 2 Door, 36x48x22 A A4

C0037 Rail, Apron, 4x36x1 A

C0039 Rail, Apron, 4x48x1 A

C0040 Rail, Apron, 4x54x1 A

C0041 Rail, Apron, 4x60x1 A

CB020 Cabinet, W/H, 2 Shelf, 1 DO, Sloping Top, 38x24x13 A A4

CE030 Cabinet, W-H, 2 SH, 2 GDO, Sloping Top, 38 x 30 x 13 A A4

CE040 Cabinet, W/H, 2 SH, 2 GDO, Sloping Top, 38x36x13 A A4

CQ030M Cabinet, W/H, Microwave Shelf, 2 DO, 30x30x13 Millwork A A4

CS010 Sink, SS, Single Compartment A

CS090 Sink, SS, Single Compartment A

CS090H Sink, SS, Single Compartment, Hands-Free A

CS150 Sink, SS, Single Compartment A

CS180H SINK, SS, SINGLE COMPARTMENT, 12X22X16 ID A

CS200 Sink, SS, Single Compartment A

CS200A Sink, SS, Single Compartment, w/ Spray-down A

CS270 Sink, Epoxy Resin A

CT020 Countertop, Solid Surface A

CT050 Countertop, Stainless Steel A

CT060 Countertop, Modified Epoxy Resin A

CW030 Cabinet, Floor Standing, 5 SH, 2 GDO, ST, 92"x30" A A4

JSN DESCRIPTION LOG CAT REMARKS

A1140 Shelving, File, Rotary, 7-Tier, Starter Unit C A12

A5075 Dispenser, Soap, Disposable C

A5077 Dispenser, Hand Sanitizer, Hands-Free C

A5107 Dispenser, Glove, Surgical/Examination, Wall Mntd C

A5210 Bracket, Television, Wall Mounted, w/Adjust Arm C A1, A10

A5212 Bracket, Television, Wall Mounted, Tilt/Angle C A1, A10

A5220 Bracket, Television, Wall Backing C A1, A10

D3310 Chair, Procedure, Dental C

D3320 Chair, Operating, Dental C

D4262 Drill System, Surgical, Oral, Electric Drive C

F3010 Board, Bulletin, 48 x 48 C

F3050 Whiteboard, Dry Erase C A1, A3

L2000 Purification System, Water C A2

M1803 Work Station, Computer, Wall Mounted C A1, A2

M2070 Shelving, Storage, 77hx36wx18d C A12

M3185 Electrosurgical Unit, Monopolar, Wall Mounted or Free-standing C A3

M8541 Microscope, Operating, Endodontic (ceiling mt) C A19

X6505 Radiographic Unit, Dental, Panographic & Cephalo. C A20

X6510 Radiographic Unit, Dental, Cone Beam, 3-D Imaging C A20

X6600 Radiographic Unit, Dental, Wall Mounted, 7 mA C A14

EQUIPMENT NOTES

REMARKS COLUMN NOTES :

A1 SEE DETAIL B1 / A-400 FOR TYPICAL MOUNTING HEIGHTS

A2 PROVIDE WALL BACKING - SEE DETAIL D1 / A-542

A3 PROVIDE WALL BACKING - SEE DETAIL D2 / A-542

A4 PROVIDE WALL BACKING - SEE DETAIL C1 / A-543

A5 PROVIDE WALL BACKING - SEE DETAIL D1 / A-401

A6 PROVIDE WALL BACKING - SEE DETAIL D2 / A-401

A7 PROVIDE WALL BACKING - SEE DETAIL A1 / A-401

A8 SEE DETAIL B1 / A-401

A9 SEE DETAIL A4 / A-401

A10 PROVIDE WALL BACKING - SEE DETAIL C4 / A-543

A11 PROVIDE WALL BACKING - SEE DETAIL C1 / A-402

A12 SEE DETAIL B3 / A-546 FOR REQUIRED SEISMIC BRACING

A13 NOT USED

A14 SEE DETAILS C1 & C3 / A-570 FOR MOUNTING DETAILS

A15 SEE DETAIL B4 / A-850

A16 SEE SHEET A-851 FOR MOUNTING DETAIL

A17 SEE SHEET A-852 FOR MOUNTING DETAILS

A18 SEE DETAIL B2 / A-850

A19 SEE DETAIL C1 / A-852

A20 PROVIDE WALL BACKING - SEE DETAIL D1 / AA-542 SIMILAR.

BACKING SHALL BE 12" DEEP TRACK ACROSS A MIN. OF 3

STUDS. (SEE MANUFACTURERS EQUIPMENT INSTALLATION

GUIDE FOR RECOMMENDED HEIGHT OF WALL BACKING.)

THE EQUIPMENT SCHEDULE

THE EQUIPMENT SCHEDULE LISTS THE EQUIPMENT SHOWN ON

THE DRAWINGS BY JOINT SCHEDULE NUMBER (JSN). THIS IS A FIVE

OR SIX DIGIT NUMBER SUCH AS "L1080".

LOGISTICAL RESPONSIBILITY

THE LOGISTICAL RESPONSIBILITY FOR EACH ITEM IS SHOWN IN

THE COLUMN LABELED "LOG CAT" AND ARE AS DESCRIBED

BELOW:

A CONTRACTOR FURNISHED CONTRACTOR INSTALLED.

EQUIPMENT IS PURCHASED AND INSTALLED BY THE

CONSTRUCTION CONTRACTOR

B GOVERNMENT FURNISHED CONTRACTOR INSTALLED.

EQUIPMENT IS PURCHASED BY THE GOVERNMENT AND

INSTALLED BY THE CONSTRUCTION CONTRACTOR.

C GOVERNMENT FURNISHED GOVERNMENT INSTALLED.

EQUIPMENT IS PROVIDED BY THE GOVERNMENT AND

INSTALLED BY THE GOVERNMENT (EQUIPMENT VENDOR

OR AGENT).

D OTHER

LEASED OR RENTED EQUIPMENT, ARRANGED BY THE

GOVERNMENT, OR ANY SIMILAR TYPE ARRANGEMENT

REQUIRING SPECIAL FUNDING AND / OR COORDINATION.

JUSTIFICATION AND APPROVALS MAY BE REQUIRED FOR

USE OF THIS CATEGORY.

NOTE: REFER TO Q-SERIES SHEETS FOR ADDITIONAL EQUIPMENT

ITEMS THAT ARE NOT A PART OF THIS CONTRACT.

SCHEDULE OF CATEGORY C ITEMS SHOWN IN THESE

DOCUMENTS FOR COORDINATION PURPOSES ONLY.

THESE ITEMS ARE NOT IN THE CONTRACT

T

E C

H A

M E

N D

4/

/2

JC

V

NOTE: F3010

REMOVED FROM

EQUIPMENT

SCHEDULE

TECHNICAL AMENDMENT 0008 - CONTINUATION SHEET
DRAWING SHEETS
A-311 - WALL SECTIONS
A-313 - WALL SECTIONS
A-314 - WALL SECTIONS
A-501 - EXTERIOR WALL DETAILS
A-660 - FINISH SCHEDULE
A-661 - FINISH SCHEDULE
A-680 - EQUIPMENT SCHEDULE