This is a Mandatory Pre-Submittal Conference Questions and Answers document for the School Board of Polk County, Florida's Continuing Contract for Environmental, Commissioning, or 3rd Party Inspection Services. The document clarifies submission requirements and eligibility criteria for qualified firms seeking to provide environmental, commissioning, or third-party inspection services for the school board's projects. Attendance at the mandatory pre-submittal conference is required for all firms to be considered; firms must sign in by 9:00 a.m. on the specified date to receive credit. Submissions may cover multiple service areas (environmental, commissioning, or third-party inspection), and firms selected will be offered individual contracts for each service area for which they qualify. The contract scope is structured as three separate continuing contracts, with inspections currently limited to new construction projects, though the board anticipates potential expansion to existing building inspections in the future. Page count limits apply to all submissions, including tabs and subcontractor information, and firms must provide only Polk County School Board-specific work experience.
Key submission details include that SF330 forms are not required for the application process. Firms submitting for multiple service types will receive separate contracts if selected rather than one combined contract. Subcontractors cannot submit separate packets and must be represented by the prime contractor who attended the mandatory conference; any subcontractor involvement must be included within the prime contractor's page count. Sign-in sheets will be posted to the VendorLink vendor portal following the conference. Applicants must include proof of Professional Liability Insurance and resumes demonstrating qualifications and past experience as part of the initial screening criteria. Firms whose signatures do not appear on the mandatory pre-submittal conference sign-in sheet will not receive consideration regardless of submission completeness.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mandatory Pre-Submittal Conference – Architectural Services Code Compliance Continuing Contracts for Environmental, Commissioning or 3rd Party Inspectors
Facilities Conference Room 12-119 Meeting Questions and Answers
9 am meeting questions:
Q: Are tabs included in the page count?
A: Tabs are included in the page count
Q: If submitting for two separate contracts do we need to submit two separate packets?
A: No, if packets are exactly the same content, notify us on the front page what contracts you are submitting for. If content is different relating to the contract you are submitting submit two separate packets.
Q: Are subcontracting companies included in the page count?
A: Yes, subcontractors are included in the page count.
Q: Are we to include all our current volume of work or only the school board's volume of work?
A: Polk County School Board volume of work included only.
Q: If our company also offers building envelope commissioning are we to include that as well or only MEP?
A: If you have a building envelope services include it, if we expand our needs it will already be included in this contract.
Q: If our company submits for multiple services will it be one contract or multiple contracts?
A: This is for three different contracts, you would be offered a contract for service if selected.
Q: If selected would it be for individual inspections or for the entire contract?
A: Inspections will be for the entire construction contract.
Q: Will sign in sheets be posted to vendor link?
A: Yes, Sign in sheets will be posted to vendor link.
Q: Are inspections for existing projects and buildings or only for new projects.
A: Inspections are currently for new projects. However, existing building inspections may be needed in the future.
10 am meeting:
Q: Can our subcontractor submit a separate packet for their field?
A: They would have needed to attend the mandatory meeting, to represent their company. Any subcontractors cannot be represented with their own packet.
Q: Is the SF330 required?
A: No SF330 is not required for this submission process.