This amendment modifies a solicitation for a multiple award construction contract to support public works projects in Maine. The selected contractors will perform design-build and design-bid-build projects involving new construction, demolition, repair, alteration, and renovation of various facilities. Work may include lead or asbestos abatement. Responses are due by September 23, 2021. The amendment provides responses to contractor questions, updates the scope of work and price proposal form. It increases the period of performance for optional fuel system upgrades to allow sufficient time for design and installation. Hazardous waste disposal will be managed by the shipyard.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SOLICITATION NO. N40085-21-R-1217 - DESIGN-BUILD (DB) /DESIGN-BID-BUILD (DBB), INDEFINITE DELIVERY, INDEFINITE QUANTITY (IDIQ), MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) FOR PUBLIC WORKS DEPARTMENT (PWD) MAINE
The purpose of this amendment is to provide responses to Pre-Proposal Inquiries, an updated scope of w ork and an updated Price Proposal Form.
The proposal due date of 23 September 2021 NLT 2:00 P.M. EST remains unchanged.
See Continuation Page(s).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Sep-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008521R1217
X 9B. DATED (SEE ITEM 11)
02-Aug-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Sep-2021
CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008521R1217
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0003
Contractor
PPI#
Section of RFP or Page Number
Paragraph Reference
Drawing Number
QUESTION RESPONSE
21 Page 10 Paragraph 8 The RFP states the following: If an Offeror is utilizing experience information of affiliates/subsidiaries/pa rent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/pare nt firm will have meaningful involvement in the performance of the contract or the Government may not consider the project.
For Tribal Companies such as ours, we base our experience and past performance on FAR 15.305[a][2][iii]; which states that TRIBAL 8(a)s may claim the past performance of sister companies and key management personnel during the evaluation period of award (FAR 15.305[a][2][iii]).
If there will be meaningful involvement from the affiliate/subsidiary, does the FAR statement hold true for this solicitation No.
N40085-21-R-1217?
Yes.
79 Attachme nt D, ST19-
Repair Oil Storage Tanks
SOW
(general) Please provide the most recent inspection and certification reports (regulatory compliance) for tanks A-101 and A- 102 pursuant with STI SP-001 and/or API 653.
See PPI Attachment #79.
80 Attachme nt D, ST19-
Repair Oil Storage Tanks
SOW
(general) Has an out-of-service inspection of A-101 and A-102 been completed in the past 5-years? If yes, please provide a copy of the report.
See PPI Attachment #80
86 13526.00
1.6.1.2 Spec says QC Manager
cannot be SSHO.
Which spec should be followed?
Three (3) hats of supervision is required at this time
87 Amend #2 PPI #29 The answer to PPI #29 says that three individuals are required to manage the work of this contract. However, Section 13 .3 of the SOW indicates that the QC Manager can also be the Site Supervisor for the seed project.
Does the SOW supersede the requirements of this the amendment?
Three (3) hats of supervision is required at this time.
88 Amend #2 PPI #55 The answer states 100 linear square feet. Is it linear feet or square feet?
Square Feet. The response to PPI#55 should read square feet and not linear feet.
89 01 33 10.05
2.2.2 Presently there is no
stipulated order of award for bid options #1 thru #4, however all options contain an award period of 100 days following award of the Base Bid. Of specific concern are options #1, #2, #3.
With no specific order of award each option price will need to be developed to include a respective increase in overhead costs associated with the projected increase in performance period.
With no known order of award these overhead costs could become duplicative if multiple
There is no stipulated order of award options are awarded as currently stated in the
RFP.
For example, Option #1 adds 90 calendar days so theoretically 90 days of overhead would be added to the bid.
Option #2 adds 60 calendar days so theoretically 60 days of overhead would be added to the bid, and so forth for Option #3. So, if all four Options are awarded theoretically no more than 90 days would be required however due to no stated order of Option award a total of 210 days of overhead would have been priced into the bid amount for the four options.
Please clarify the order of the Option award to avoid this duplication of costs.
90 Price Proposal Form- Attachment F
Contract Line Item Note i
This note states in part “If any or all option items are exercised, the contract completion date remains the same as that of the base price (CLIN 0001), as the work required by these options can be performed concurrent to the base work.” Please confirm as the Option items (Notes e, f, g) all indicate the performance period will be extended if the Options CLIN 0002, 0003 and 0004 are awarded.
