Mech 035 - Pages 4-6.pdf
PDF 42 MB Posted
- Attached to
- Y1DA--504-18-119 Replace Boilers and Piping Federal contract opportunity
- Solicitation number
- 36C25722R0010
About this file
This document provides details on a federal contract solicitation. The solicitation number is 36C25722R0010 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17 for replacing boilers and piping at VA-22-00004245. The opportunity type is listed as a solicitation to replace existing boilers and piping. No other salient details are provided in this document.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 36C25722R0010 0001.docx | DOCX document | |
| Past Performance Questionnaire.pdf | ||
| Answers to Questions 36C25722R0010 DB Replace Boilers.pdf | ||
| VA NOTICE OF LIMITATIONS ON SUBCONTRACTING REQUIREMENT.pdf | ||
| Mech 035 - Pages 1-3.pdf | ||
| OSHA - EMR requirement.pdf | ||
| BP-3-Boiler-steam.pdf | ||
| BP-1-Boiler-fueloil.pdf | ||
| 36C25722R0010_1.docx | DOCX document | |
| Mech 035 - Pages 7-12.pdf | ||
| Phasing sheets.pdf | ||
| Struct 035.pdf | ||
| SELF-PERFORMED CALCULATIONS.pdf | ||
| Mech 035 - Pages 8-19.pdf | ||
| BP-2-Boilers-natgasandpropane.pdf | ||
| 20-09 035 Narrative 02 1r1 Phasing Narrative.pdf | ||
| 20-09 035 Narrative 06 1r1 Civil-LS Design Narrative.pdf | ||
| 20-09 035 Narrative 13 1r1 Specs TOC 000110 035 21-06-30.pdf | ||
| AS ST Series Sheets.pdf | ||
| AD AE Series Sheets.pdf | ||
| Elect 035.pdf | ||
| G Series Sheets.pdf | ||
| BP-4-Water-Treatment.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STORAGE
ELEVATOR/MACH
MECHANICAL
ROOM
1005B
EXISTING HEAT
EXCHANGER ABOVE
AHU
EXISTING AHU
REPLACE EXISTING
PRESSURE
REDUCING VALVE
REPLACE EXISTING
STEAM TO HOT
WATER HEAT
EXCHANGER
3/4" CONDESATE
MPS
GENERAL NOTES:
1. REINSULATE EXISTING STEAM AND CONDENSATE PIPING.
FURNISH LABELS ON ALL STEAM AND CONDENSATE PIPING.
2. RE-PIPE EXISTING CONDENSATE AND REMOVE ABANDONED
PIPING.
EXISTING HEAT
EXCHANGER ABOVE
AHU TO REMAIN
EXISTING AHU-19
REPLACE EXISTING
PRESSURE
REDUCING VALVE
REPLACE CONDESATE
RECEIVER WITH DUAL
PUMP CONDENSATE
RECEIVER
HPS FROM FLOOR
BELOW
REPLACE EXISTING
DOMESTIC HOT
WATER HEAT
EXCHANGER
3/4" CONDESATE
MPS
GENERAL NOTES:
1. REINSULATE EXISTING STEAM AND CONDENSATE PIPING.
FURNISH LABELS ON ALL STEAM AND CONDENSATE PIPING.
2. RE-PIPE EXISTING CONDENSATE AND REMOVE ABANDONED
PIPING.
NO SCALE2
DOMESTIC RECIRC PUMP
NO SCALE3
CONDENSATE PIPING
NO SCALE4
PIPE RISER
NO SCALE5
CONDENSATE RECEIVER
NO SCALE14
CONDENSATE RECEIVER
NO SCALE15
DOMESTIC RECIRC PUMP
NO SCALE16
PRV
NO SCALE10
WATER HEATER
NO SCALE11
AHU AND HEAT EXCHANGER
NO SCALE12
UNINSULATED PIPE
NO SCALE13
UNINSULATED PIPING
NO SCALE6
RISERS FROM TUNNEL
NO SCALE7
PRV
NO SCALE8
WATER HEATER
NO SCALE9
UNINSULATED PIPE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMP
321 4 5 6 7 8 9 10
Calvin rchitects, P.C.L 3705 North 200th Street
Elkhorn, Nebraska 68022
Phone: 402.291.6941 Fax: 402.291.9193
AH. INZ
Shaffer & Stevens 9910 North 48th Street
Omaha, Nebraska68152
Phone: 402.455.7698 Fax: 402.455.7597
504-18-119
AMI Environmental Inc
8802 S 135th Street
Omaha, NE 68138
Phone:(402) 397-5001
IMEG Corp.
