0302_A_ PLC SURVEY REV A.docx

DOCX document 44 KB Posted

Attached to
USNS SPEARHEAD Federal contract opportunity
Solicitation number
N32205-15-R-4006
Issued by
Department of the Navy Military Sealift Command

About this file

WI 0302

View the file

Other files for this federal contract opportunity

Other files attached to USNS SPEARHEAD, newest first.
File Type Posted
N32205-15-R-4006-0005.doc DOC document
RFP_Q_ _A_13.docx DOCX document
0910_A_RIDE_CONTROL_SCF_BEARING_SUPPORT_REV_A_(TALT_XXR).docx DOCX document
RFP_Q_ _A_10.docx DOCX document
0011_A_GENERAL_SERVICES_FOR_SHIP_REV_A.docx DOCX document
J_-_1_SPEARHEAD-_ROH_WI_Index_ROH.docx DOCX document
0304_A_MODIFY_EXTERIOR_FLOOD_LIGHTING_REV_A.docx DOCX document
AMENDMENT_N32205-14-R-4006-0004.doc DOC document
RFP_Q_ _A_11.docx DOCX document
J_-_2_Category_A_Items_Spearhead_ROH.xls XLS spreadsheet
RFP_Q_ _A_10.docx DOCX document
RFP_Q_ _A_11.docx DOCX document
N32205-15-R-4006-03.doc DOC document
RFP Q A 6.docx DOCX document
RFP Q A 9.docx DOCX document
RFP Q A 8.docx DOCX document
RFP Q A 7.docx DOCX document
RFP Q A 12.docx DOCX document
0907_A_WATERJET MAINTENANCE REV A.docx DOCX document
0903_A_ INSPECT SEA VALVES AND SEA CHESTS REV A.docx DOCX document
0506_A_TEST MAIN AIR RECEIVERS REV A.docx DOCX document
0905_A_INSPECT AND REPAIR UW HULL COATING REV A.docx DOCX document
0510_A_REBUILD FIREPUMP REV A.docx DOCX document
0101_A_ INSPECT FLIGHT DECK TIE DOWNS REV A.docx DOCX document
0102_A_STRUCTURAL INSPECTIONS REV A.docx DOCX document
RFP_Q_ _A_2.docx DOCX document
RFP_Q_ _A_3.docx DOCX document
0803_A_HVAC SYSTEM ANNUAL MAINT REV A.docx DOCX document
0011_A_GENERAL SERVICES FOR SHIP REV A.docx DOCX document
0908_B_REMOVE WATERJET JETAVATOR REV A.doc DOC document
J A_Mod_1_OEM_Reps_-_USNS_SPEARHEAD_(FebBizOps).docx DOCX document
RFP_Q_ _A_4.docx DOCX document
0609_A_FIRE DOOR MAINT REV A.docx DOCX document
0304_A_MODIFY_EXTERIOR_FLOOD_LIGHTING REV A.docx DOCX document
0910_A_RIDE CONTROL SCF BEARING SUPPORT REV A —
RFP_Q_ _A_5.docx DOCX document
0906_A_RIDE CONTROL SYSTEM MAINT REV A.docx DOCX document
AMENDMENT_N32205-15-R-4006-02.doc DOC document
N32205-15-R-4006_P00001.doc DOC document
RFP-RFQ_Q_ A__1.docx DOCX document
SPHD_15-R-4006_CDRLS.zip ZIP file
N32205-15-R-4006.doc DOC document
Spearhead_J A.PDF PDF
SPHD_15-R-4006_J_Attachments.zip ZIP file
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS SPEARHEAD

(JHSV-1)

MACHINERY, PROPULSIONN32205-15-R-4006
31 May 2015
ITEM NO. 302 Category “A”MSC/PALANDRO/SM
PLC SURVEY

1.0 ABSTRACT

1.1 This item describes the requirements to perform a survey of all Automation Programmable Logic Controllers (PLC) and Human Machine Interfaces (HMI) and providing applicable support software for the purpose of documenting and maintaining the existing class configuration.