See updated Price Proposal Form – Attachment F
91 Scope of Work
Please confirm via amendment clarifying statements made during the site visit that one tank and the existing pump system is required to remain in service while the tanks are worked and new pump system (if Option is awarded) is installed.
See updated SOW section 1.6.2 - Temporary Pump Skid and Section 1.10
- Fuel Tank Out-of-Service Phasing.
92 Scope of Work
During the work on this tank storage system there will be a need to have the system out of service for tank to tank transition, re-piping the offload system, conversion of the pumping system, etc., what is the maximum out of service period that will be permitted?
See updated SOW section 1.6.2 - Temporary Pump Skid and Section 1.10
- Fuel Tank Out-of-Service Phasing.
93 Price Proposal Form- Attachment F
CLIN 002
Option 1 - Fuel Oil Pump Skid
There is no specific technical information provided in the Scope of Work related to the requirements for the Option #1 (fuel oil pump skid). What are the specific “current capabilities and new standards and specifications” that are referenced in the Scope of Work for the fuel oil pump skid?
For Option #1 referto the Div 1 specifications for design build projects.
(see FC 1-300-09N Navy And Marine Corps Design Procedures and UFC 3- 401-01 Mechanical Engineering)
94 Scope of Work
1.6.1 States in part “…to
replace all pumps, strainers, valves, controls and any additional accessories to the fuel oil skip located in B72.”. As written the scope of work is anticipating that the existing fuel oil skid will be rebuilt with new components. To minimize the amount of time the fuel oil skid will be out of service would PNSY and the Power Plant consider replacing the fuel oil skid with a new skid that would be delivered pre-built?
A pre-built skid would be considered by the PNSY and the Power Plant if the flow requirements were met. See the PPI Attachment - Equipment List for flows and capacities.
95 Price Proposal Form- Attachment F
CLIN 003
Option 2 - Fuel Oil Water Separator
There is no specific technical information provided in the Scope of Work related to the requirements for the Option #2 (oil-water separator). For the oil water separator; what are the flow requirements?
See PPI Attachment #95 - B72 Fuel Oil Water Separator As built for OWS requirements and operations.
96 Price Proposal Form- Attachment F
CLIN 003
Option 2 - Fuel Oil Water Separator
Please clarify if the oil water separator is to be a double walled tank? Is a fiberglass or steel oil-water separator tank required?
The OWS shall match existing General Specifications:
Type: HT, ACT-100-U, Double Wall Material: Mild Carbon Steel Diameter: 3’-6” Length: 7’-9”
97 Price Proposal Form- Attachment F
CLIN 003
Option 2 - Fuel Oil Water Separator
Confirm type of oil-water separator required, coalescing parallel plate per UFGS 46 25 14?
PPI Attachment #95 - B72 Fuel Oil Water Separator As built for OWS requirements and operations.
98 Price Proposal Form- Attachment F
CLIN 003
Option 2 - Fuel Oil Water Separator
For fuel oil water separator, provide anticipated maximum petroleum concentrations anticipated.
PPI Attachment #95 - B72 Fuel Oil Water Separator As built for OWS requirements and operations. The Navy cannot provide further guidance on the anticipated concentrations at this time.
99 Price Proposal Form- Attachment F
CLIN 003
Option 2 - Fuel Oil Water Separator
For fuel oil water separator, is any monitoring instrumentation required?
The system shall be provided with local controls:
High Oil Level High-High Oil Level Leak Detection Alarm Panel
100 Price Proposal Form- Attachment F
CLIN 004
Option 3 - Fuel Oil Fill Station
There is no specific technical information provided in the Scope of Work related to the requirements for the Option #3 (fuel oil fill station). For the fuel oil fill station, how is fuel delivered and unloaded?
Option #3: Fuel Oil Fill Station shall be removed from the RFP. Section 1.8 from the SOW shall be disregarded .
101 Price Proposal Form- Attachment F
CLIN 004
Option 3 - Fuel Oil Fill Station
For the fuel oil fill station, is the delivery truck equipped to pump or are offload pumps part of this Option?
Option #3: Fuel Oil Fill Station shall be removed from the RFP. Section 1.8 from the SOW shall be disregarded .
102 Price Proposal Form- Attachment F
CLIN 004
Option 3 - Fuel Oil Fill Station
Is spill containment required as part of fuel oil fill station scope? If so, what would be acceptable to PNSY and the Power Plant operators?