14755 Preston Rd., Suite 845
Dallas, TX 75254
Phone:(972) 239-6100
15% Design Submission 07/14/2020
20% Design Submission
30% Design Submission
35%/SD1 Schematic Design Submission
09/08/2020
08/14/2020
11/17/2020
FOR REFERENCE
ONLY NOT FOR
CONSTRUCTION
C R e v it L o c a l F ile s \M
E
.0
A m a ri llo B o ile r R e p la c e m e n t_ C d e ta c h e d
P a u l.
W
.L ic h te n h a n .r v t
/1 /2
:4
:5
P M
04-M-100
EXISTING CONDITIONS PLAN AND
PHOTOS - MECH ROOM - BLDG 4
November 17, 2020
Replace Boilers and PipingSD-1 35% SUBMITTAL
REQUEST FOR PROPOSAL
Thomas E. Creek VAMC-Amarillo, TX
REFERENCE SCALE IN INCHES
0 1 2 3
PROJECT #
IMEG CORP RESERVES PROPRIETARY RIGHTS, INCLUDING COPYRIGHTS, TO THIS
DRAWING AND THE DATA SHOWN THEREON. SAID DRAWING AND/OR DATA ARE
THE EXCLUSIVE PROPERTY OF IMEG CORP AND SHALL NOT BE USED OR
REPRODUCED FOR ANY OTHER PROJECT WITHOUT THE EXPRESS WRITTEN
APPROVAL AND PARTICIPATION OF IMEG CORP. © 2020 IMEG CORP.
14755 PRESTON ROAD, SUITE 845
DALLAS, TX 75254
972.239.6100 FAX: 972.239.6102
www.imegcorp.com
TBPE# F-18632
20001967.00
N O R
HT
1/4" = 1'-0"
FIRST FLOOR PLAN- BLDG. 4 - MECHANICAL ROOM 1001
Revisions: Date:
1 1/2"LPC
4"LPS
11-B-4
(EXIST)
11-B-3 11-B-2 11-B-1
11-DA-1
11-HVU-1
2.2
C K M N
4A
A
2.7
B
GD E F
3.5
L
2.2
H
1A
JC1
19-SW-2 19-SW-319-SW-1
EXISTING
LOUVER TO
REMAIN
6"HPS
6"HPS
6"HPS
4"HPS
"H
P S
2"RO
2"SCW
2"CW
11-B-2 11-B-311-B-4 11-B-1
DA-1
1 1
ST-1
(EXIST)
19-WS-219-WS-1 19-WS-319-BT-1
(EXIST)
4"CW
(EXIST)
2"SW
(EXIST)
2"RO
(EXIST)
2"SW
(EXIST)
2"CW
(EXIST)
2"CW
(EXIST)
2.2
C K M N
4A
A
2.7
B
GD E F
3.5
L
2.2
H
1A
JC1
15 9
16 16
2"LPS
(EXIST)
1"LPC
(EXIST)
FLOW METER
(EXIST)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMP
321 4 5 6 7 8 9 10
Calvin rchitects, P.C.L 3705 North 200th Street
Elkhorn, Nebraska 68022
Phone: 402.291.6941 Fax: 402.291.9193
AH. INZ
Shaffer & Stevens 9910 North 48th Street
Omaha, Nebraska68152
Phone: 402.455.7698 Fax: 402.455.7597
504-18-119
AMI Environmental Inc
8802 S 135th Street
Omaha, NE 68138
Phone:(402) 397-5001
IMEG Corp.
