RFP_Q_ _A_13.docx

DOCX document 29 KB Posted

Attached to
USNS SPEARHEAD Federal contract opportunity
Solicitation number
N32205-15-R-4006
Issued by
Department of the Navy Military Sealift Command

View the file

Other files for this federal contract opportunity

Other files attached to USNS SPEARHEAD, newest first.
File Type Posted
N32205-15-R-4006-0005.doc DOC document
RFP_Q_ _A_11.docx DOCX document
J_-_2_Category_A_Items_Spearhead_ROH.xls XLS spreadsheet
0910_A_RIDE_CONTROL_SCF_BEARING_SUPPORT_REV_A_(TALT_XXR).docx DOCX document
RFP_Q_ _A_10.docx DOCX document
0011_A_GENERAL_SERVICES_FOR_SHIP_REV_A.docx DOCX document
J_-_1_SPEARHEAD-_ROH_WI_Index_ROH.docx DOCX document
0304_A_MODIFY_EXTERIOR_FLOOD_LIGHTING_REV_A.docx DOCX document
AMENDMENT_N32205-14-R-4006-0004.doc DOC document
RFP_Q_ _A_10.docx DOCX document
RFP_Q_ _A_11.docx DOCX document
RFP Q A 6.docx DOCX document
RFP Q A 9.docx DOCX document
N32205-15-R-4006-03.doc DOC document
RFP Q A 8.docx DOCX document
RFP Q A 7.docx DOCX document
RFP Q A 12.docx DOCX document
J A_Mod_1_OEM_Reps_-_USNS_SPEARHEAD_(FebBizOps).docx DOCX document
RFP_Q_ _A_4.docx DOCX document
0609_A_FIRE DOOR MAINT REV A.docx DOCX document
0304_A_MODIFY_EXTERIOR_FLOOD_LIGHTING REV A.docx DOCX document
0910_A_RIDE CONTROL SCF BEARING SUPPORT REV A —
RFP_Q_ _A_5.docx DOCX document
0906_A_RIDE CONTROL SYSTEM MAINT REV A.docx DOCX document
AMENDMENT_N32205-15-R-4006-02.doc DOC document
0510_A_REBUILD FIREPUMP REV A.docx DOCX document
0302_A_ PLC SURVEY REV A.docx DOCX document
0101_A_ INSPECT FLIGHT DECK TIE DOWNS REV A.docx DOCX document
0102_A_STRUCTURAL INSPECTIONS REV A.docx DOCX document
RFP_Q_ _A_2.docx DOCX document
RFP_Q_ _A_3.docx DOCX document
0907_A_WATERJET MAINTENANCE REV A.docx DOCX document
0903_A_ INSPECT SEA VALVES AND SEA CHESTS REV A.docx DOCX document
0506_A_TEST MAIN AIR RECEIVERS REV A.docx DOCX document
0905_A_INSPECT AND REPAIR UW HULL COATING REV A.docx DOCX document
0803_A_HVAC SYSTEM ANNUAL MAINT REV A.docx DOCX document
0011_A_GENERAL SERVICES FOR SHIP REV A.docx DOCX document
0908_B_REMOVE WATERJET JETAVATOR REV A.doc DOC document
RFP-RFQ_Q_ A__1.docx DOCX document
N32205-15-R-4006_P00001.doc DOC document
SPHD_15-R-4006_J_Attachments.zip ZIP file
N32205-15-R-4006.doc DOC document
SPHD_15-R-4006_CDRLS.zip ZIP file
Spearhead_J A.PDF PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-15-R-4006

QUESTIONS AND ANSWERS

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

SPECIFICATION ITEM NO.: _____511________________

PARAGRAPH / SECTION NO.: _____Various___________

TITLE: ____WASTE OIL TANK REPAIR AMENDMENT B______

QUESTION:

1. None of the references were provided with the item and they are critical for fabrication. Please forward all references.

2.0REFERENCES
2.1DWG 8444467_D Waste Oil Tank 4000L
2.2DWG 8442868_D Material List
2.3DWG 8443695_C Module H04P Machinery Space Arrangement
2.4DWG 8443696_D Module H04P Equipment Removal Route
2.5DWG 8442890_C Typical Structural Frames Hull Void 42-51
2.6DWG 8442897_F Structural Plan Main Deck

2. Is the intent of the item to fabricate a new port waste oil tank in its entirety? What does the reference to shell plating mean?

3. Will any work be accomplished on the starboard oil tank?

4. Will any main deck plating be replaced or is reference 2.6 provided because the expected rigging route will pass through the main deck?

ANSWER:

1. References available via AMRDEC SAFE Website.

2. Yes, fabricate a new port waste oil tank in its entirety. Reference to shell plating refers to the plating making up the tank boundary. Tank is a free standing tank and thus does not share a boundary with the ships shell.

3. Starboard tank will be coated.

4. Reference 2.6 is provided for purposes of rigging route development. Apart from possible rigging route interference the main deck is not required to be replaced. Contractor shall use this reference along with the remaining references to determine the optimal rigging route to submit for MSCREP approval.

File details come from the government source that posted it. Updated .