0907_A_WATERJET MAINTENANCE REV A.docx

DOCX document 40 KB Posted

Attached to
USNS SPEARHEAD Federal contract opportunity
Solicitation number
N32205-15-R-4006
Issued by
Department of the Navy Military Sealift Command

About this file

WI 0907

View the file

Other files for this federal contract opportunity

Other files attached to USNS SPEARHEAD, newest first.
File Type Posted
N32205-15-R-4006-0005.doc DOC document
0910_A_RIDE_CONTROL_SCF_BEARING_SUPPORT_REV_A_(TALT_XXR).docx DOCX document
RFP_Q_ _A_10.docx DOCX document
0011_A_GENERAL_SERVICES_FOR_SHIP_REV_A.docx DOCX document
J_-_1_SPEARHEAD-_ROH_WI_Index_ROH.docx DOCX document
RFP_Q_ _A_11.docx DOCX document
J_-_2_Category_A_Items_Spearhead_ROH.xls XLS spreadsheet
0304_A_MODIFY_EXTERIOR_FLOOD_LIGHTING_REV_A.docx DOCX document
AMENDMENT_N32205-14-R-4006-0004.doc DOC document
RFP_Q_ _A_13.docx DOCX document
RFP_Q_ _A_10.docx DOCX document
RFP_Q_ _A_11.docx DOCX document
RFP Q A 6.docx DOCX document
RFP Q A 9.docx DOCX document
RFP Q A 8.docx DOCX document
RFP Q A 7.docx DOCX document
RFP Q A 12.docx DOCX document
N32205-15-R-4006-03.doc DOC document
0510_A_REBUILD FIREPUMP REV A.docx DOCX document
0302_A_ PLC SURVEY REV A.docx DOCX document
0101_A_ INSPECT FLIGHT DECK TIE DOWNS REV A.docx DOCX document
0102_A_STRUCTURAL INSPECTIONS REV A.docx DOCX document
RFP_Q_ _A_2.docx DOCX document
RFP_Q_ _A_3.docx DOCX document
J A_Mod_1_OEM_Reps_-_USNS_SPEARHEAD_(FebBizOps).docx DOCX document
RFP_Q_ _A_4.docx DOCX document
0609_A_FIRE DOOR MAINT REV A.docx DOCX document
0304_A_MODIFY_EXTERIOR_FLOOD_LIGHTING REV A.docx DOCX document
0910_A_RIDE CONTROL SCF BEARING SUPPORT REV A —
RFP_Q_ _A_5.docx DOCX document
0906_A_RIDE CONTROL SYSTEM MAINT REV A.docx DOCX document
AMENDMENT_N32205-15-R-4006-02.doc DOC document
0803_A_HVAC SYSTEM ANNUAL MAINT REV A.docx DOCX document
0011_A_GENERAL SERVICES FOR SHIP REV A.docx DOCX document
0908_B_REMOVE WATERJET JETAVATOR REV A.doc DOC document
0903_A_ INSPECT SEA VALVES AND SEA CHESTS REV A.docx DOCX document
0506_A_TEST MAIN AIR RECEIVERS REV A.docx DOCX document
0905_A_INSPECT AND REPAIR UW HULL COATING REV A.docx DOCX document
RFP-RFQ_Q_ A__1.docx DOCX document
N32205-15-R-4006_P00001.doc DOC document
N32205-15-R-4006.doc DOC document
SPHD_15-R-4006_J_Attachments.zip ZIP file
Spearhead_J A.PDF PDF
SPHD_15-R-4006_CDRLS.zip ZIP file
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS SPEARHEAD

(JHSV 1)

DRYDOCKING AND UNDOCKINGN32205-15-R-4006
31 May 2015
ITEM NO. 0907Category "A"MSC-Norfolk/Palandro/RP

WATERJET MAINTENANCE

1.0 ABSTRACT:

1.1 This item describes maintenance of for Wartsila Waterjet units.

2.0 REFERENCES:

2.1 T/M S9230-AL-MMC-010, Waterjet Propulsors Model WLD 1400 SR

2.2 MSC Standard Item 25 Prop Blade Polishing

2.3 Removal of Seat Ring without Shaft or Impeller Removal

2.4 Reversing Bucket NDT

2.5 JHSV-1WJ Reversing Plate Failures_SEPT2014

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Location/Quantity
3.1.1 Location: Waterjets #1, #2, #3 and #4, Frame 82

4.0 GOVERNMENT-FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Shaft Seal PN H78480-01-7 Seal Kit, (split)

5.0 NOTES:

5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s.

5.2 The contractor and all subcontractors, regardless of tier are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

5.3 The Shipyard shall furnish, fabricate, procure as necessary, all tools and equipment recommended by the O.E.M. Wartsila to perform the removals and installations. This includes all lifting and rigging equipment.

QUALITY ASSURANCE REQUIREMENTS: None Additional

STATEMENT OF WORK REQUIRED:

5.4 The Shipyard shall furnish the services of a Wartsila Technical Representative to oversee and perform all waterjet work described by this work item.