14755 Preston Rd., Suite 845
Dallas, TX 75254
Phone:(972) 239-6100
15% Design Submission 07/14/2020
20% Design Submission
30% Design Submission
35%/SD1 Schematic Design Submission
09/08/2020
08/14/2020
11/17/2020
FOR REFERENCE
ONLY NOT FOR
CONSTRUCTION
C R e v it L o c a l F ile s \M
E
.0
A m a ri llo B o ile r R e p la c e m e n t_ C d e ta c h e d
P a u l.
W
.L ic h te n h a n .r v t
/1 /2
:5
:5
P M
11-M-100
FIRST FLOOR PLAN - MECHANICAL -
BLDGS. 11, 16, & 19
November 17, 2020
Replace Boilers and PipingSD-1 35% SUBMITTAL
REQUEST FOR PROPOSAL
Thomas E. Creek VAMC-Amarillo, TX
REFERENCE SCALE IN INCHES
0 1 2 3
PROJECT #
IMEG CORP RESERVES PROPRIETARY RIGHTS, INCLUDING COPYRIGHTS, TO THIS
DRAWING AND THE DATA SHOWN THEREON. SAID DRAWING AND/OR DATA ARE
THE EXCLUSIVE PROPERTY OF IMEG CORP AND SHALL NOT BE USED OR
REPRODUCED FOR ANY OTHER PROJECT WITHOUT THE EXPRESS WRITTEN
APPROVAL AND PARTICIPATION OF IMEG CORP. © 2020 IMEG CORP.
14755 PRESTON ROAD, SUITE 845
DALLAS, TX 75254
972.239.6100 FAX: 972.239.6102
www.imegcorp.com
TBPE# F-18632
20001967.00
KEYNOTES:
1. PROVIDE NEW BOILER BREECHING
ECONOMIZER AT NEW BOILER. (TYPICAL OF
BOILER 1, 2 & 3)
2. PROVIDE NEW 250 BHP BOILER AS
SCHEDULED. (TYPICAL OF BOILER 1, 2 & 3)
3. 2" BOILER BLOW DOWN. RUN PIPING IN
EXISTING TRENCH. (TYPICAL OF BOILER 1, 2 &
3)
4. BOILER SAFETY RELIEF VALVE PIPING UP
THROUGH ROOF. (TYPICAL OF BOILER 1, 2 & 3)
5. NEW 2" BOILER BLOW DOWN MAIN PIPING IN
EXISTING TRENCH. ROUTE TO NEW BOILER
BLOW DOWN SEPARATOR.
6. NEW BOILER BLOWDOWN SEPARATOR. ROUTE
NEW VENT UP THROUGH ROOF AND CONNECT
AFTER COOLER TO DRAIN.
7. FURNISH NEW BOILER FUEL OIL PIPING.
8. PROVIDE NEW BOILER FUEL OIL PUMPS.
9. FURNISH NEW BOILER HIGH PRESSURE STEAM
HEADER WITH SHUT OFF VALVES AND DRAIN
AS REQUIRED TO CONNECT NEW BOILERS.
10. 1" BOILER FEEDWATER SUPPLY AND RETURN
TO ECONOMIZER. (TYPICAL OF BOILER 1, 2 & 3)
11. NEW BOILER FUEL OIL SUPPLY AND RETURN
PIPING. ROUTE IN EXISTING PIPE TRENCH TO
EACH NEW BOILER.
12. PROVIDE NEW BOILER ROOM COMBUSTION AIR
SUPPLY UNIT. FURNISH WITH STEAM HEATING
COIL. CONNECT INTAKE DUCTWORK TO
EXISTING LOUVER. ROUTE NEW DISTRIBUTION
DUCTWORK THROUGHOUT BOILER PLANT AS
SHOWN.
13. PROVIDE NEW STEAM HEADER SUPPORT
PEDESTAL SIMILAR TO EXISTING.
14. REPLACE EXISTING WATER SOFTENERS. (TYP.)
15. FURNISH NEW DEARATOR. EXISTING PUMPS
TO REMAIN RECONNECT TO EXISTING PIPING.
16. NEW 8" HPS EMERGENCY CONNECTION.
PROVIDE CONDENSATE PIPING AND NATURAL
GAS PIPE CONNECTIONS. COORDINATE EXACT
LOCATION WITH OWNER.