2.0 REFERENCES/ENCLOSURES:

2.1 References:

2.1.1 Drawing No. 8443074_A, Electrical System Overview Layout of Panels

2.1.2 Drawing No. 8442941_B, Electric Plan Control System

2.1.3 Drawing No. 8442940_C, Machinery Control System and Monitoring System

2.1.4 JHSV Software 3_2012

2.1.5 JHSV PC PSWD LIST

2.1.6 T-AKE PLC Summary

2.1.7 TAKE-2 Automation Survey Results

2.1.8 Load CTR Batteries

2.1.9 Tech Manual S9247-AM-MMC-010: Lipstronic Waterjet Control System

2.2 Enclosures: None

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location: Various locations throughout the vessel

4.0 GOVERNMENT FURNISHED EQUIPMENT/ MATERIAL / SERVICE

4.1 GOVERNMENT FURNISHED EQUIPMENT: NONE

4.2 GOVERNMENT FURNISHED MATERIALS: NONE

4.3 GOVERNMENT FURNISHED SERVICES: 110V Electrical service. Government will not furnish wiring, plugs and receptacle connectors.

5.0 NOTES

5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s including but not limited to GTR’s 1 through 7, 22, 23, 26, 28 and 29.

5.2 The contractor shall not operate ship’s equipment.

5.3 The contractor shall follow the MSC Lock Out Tag Out Procedure administered by the vessel’s Chief Engineer.

6.0 QUALITY ASSURANCE REQUIREMENTS

6.1 The contractor is responsible for cleaning all areas disturbed as a result of work performed.

7.0 STATEMENT OF WORK REQUIRED

7.1 Arrangement/Outfitting: None

7.2 Structural Modifications: None Additional

7.3 Mechanical/Fluids: None Additional

7.4 Electrical: None Additional

7.5 Electronics:

7.5.1 Verify with Chief Engineer that ship’s crew performed Lock Out and Tag Out of effected systems prior to work start.

7.5.2 Using references 2.1.1 thru 2.1.7 as guidance Perform survey of vessels PLCs and HMIs related to all machinery automated control systems. Submit survey report to MSCREP.

7.5.3 Provide and replace a total of 42 load center batteries using reference 2.1.7 as guidance. Ensure that government furnished Austal rep has recorded existing configuration prior to battery replacement.

7.5.4 Provide and replace a total of 8 wartsila lipstronic Q CPU batteries using reference 2.1.8 as guidance. Battery replacement shall be supervised by wartsila rep provided in WI 907. Ensure that Wartsila rep has recorded existing configuration prior to battery replacement.

7.5.5 Perform the following for each PLC and HMI identified in para 7.5.2:

7.5.5.1 Document and obtain all software, instruction manuals, interface cables and equipment required to access to each component. Document these items on a list and provide one copy of this list to the MSCREP and one copy to the vessel upon equipment turnover listed in para 7.5.3.3.

7.5.5.1.1 Software shall include any programs required to develop, debug, compile and build the program used by each PLC or HMI.

7.5.5.1.2 Instruction manuals shall include instructions for set up, generation, compiling, and debugging all software.

7.5.5.2 Download the existing source code from each of the components listed in survey. Document all the components which were unable to download the program and provide that to MSCREP so he can pursue acquiring these from original providers.

7.5.5.2.1 Contact vendors to acquire any software that could not be uploaded or otherwise obtained.

7.5.5.3 Source and provide to CHENG all software, existing source code files and manuals in CD format. Label and provide all interface cables and equipment to CHENG.

7.5.5.4 Install software, source code files and software manuals onto the ships maintenance laptop provided by CHENG.

7.5.5.5 All documentation, files, software, manuals and hardware delivered to the ship shall be organized to allow for control and means to maintain it.

7.5.6 Provide to the MSCREP a detailed report containing all items delivered to the vessel. Final report shall be in format of 2.1.6 and 2.1.7.

8.0 General Requirements: NONE