5.5 Perform UT Shearwave inspection of welds identified on all four Waterjet Jetavator Reversing Plates. Reference 2.4 and 2.5

5.6 Remove Waterjet #2 Jetavator and Seat Ring for Inspection.

5.6.1 Use Wartsila Guidance per Reference 2.3. Do not remove shaft or shaft Vulkan Coupling.

5.6.2 Return Jetavator and Seat Ring with contractor furnished seals and gaskets.

5.6.3 Perform cleaning, polish, NDT dye penetrant inspection of impeller lead and trailing blades IAW instruction within.

5.7 During dry docking, the water in the stator bowl must be drained. Neglecting this can cause corrosion damage.

5.8 The contractor shall perform Waterjet to vessel hull isolation electrical continuity readings. Readings shall be recorded in Megohms and provided to MSC Rep. Readings shall be witnessed by Chief MSCREP. All Readings shall be taken with vessel out of the water and shaft seals drained of water. Readings shall include Hull to Jetavator, Hull to Shaft, Hull to Thrust Bearing, Hull to Shaft Seal. For any disassembly these readings shall be taken upon assembly and prior to shaft seal hydro testing and vessel entering water.

5.9 Perform Water Lubricated Bearing and Shaft Clearance readings for all four units.

5.9.1 The Water Lubricated Bearing readings shall be taken using the feeler gauge method at the 12:00, 3:00, 6:00 and 9:00 (o-clock) positions per the O.E.M. instruction.

5.9.2 Take measurements of the clearance between blade tips of the impeller and the seat ring (housing of the impeller) prior to any disassembly and upon re-assembly. Readings shall be recorded and submitted to the MSCREP via condition report.

5.9.3 ABS, MSCREP shall witness all readings.

5.10 Furnish materials to inspect and rebuild one Shaft Seal to be determined by MSCREP. Shaft Seal faces shall be re-used unless determined to be not suitable. Shaft Seal if required shall be GFE.

5.11 Inspect Ground wires on Jetavators.

5.11.1 Furnish and replace four (4) EA Ground Wires.

5.12 Contractor shall build scaffolding underneath the vessel at each Waterjet Duct inlet and Jetavator to provide inspection and access at all times vessel is in dry-dock. Scaffolding shall be installed within 72 hours of vessel docking. This is in addition to operator assisted lift equipment.

5.13 Clean The Water Jet Shafts and Impellers

5.13.1 Jetavator shall be thoroughly cleaned of all barnacles and sea growth using 2500 PSI Water Jet Blast and cleaning tools.

5.13.2 Apply 3 coats of Rydlyme to shaft and impeller and allow soak for 30 minutes between applications.

5.13.3 Inspect shaft blades for imperfections.

5.13.4 Perform NDT dye penetrate examination of each impeller. Dye-check the blade palms and the blade leading and trailing faces. NDT shall be observed by the MSCREP and ABS Surveyor.

5.13.5 Provide a condition report of all findings.

5.14 Clean the removed Seat Ring. Prepare external surface and repair coating using International Intersleek 970 Coating System to match existing. Coating shall be applied in accordance with Wartsila surface profile requirement.

5.15 Clean hull transom Seat Ring seating surface, coat with two applications of epoxy Intergaurd 264.

5.16 Re-install Seat Ring in accordance with OEM Recommendations using 2.3 as guidance and contractor furnished seal.

5.17 Furnish and replace all Waterjet Jetavator Steering and Reversing Cylinder Hydraulic Hoses.

5.17.1 Jetavator installed Steering and Reversing Hydraulic Hoses shall be O.E.M. replacement hoses.

5.17.2 Vessel’s Transom to Jetavator Steering and Reversing Hoses shall be Parker 722-16 4000 PSI. No substitutes without MSCREP authorization.

5.17.3 All hoses shall be pre-tested, tagged with stainless ID to identify test pressure and date of test.

5.17.4 Contractor shall furnish a hydraulic hose list include hose, type, fitting designation for each end, size diam, length, test pressure. Each hose shall be identified individually. The hose schedule shall be included in the Representatives final report.

5.17.5 All removed hoses shall be drained, ends capped and retained onboard vessel for spares.

5.18 Wartsila Rep shall perform an inspection of the current collector.

5.18.1 Contractor shall furnish and replace current collector contacts/brushes for all four shafts and perform a general maintenance of the system.

5.19 Wartsila Rep shall inspect and perform calibration of Steering and Reversing systems. Follow-up and Non-Follow up shall be inspected and adjusted and verified with all local and remote indicators.

5.20 Preparation of Drawings/Documents:

Service Reports: Provide a service report from the technical representatives including all critical measurements and maintenance performed.

5.21 Manufacturer’s Representative:

5.21.1 Provide the services of a manufacturer's representative during inspections. Wartsila Rep. shall be present for final testing to include Dock Trial IAW WI 022.

Wartsila Defense Inc.

Tony Hughes 3617 Koppens Way Chesapeake, VA 23323 Office: 757-966-5438 Fax: 757-966-3627 Cell: 757-409-7426 Tony.Hughes@wartsiladefense.com

8.0 GENERAL REQUIREMENTS: None additional.

0907-4