This document appears to be an engineering drawing and specifications related to a federal contract opportunity for repairs to a paint booth at Building AS518 on the Camp Lejeune military installation.
The key details are: The contract is for the modification of an existing paint booth to meet NESHAP (National Emission Standards for Hazardous Air Pollutants) requirements. This includes installing a new 3-stage filter chamber, a new 25HP exhaust fan, air solenoid valve, and roof penetration for the exhaust stack. The work must be completed by factory authorized technicians. The solicitation number is N4008524R2728, the opportunity type is a Solicitation, and the contracting agency is the Department of the Navy Naval Facilities Engineering Command. Only pre-qualified MACC (Multiple Award Construction Contract) mechanical contractors are eligible to submit a proposal for this project.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(X) GUH5-1
(X)MAU1
44x44
2246 Yaupon Drive Wilmington, NC 28401
Phone: 910.791.4000 Fax: 910.791.5266 www.cbhfengineers.com NC# P-0506c Copyright 2024CBHF Engineers, PLLC
Engineers, PLLC 043801
TROY O. GRADY
SEAL
R
EENI GN
P R
OF E S S I ON
A
E
L
NO
RT H CAROL I NA
ADDENDUM: ADDED TWO SHEETS 06/19/24
1/4" = 1'-0" 0 4' 8'2'1 PARTIAL FLOOR PLAN
PLAN
NORTH
INSTALL NEW FILTER CHAMBER WHILE MAINTAINING ALL OF THE MANUFACTURER'S
RECOMMENDED CLEARANCES.
INSTALL NEW EXHAUST FAN WHILE MAINTAINING ALL OF THE MANUFACTURER'S
RECOMMENDED CLEARANCES.
INSTALL VERTICAL EXHAUST DUCTWORK UP THROUGH NEW ROOF PENETRATION.
PROVIDE DUCT OFFSETS AS NEEDED. INSTALL NEW CURB, SEE 1/M-501 AND
3/M-501 FOR FURTHER INFORMATION.
CONSTRUCTION KEYED NOTES
WORK THIS AREA
GENERAL NOTES
1. EXISTING PAINT BOOTH IS BY ROHNER FINISHING SYSTEMS OUT OF VANCOUVER
WASHINGTON.
2. MODIFICATIONS AND START-UP OF THE PAINT BOOTH MUST BE COMPLETED BY
FACTORY AUTHORIZED TECHNICIANS.
3. MODIFY THE EXISTING PAINT BOOTH TO MEET APPLICABLE NESHAP REQUIREMENTS.
4. PROVIDE NEW NESHAP 3-STAGE FILTER CHAMBER. FILTER SYSTEM MUST MEET OR
EXCEED NATIONAL EMISSION TEST STANDARD 319. PROVIDE MANOMETER TO
MONITOR OVER SPRAY BUILDUP ON FILTERS.
5. PROVIDE NEW 25 HP 460 VOLT 3 PHASE MIXED FLOW CENTRIFUGAL FAN WITH SPARK
RESISTANT CONSTRUCTION AND VFD. FAN MUST BE CAPABLE OF 22,000 CFM WITH
THE ADDITIONAL PRESSURE DROP RESULTING FROM ADDITIONAL FILTRATION. FAN
TO BE INTEGRATED INTO THE EXISTING PAINT BOOTH CONTROL SYSTEM
6. INSTALL AIR SOLENOID VALVE INTERLOCKED WITH SPRAY APPARATUS TO ONLY
ALLOW SPRAY WHILE THE EXHAUST SYSTEM IS OPERATIONAL.
7. ROOF PENETRATION FOR EXHAUST STACK AND GUY WIRES TO BE MADE WEATHER
TIGHT.
ROOF MEMBERS ABOVE (TYPICAL).