This amendment modifies an indefinite delivery/indefinite quantity multiple award construction contract solicitation to provide updated wage determinations and discussions with offerors in the competitive range. The solicitation is for design-build and design-bid-build construction projects to be performed for the Public Works Department Maine across its area of responsibility by the Naval Facilities Engineering Command Mid-Atlantic. Work will include new construction, demolition, repair, alteration, and renovation of buildings, systems and infrastructure such as administrative facilities, industrial facilities, maintenance facilities, warehouses, communications facilities, personnel support facilities, recreational facilities, lodging facilities, medical facilities, training facilities, ranges, and roads. Lead or asbestos abatement may be required. Selected contractors will be responsible for labor, supervision, engineering, design, materials, equipment, tools, parts, supplies and transportation for individual projects. Explosive facility and site work may be included. The wage determination was updated and discussions are being provided to offerors still under consideration for award.

View the file

Other files

File Type Posted
Amendment 0003 Attachment F_Rev1- Price Proposal Form - 1660646_ST19-0831 Repair Oil Storage Tanks.pdf PDF
Amendment 0003 SV Sign-in 21R1217.pdf PDF
Amendment 0003 PPI Attachment 95 - B72 Fuel Oil Water Seperator Asbuilt.pdf PDF
Amendment 0003 PPI Attachment 80B - PNSY A-102_PNSY-Kittery_IntExt-UT_InspectionRpt_2018-signed.pdf PDF
Amendment 0003 SOW_REV2 9-17-21 - 1660646_ST19-0831 Repair Oil Storage Tanks.pdf PDF
AMENDMENT 0003.pdf PDF
Amendment 0003 PPI Attachment 125 - B72 Repair Fuel Oil Storage Tanks.pdf PDF
Amendment 0003 PPI Attachment 80 - PNSY A-101_PNSY-Kittery_IntExt-UT_InspectionRpt_2018.pdf PDF
Amendment 0003 PPI Attachment 79B - A-102-BLDG72 - 2020 Inspection.pdf PDF
Amendment 0003 PPI Attachment 79 - A-101-BLDG72 - 2020 Inspection.pdf PDF
Amendment 0002 - PPI Attachment Q50 - Attachment 3.1 - Updated Coating Spec 09 97 13.27.pdf PDF
AMENDMENT 0002.pdf PDF
Amendment 0002 - PPI Attachment Q46 - Haz Material Survey Report-Final - Credere - 6-22-21.pdf PDF
Amendment 0002 - Attachment 4 - Submittal Register - Rev2.xls XLS spreadsheet
Amendment 0002 - PPI Attachment Q8 - Fuel Oil One-Line Drawing.pdf PDF
Amendment 0002 - PPI Attachment Q7 - Fuel Oil Skid Drawing.pdf PDF
Amendment 0001 - 5500 DBIDS Form.docx DOCX document
Amendment 0001 - Attachment 4 - Submittal Register - Rev1.xls XLS spreadsheet
AMENDMENT 0001.pdf PDF
Amendment 0001 - secnav 5512-1.pdf PDF
Amendment 0001 - Attachment 3 - Technical Specifications Rev2.pdf PDF
Amendment 0001 - Acceptable Forms of ID.docx DOCX document
Attachment D - SOW With OPTONS - ST19-0831 Repair Oil Storage Tanks.pdf PDF
Attachment 1 - Price Proposal Form.pdf PDF
Attachment 5 - Drawings.pdf PDF
Attachment C - Construction Design Exp.docx DOCX document
Attachment 2 -DIV1 Specs.pdf PDF
Attachment 4 - Submittal Register - 1660646.xls XLS spreadsheet
Attachment B - Past Performance Questionnaire.docx DOCX document
Attachment 3 - Technical Specifications Rev1.pdf PDF
Attachment A - Pre-Proposal Inquiry Log.doc DOC document
N4008521R1217.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION NO. N40085-21-R-1217 - DESIGN-BUILD (DB) /DESIGN-BID-BUILD (DBB), INDEFINITE DELIVERY, INDEFINITE QUANTITY (IDIQ), MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) FOR PUBLIC WORKS DEPARTMENT (PWD) MAINE

The purpose of this amendment is to issue discussions to all Offerors in the competitive range and to provide an updated Wage Determination.

See Continuation Page(s).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Jan-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008521R1217

X 9B. DATED (SEE ITEM 11)

02-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Jan-2022

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008521R1217

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

WAGE DETERMINATION

"General Decision Number: ME20220019 01/07/2022

Superseded General Decision Number: ME20210019

State: Maine

Construction Type: Building

County: York County in Maine.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

If the contract is entered into on or after January 30, 2022, or the contract is renewed or extended (e.g., an option is exercised) on or after January 30, 2022, Executive Order 14026 generally applies to the contract. The contractor must pay all covered workers at least $15.00 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on that contract in 2022.

If the contract was awarded on or between January 1, 2015 and January 29, 2022, and the contract is not renewed or extended on or after January 30, 2022, Executive Order 13658 generally applies to the contract. The contractor must pay all covered workers at least $11.25 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on that contract in 2022.

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/07/2022

CARP0349-001 09/01/2020

Rates Fringes

CARPENTER

Includes Drywall Hanging and Metal Stud Installation.$ 25.90 17.45

CARP0352-008 09/01/2020

Rates Fringes

CARPENTER (Includes Drywall Hanging, Form Work, and Metal Stud Installation)...............$ 25.90 17.45

ELEC0490-009 01/01/2021

Rates Fringes

ELECTRICIAN (Includes Low Voltage Wiring)..................$ 31.45 20.94

ELEV0004-006 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 61.42 34.77

IRON0007-034 03/16/2021

Rates Fringes

IRONWORKER (ORNAMENTAL AND

REINFORCING).....................$ 27.98 23.59

* LABO0976-007 12/01/2020

Rates Fringes

LABORER: Common or General (Industrial Work Only)...........$ 21.76 20.07

PLUM0131-002 06/01/2020

Rates Fringes

PLUMBER (Includes HVAC Pipe Installation)....................$ 35.67 23.73

SUME2014-028 01/31/2017

Rates Fringes

BRICKLAYER.......................$ 30.42 2.94

CEMENT MASON/CONCRETE FINISHER...$ 17.65 5.01

INSULATOR - MECHANICAL

(Duct, Pipe & Mechanical

System Insulation)...............$ 20.14 2.29

IRONWORKER, STRUCTURAL...........$ 24.16 17.25

LABORER: Common or General......$ 15.29 4.67

LABORER: Demolition.............$ 18.20 5.05

LABORER: Mason Tender - Brick...$ 19.16 3.56

MILLWRIGHT.......................$ 22.17 7.75

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 39.38 8.55

OPERATOR: Crane.................$ 23.33 0.00

PAINTER (Brush and Roller).......$ 15.38 2.95

PAINTER: Spray..................$ 17.47 2.22

ROOFER...........................$ 20.22 2.09

SHEET METAL WORKER, Includes HVAC Duct Installation...........$ 17.30 2.35

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union, which prevailed in the survey for this classification, which in this example would be Plumbers 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Division National Office Branch of Wage Surveys. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

(End of Summary of Changes)