This document appears to be an addendum to engineering drawings for a project at Camp Lejeune. The addendum instructs the removal of an exhaust fan disconnect switch, wiring, and conduit back to the MAU1 distribution bus. This is a modification to the previous mechanical and electrical drawings for the project.
The related federal contract opportunity is for repairs to Building AS518 Paint Booth at Camp Lejeune. The solicitation is only open to mechanical MACC contractors listed on the General Requirements cover page. The required scope of work and any applicable drawings are provided in the attached documents.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(X) GUH5-1
(X)MAU1
44x44
2246 Yaupon Drive Wilmington, NC 28401
Phone: 910.791.4000 Fax: 910.791.5266 www.cbhfengineers.com NC# P-0506c Copyright 2024CBHF Engineers, PLLC
Engineers, PLLC 043801
TROY O. GRADY
SEAL
R
EENI GN
P R
OF E S S I ON
A
E
L
NO
RT H CAROL I NA
ADDENDUM: ADDED TWO SHEETS 06/19/24
REMOVE EXHAUST FAN DISCONNECT SWITCH, WIRING AND CONDUIT BACK TO MAU1 DISTRIBUTION BUS.
REMOVE DISCONNECT, CONDUIT AND CONDUCTORS BACK TO SOURCE.
DEMOLITION KEYED NOTES
1/4" = 1'-0" 0 4' 8'2'1 PARTIAL FLOOR PLAN
PLAN
NORTH
1/4" = 1'-0" 0 4' 8'2'1 PARTIAL FLOOR PLAN
PLAN
NORTH
WORK THIS AREA
NOT TO SCALE0 KEY PLAN
JFamiglietti Date 06/19/2024