Option #3: Fuel Oil Fill Station shall be removed from the RFP. Section 1.8 from the SOW shall be disregarded .
103 MD101-
Mechanical Demolition & M101- Mechanical New Work
Key Note #1
Drawing MD101 by Demolition Key Note #1 shows removal of existing abandoned piping, pumps, valves, etc. within the dike area. For Tank A-101 this piping connects to a tank nozzle on the east side of the tank. Under the revised piping configuration shown on Drawing M101 the existing tank nozzle on the east side of tank A- 101 is not shown, the Scope of Work does not state that this tank nozzle is to be removed.
Please confirm that the existing tank nozzle on the east side of Tank A- 101 is to be removed and the tank shell is to be patched, or direct otherwise.
The connections mention are refereeing to the return piping. The return piping is to remain. The existing pipe to be demolished makes connections on the return piping. The contractor shall remove the tee and straight pipe the return to the tank port. See Keynote #7.
104 M101 – Mechanical New Work Plans
Key Note #8a
Note states to provide “Pressure relief valve on supply and return piping”. Where is the discharge from the pressure relief piping to be piped?
The relief shall discharge to the tank side of the piping or to the tank itself.
105 MD101-
Mechanical Demolition & M101- Mechanical New Work
These drawings identify “Abandoned Float Gauges” at the tank roof of both tanks. Is the float gauge equipment currently in place and connected to the three ports shown on the tanks?
The "Abandoned Float Gauges" refers to the ports that utilized the previous level gauge system. The tanks have different levels of demolished system that is remaining. Assume for bidding purposes the full system exists and needs to be replaced.
106 M101- Mechanical New Work
Key Note 8b
Scope of Work item
1.4.2.2 indicates the installation of a Varec Model 2500 level indicator, which is a float and tape indicator, utilizing the three abandoned tank ports.
Drawing M101, Key Note #8b indicates a “Level Indicator (at Tank Location)”.
Please confirm that the Key Note level indicator is the Varec Model 2500 per SOW
1.4.2.2 and that no remote reporting (local read only) from the
For the Varec Model level system only local reporting is required. This will be a secondary level gauge system.
Varec 2500 level indicator is required.
107 Submittal Register - Attachment
In both the original RFP and Amendment 01, In both versions of the Submittal Register, Lines #11, 13, 14, 15, 16, and 18 are all crossed out for the submission of Consolidated RFP Documents, Design Drawings, Specifications, Design Analysis, Design Submittals, and the DD Form 1354. Per SOW (Attachment D), Sections 1.6, 1.7, and
1.8 require ‘design-build services’ to construct each respective option. If the options are awarded and contractor design is required, please confirm if we are to provide submittals in accordance with specification section 01 33 10.05 20 and not the submittal register?
Please clarify why the submittal items pertaining to this design are crossed out in the submittal registers?
Please See the revised Submittal Register.
108 Scope of Work
1.4.1.1 Requires an annunciator
to be installed interconnected with the alarm in the existing operator console. This scope of work does not indicate the location of the new annunciator, please clarify the location.
The new annunciator shall be located near the fill station to notify the filling personnel.
109 Scope of Work
1.4.1.1 This scope requires the
contractor to contact the manufacturer of the existing level indicator to determine the compatible annunciator to use. Please provide
The existing system is unknown at this time. No documentation can be provided.
the name of the existing level indicator manufacturer.
110 Scope of Work
1.4.2.1 Is there an existing tank
strapping chart to utilize to calibrate the existing fuel monitoring system or will the contractor be required to strap the tanks as part of this scope of work?
No strapping chart is available. Assume that tank strapping will need to be performed for use in the calibration.
111 Scope of Work
1.4.5.1 This indicates to
provide new 8-inch gate valves at tank supply.
Referencing Drawing M101 the existing fuel oil supply lines are shown to be 3-inch and there is no indication that the tank supply nozzles are other than 3-inch. Please confirm the valve size associated with scope of work item 1.4.5.1.
Both tanks have an 8" isolation valves connected to a 10" fill line that interconnects the tanks. The Valve size is 8" for both tanks.
112 M101- Mechanical New Work
Drawing M101 shows two ball valves at the tank supply nozzle, are both ball valves at each tank supply nozzle to be replaced?
Yes. The isolation valves at the tank supply shall be replaced. Each tanks has an 8" isolation valve (Gate valve). The isolation valve at the nozzle shall remain unless the fuel fill option is awarded.
