About this file

This document provides a narrative for the civil design and landscaping aspects of a federal contract opportunity to replace boilers and piping at a Veterans Affairs health care facility. The project involves removing existing boilers and installing new ones through openings in the exterior walls of an existing boiler plant. It also requires replacing an existing deaeration tank. The selected contractor will be responsible for designing and constructing temporary pathways for removing and installing the boilers and tank. Additional requirements include siting a temporary boiler and fencing against the building exterior, identifying laydown areas and providing temporary fencing, and protecting and restoring existing site features. The contractor must also submit a physical security risk mitigation plan.

The related federal contract opportunity is solicitation number 36C25722R0010 to replace boilers and piping at the Amarillo VA Health Care System in Amarillo, Texas. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--504-18-119 Replace Boilers and Piping, newest first.
File Type Posted
Answers to Questions 36C25722R0010 DB Replace Boilers.pdf PDF
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING REQUIREMENT.pdf PDF
Amendment 36C25722R0010 0001.docx DOCX document
Past Performance Questionnaire.pdf PDF
AS ST Series Sheets.pdf PDF
AD AE Series Sheets.pdf PDF
Elect 035.pdf PDF
G Series Sheets.pdf PDF
BP-4-Water-Treatment.pdf PDF
Mech 035 - Pages 1-3.pdf PDF
Mech 035 - Pages 4-6.pdf PDF
OSHA - EMR requirement.pdf PDF
BP-3-Boiler-steam.pdf PDF
BP-1-Boiler-fueloil.pdf PDF
36C25722R0010_1.docx DOCX document
Mech 035 - Pages 7-12.pdf PDF
Phasing sheets.pdf PDF
Struct 035.pdf PDF
SELF-PERFORMED CALCULATIONS.pdf PDF
Mech 035 - Pages 8-19.pdf PDF
BP-2-Boilers-natgasandpropane.pdf PDF
20-09 035 Narrative 02 1r1 Phasing Narrative.pdf PDF
20-09 035 Narrative 13 1r1 Specs TOC 000110 035 21-06-30.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2021-06-30 Rev CIVIL DESIGN & LANDSCAPING NARRATIVE C-1

REPLACE BOILERS & PIPING - AVAHCS

REPLACE BOILERS & PIPING

THOMAS E. CREEK AMARILLO VA HEALTH CARE SYSTEM

AMARILLO, TEXAS

35% Project Narrative - November 2020 (Rev 6/21)

CIVIL AND LANDSCAPING DESIGN NARRATIVE

I. PROJECT DATA

A. Project Description:

1. This renovation project does not have a Civil Engineer on the A/E Schematic Design

Team.

a. No indication for the need for civil engineering was provided in the Scope of

Work as project is primarily related to removal and replacement of steam boilers inside Building 11, steam/condensate piping replacement in underground steam tunnels, and work within other existing buildings on campus for plumbing and steam distribution.

2. No landscaping or irrigation is included as part of the design for this project.

3. The DB offeror is to provide design, construction, and restoration of pathways for removal of existing boilers and deaeration tank and installation of new ones.

a. The Schematic Design has determined that boilers are to be accessed through the west exterior wall of the Boiler Plant between existing columns/pilasters forming the bay which contains the 200hp Boiler #1.

1) The DB offeror may access the west temporary opening from parking lot

“K,” located to the west and downhill from Buildings 11 and 21, or along the west side of Building 11 from the drive on the west side of Building 19 and along the west side of Building 11.

1) Existing chain-link fencing and site furnishings at the west side of Building

11 may be removed as required to allow for boiler removal and delivery.

Fencing and site furnishings shall be reinstalled and restored to pre-work condition prior to completion of the Project.

b. The Schematic Design has also determined that access for removal and replacement of the Deaerator Tank shall be through the east exterior wall at the same level as the Deaeration Platform (approximately 12-feet above the boiler room floor level and 10-feet above grade) between existing columns/pilasters forming the bay containing the Deaeration Tank platform.

1) The DB offeror may access the east temporary opening from Parking Lot

“J,” located adjacent to and east of the Boiler Plant. Protection of the paving and existing stair enclosure, along with access to the doors and stairs into the Boiler Plant, will be required during work for removal and restoration of portions of the east exterior wall and replacement of the Deaeration Tank.

2021-06-30 Rev CIVIL DESIGN & LANDSCAPING NARRATIVE C-2

REPLACE BOILERS & PIPING - AVAHCS

4. Siting for a temporary boiler and related flatbed semi trailer against the east exterior wall of the Boiler Plan and provision of temporary fencing will be required by the DB offeror.

a. DB offeror is to provide constant monitoring and maintenance of temporary boilers – see FPEMT Narrative.

5. The DB offeror is to identify in their submittal areas required for lay-down, staging and storage of equipment and materials, and provide approved temporary fencing for enclosure and securing of the area(s).

6. Existing grades, paving, walks, manholes, curbs and gutters are to be protected with approved earthen cover to a compaction and depth sufficient to accommodate wheeled and static loads of heavy equipment, loaded trailers and other equipment and traffic required for completion of the Project. Cover to be removed and site restored to pre-work condition prior to completion of the Project.

7. Additional site work will depend on staging and placement of temporary boiler equipment, construction materials, etc.

8. The DB offer is to identify physical security risk measures to be incorporated, with a

Physical Security Risk Mitigation Plan to be submitted to the VHA Oversight

Committee on Physical Security and Resiliency for review and concurrence.