17. PROVIDE 1-1/4" MAKEUP COLD WATER
CONNECTION FOR DEARATOR.
18. FURNISH NEW BOILER ROOM EXHAUST FAN
VENTILATION SYSTEM.
N O R
HT
1/8" = 1'-0"
FIRST FLOOR PLAN - MECHANICAL
ADD ALTERNATE:
19. PROVIDE NEW GENERATOR FLUE AND
MUFFLER. CONNECT FUEL OIL PIPING TO
EXISTING. FURNISH NEW RADIATOR DUCT
CONNECTION FROM RADIATOR TO EXISTING
LOUVER. REFER TO 6/M307
N O R
HT
1/8" = 1'-0"
FIRST FLOOR DEMOLITION - MECHANICAL
DEMOLTION KEYNOTES:
1. DEMOLISH EXISTING 200 BHP BOILER AND ALL
ASSOCIATED APPURTENANCES INCLUDING
BOILER BREECHING AND CATWALK PLATFORM
(TYPICAL 3). BOILER #4 TO REMAIN.
2. DEMOLISH EXISTING DEAERATOR AT
MEZZANINE LEVEL AND ALL ASSOCIATED
APPURTENANCES. PUMPS TO REMAIN.
3. DEMOLISH EXISTING WATER SOFTENERS.
4. EXISTING BRINE TANK TO REMAIN.
5. EXISTING REVERSE OSMOSIS TRANSFER
PUMPS TO REMAIN.
6. EXISTING REVERSE OSMOSIS WATER
STORAGE TANKS TO REMAIN.
7. EXISTING REVERSE OSMOSIS FILTER SYSTEM
TO REMAIN.
8. EXISTING CHARCOAL FILTER WATER TANK TO
REMAIN.
9. EXISTING CONDUIT TRAY OVERHEAD TO
REMAIN.
10. DEMOLISH EXISTING BOILER BLOW DOWN
SEPARATOR TANK, INCLUDING VENT AND
DRAIN.
11. EXISTING DUPLEX CONDENSATE PUMP UNIT IN
LOWER LEVEL TO REMAIN.
12. DEMOLISH EXISTING BOILER PLANT EXHAUST
FAN SYSTEM.
13. DEMOLISH COMBUSTION AIR SUPPLY UNIT
INCLUDING DUCTWORK, PIPING, AND AIR
DEVICES.
14. DEMOLISH EXISTING BOILER FUEL OIL PUMPS
INCLUDING FUEL OIL PIPING TO EACH BOILER.
15. DEMOLISH EXISTING COLUMN MOUNTED
STEAM PRESSURE TRANSMITTERS.
16. REMOVE EXISTING GANTRY AND TROLLEY AS
REQUIRED FOR NEW BOILER PLACEMENT.
GANTRY AND TROLLEY SHALL BE REUSED AND
REPOSITIONED. REFER TO NEW WORK FOR
LOCATION. PRIOR TO REMOVAL OF GANTRY
THE CONTRACTOR SHALL TEMPORARILY
SUPPORT THE EXISTING BOILER FEED WATER
SUPPLY PIPING.
GENERAL NOTES:
1. REFER TO BOILER PLAN- WATER AND STEAM
DIAGRAMS. NEW WORK AND DEMO; SHEETS
M-400 AND M-401.
2. REFER TO BOILER FUEL OIL DIAGRAM NEW
AND DEMO ON SHEETS M-403 AND M-404.
C
4A
D
3.5
1A
C1
11-FOP-211-FOP-1
11-CP-1
11-CP-2
11-BDS-1
C
4A
D
3.5
1A
C1
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMP
321 4 5 6 7 8 9 10
Calvin rchitects, P.C.L 3705 North 200th Street
Elkhorn, Nebraska 68022
Phone: 402.291.6941 Fax: 402.291.9193
AH. INZ
Shaffer & Stevens 9910 North 48th Street
Omaha, Nebraska68152
Phone: 402.455.7698 Fax: 402.455.7597
504-18-119
AMI Environmental Inc
8802 S 135th Street
Omaha, NE 68138
Phone:(402) 397-5001
IMEG Corp.