113 33 01 50.60
- Cleaning of Petroleum Storage Tanks
Will PNSY be responsible for disposal of tank cleaning residual wastes (i.e.
sludge, sediment, residual product) similar to how lead or asbestos wastes are handled? 3.5 states Govt will provide drums or tanks to containerize ‘waste fuel’? Is the Contactor responsible for disposal?
Yes. Disposal of hazardous waste and tank cleaning residual waste will be managed by PNSY Building 357. PNSY Building 357 will provide 55-gallon drums to the contractor for proper waste containerization
114 33 01 50.60
- Cleaning of Petroleum Storage Tanks
3.7 Part 3.7 of this
specification references abrasive blasting or power wire cleaning for tenaciously adherent materials. The RFP does not include any work associated with coating or lining the tank interiors, please confirm if coating work on tank interior will be
Paragraph 3.7 shall not apply. No interior work shall be completed besides tank cleaning and any associated inspections.
required, so we would prefer not to do any abrasive blasting to support tank cleaning .
115 33 01 50.60
- Cleaning of Petroleum Storage Tanks
3.7.6 (a) Paragraph 3.7.6.a directs the Contractor to refer to paragraph “Water, Sediment, and Sludge Analysis” for testing requirements prior to discharging water, sediment, or sludge. We do not find any paragraph with that title in this specification.
Paragraph 3.7 shall not apply. No interior work shall be completed besides tank cleaning and any associated inspections required for recertification.
116 Attachment F - Price Proposal From
1.2.e, 1.2.f The referenced paragraphs relate to Bid Option #1 - design-build Fuel Oil Pump Skid and Bid Option #2
- design-build Oil Water Separator. Each of these options have award periods of 100 days following the Base Bid award date. Bid Option #1 allows for an additional 90 days of performance time and Bid Option #2 allows for an additional 60 days of performance time if awarded. The design of each of these options is in accordance with 01 33 10.05 20 paragraph 2.2.2 which requires three design package submissions to the Navy for review and approval, each with a 21-day Navy review period. Based on the current design submission requirements and the lead time required for the fuel oil skid (12-16 weeks) and the oil water separator (10-12 weeks) there is not sufficient time in the allotted performance period to allow for the design, delivery and installation of the fuel oil skid and oil water separator. The
The period of peformace shall be increased to 150 days for Option 1 and 120 days for Option 2. See the updated Attachment F - Price Proposal Form as well as the updated SOW.
additional performance period for each of these options should be increased by 60 days each to 150 days for Option #1 and 120 days for Option #2.
117 Amend #2 The asbestos report in Amend #2 does not identify any asbestos present in the tank components. Is asbestos abatement of the tanks still a requirement of the seed project?
Valve gaskets were unable to be tested so all valve gaskets shall be treated as asbestos.
119 Amendme nt #2
Question 55 Amd 2, response to question 55 states: “For bidding purposes assume 100 linear square feet of concrete repairs (minor cracks and spalling) are required. Please clarify the government response. Are we to assume 100 square feet or 100 Lineal Feet?
Square Feet. The response to PPI#55 should read square feet and not linear feet.
120 Amendme nt #2
Question 27 Amd 2, response to question 27 states: “See updated SOW”. There was no updated SOW provided in Amendment
2. Please provide updated SOW
The updated SOW shall be provided.
121 Price Proposal Form – Attachme nt F
CLIN
0001AA &
CLIN
0001AF
The description of CLIN0001AA States:
“Price for hazardous material removal and removing insulation, complete and in accordance with the drawings and specifications, but excluding work described in CLIN(s)
0001AB, 0001AC,
0001AD, 0001AE,
0001AF, 0002, 0003,
0004 and 0005.”
The description of CLIN0001AF States:
“Price for hazardous material removal and removing insulation complete and in accordance with the drawings and specifications, but excluding work described in CLIN(s)
0001AA, 0001AB,
0001AC, 0001AD,
0001AE, 0002, 0003,
0004 and 0005” Both of these CLIN’s have the same SOW description; Hazardous Materials removal and removing insulation.
Please clarify what scope of work is to be priced under each
CLIN.
Description of CLIN0001AF has been updated to correct verbage. See updated Price Proposal Form – Attachment F
122 Hazardou s Material Disposal
On previous projects performed at the PNSY
– all hazardous waste was taken to CODE 109 and was disposed of by the shipyard. For this contract – are we to take all Hazardous Waste Materials to Code 109 for them to dispose of the waste?
Yes. Disposal of hazardous waste and tank cleaning residual waste will be managed by PNSY Building 357. PNSY Building 357 will provide 55-gallon drums to the contractor for proper waste containerization
123 Amend #2 Questions 68 & 69
Amendment #2 – responses to PPI 68 &
69. The information provided by the Government in responses to PPI 68 & 69 does not provide the sizing, capacities, demands etc for the existing Fuel Oil Pump Skid. The drawings are schematic. SOW page 21a para 1.6.1 states to “provide D-B services to replace all pumps, strainers, valves, controls, and any additional accessories to the fuel oil pump skid located in B72. The system shall be complete and usable and meet all current capabilities and new standards and specifications.” Please provide current data for fuel usage from all appliances, minimum supply capacity, required supply duration and maximum consumption rates for supplied equipment.
If AS-BUILT information is not available – Govt to provide assumptions for bidding purposes to allow for qualified pricing from all Contractors.
Fuel Oil Day Tank / Pump Manufacturer: Phillips Pump Tank capacity: 500 gallons Pump: 15 gpm @ 150 psi
Packaged Boilers 3&4 Oil Firing:
Heat input: 83.2 mmbtu/hr Pressure @ burner: 150 psig
HRSG-2 Duct Burner:
124 Amendme nt #2
Question 77 PPI 77 – Government response states “ The Navy will bring the fuel level in the tanks to as low as the pumps will allow. Final cleaning and removal shall be completed by the Contractor.” We are unable to know how much fuel remains in these tanks once the NAVY removes the fuel with the pumps.
Please provide a quantity of fuel removal we are to assume for bidding purposes.
It is assumed approximately 2200-2500 gallons will remain at the bottom of the tank after fuel transfer. This
125 Amendme nt #2
1.7.1 Fuel
Oil Water Separator
PPI 71 – The Government response to PPI 71 does not provide enough clarification to Size the new oil/water separator. Are we to size this Unit to service the containment, draining of existing boilers, and heavy rainfalls (per the Government Response)?
If so – we will need additional information on the quantity of boilers, inspection schedule and also asbuilts of the existing grades in this area to quantify rainfall calculations. Please clarify the Government response or confirm that we are to size the new oil water separator for the tank containment area only.
Oil Water Separator shall be sized for the fuel tank containment alone. Please disregard PPI #71. See PPI Attachment
- Equipment list for additional information
126 Amend #2 PPI #74 Answer to PPI 74 indicates that the system needs to allow for fill as well as dispensing. The fuel oil that is stored in the tanks is likely dyed and is not allowable for over the road use. Is a dispensing system really desired?
Option #3: Fuel Oil Fill Station shall be removed from the RFP. Section 1.8 from the SOW shall be disregarded.
127 Amendme nt 2
Amendment 2 provided the ACM sampling test results, since there is no ACM, how do we proceed?
Based on the June 22, 2021 Building 72 Fuel Tanks Hazardous Material Sampling & Testing Report, previously provided to bidders under Amendment 2, the following should be considered presumed asbestos containing material (PACM) and should be managed accordingly, pursuant to the project specifications, PNSY and Navy requirements, and local, state and federal statutes and regulations:
- The adhesive and/or caulk used to attach antiskid material on top of the two tanks. The estimated area of PACM to be managed is estimated at 60 square feet per tank (total of 120 square feet).
- The gaskets at pipe joints and valves, and the valve packings, for all piping and fixtures to be disturbed or removed during tank renovation
128 M101 Drawing M101 only shows a single fuel oil return line, is this correct?
Yes. The fuel oil return line is a single line until it splits as it enters the containment area.
129 General Is there a basis of design for the oil water reparatory? Flow?
See PPI Attachment #95 - B72 Fuel Oil Water Separator As built for OWS requirements and operations.
130 General Please clarify the use of the tanks as emergency truck fuel, is there to be a dispenser?
Option #3: Fuel Oil Fill Station shall be removed from the RFP. Section 1.8 from the SOW shall be disregarded.
131 General Fuel oil pumps, please provide the requied flow and output pressure.
See PPI Attachment #95 - B72 Fuel Oil Water Separator As built for OWS requirements and operations.
(End of Summary of Changes)