14755 Preston Rd., Suite 845
Dallas, TX 75254
Phone:(972) 239-6100
15% Design Submission 07/14/2020
20% Design Submission
30% Design Submission
35%/SD1 Schematic Design Submission
09/08/2020
08/14/2020
11/17/2020
FOR REFERENCE
ONLY NOT FOR
CONSTRUCTION
C R e v it L o c a l F ile s \M
E
.0
A m a ri llo B o ile r R e p la c e m e n t_ C d e ta c h e d
P a u l.
W
.L ic h te n h a n .r v t
/1 /2
:5
:5
P M
11-M-101
PARTIAL LOWER LEVEL -
MECHANICAL- BLDG. 11
November 17, 2020
Replace Boilers and PipingSD-1 35% SUBMITTAL
REQUEST FOR PROPOSAL
Thomas E. Creek VAMC-Amarillo, TX
REFERENCE SCALE IN INCHES
0 1 2 3
PROJECT #
IMEG CORP RESERVES PROPRIETARY RIGHTS, INCLUDING COPYRIGHTS, TO THIS
DRAWING AND THE DATA SHOWN THEREON. SAID DRAWING AND/OR DATA ARE
THE EXCLUSIVE PROPERTY OF IMEG CORP AND SHALL NOT BE USED OR
REPRODUCED FOR ANY OTHER PROJECT WITHOUT THE EXPRESS WRITTEN
APPROVAL AND PARTICIPATION OF IMEG CORP. © 2020 IMEG CORP.
14755 PRESTON ROAD, SUITE 845
DALLAS, TX 75254
972.239.6100 FAX: 972.239.6102
www.imegcorp.com
TBPE# F-18632
20001967.00
N O R
HT
1/8" = 1'-0"
PARTIAL LOWER FLOOR PLAN - MECHANICAL
KEYNOTES:
1. NEW BOILER BLOW DOWN SEPARATOR TANK.
ROUTE VENT UP THROUGH ROOF AND
CONNECT UNIT DRAIN TO SANITARY DRAIN.
2. PROVIDE COLD WATER CONNECTION TO NEW
BLOW DOWN SEPARATOR.
3. NEW BOILER FUEL OIL PUMPS AS SCHEDULED.
PROVIDE FUEL SPILL CONTAINMENT PAN AT
PUMPS AND ROUTE FOS & FOR IN EXISTING
FLOOR TRENCH.
4. EXISTING CONDENSATE TRANSFER PUMPS TO
REMAIN.
5. EXISTING BOILER FEED PUMPS TO REMAIN.
6. PROVIDE NEW FEED WATER FILTER.
7. EXISTING AIR COMPRESSORS TO REMAIN.
8. 2" DEAERATOR OVERFLOW DRAIN DROP FROM
ABOVE.
9. CONNECT PUMPED CONDENSATE AT ELBOW
UP TO EXISTING DEAERATOR AT MEZZANINE
LEVEL.
N O R
HT
1/8" = 1'-0"
PARTIAL LOWER FLOOR DEMOLITION - MECHANICAL
DEMOLITION KEYNOTES:
1. DEMOLISH EXISTING BOILER BLOW DOWN
SEPARATOR TANK, INCLUDING VENT AND
DRAIN.
2. EXISTING CONDENSATE PUMP UNIT IN LOWER
LEVEL TO REMAIN.
3. DEMOLISH EXISTING BOILER FUEL OIL PUMPS
INCLUDING FUEL OIL PIPING TO EACH BOILER.
4. EXISTING CONDENSATE TRANSFER PUMPS TO
REMAIN.
5. EXISTING BOILER FEED PUMPS TO REMAIN.
6. DEMOLISH EXISTING WATER FILTER.
7. EXISTING AIR COMPRESSORS TO REMAIN.
8. DEMOLISH 2" DEAERATOR OVERFLOW DRAIN
DROP FROM ABOVE.
9. DEMOLISH PUMPED CONDENSATE FROM
ELBOW UP TO EXISTING DEAERATOR AT
MEZZANINE LEVEL.
File details come from the government source that posted it. Updated .