KUA_43747225801_PH_I_LAP_UWS..doc

DOC document 50 KB Posted

Attached to
Connect Kissimmee Complete Streets Phase 1 - Professional Services for Construction Engineering & Inspection (CEI)
Solicitation number
RFQ2026013
Issued by
Polk County, Lake Harbor CDP, Florida

About this file

This is a Utility Work Schedule document executed between the City of Kissimmee and the Kissimmee Utility Authority (KUA) pursuant to Section 337.403 of the Florida Statutes, establishing the framework for utility relocation and adjustment activities required for the Connect Kissimmee Complete Streets Phase 1 project. The project involves work along Emmett Street, Broadway, and Main Street in Osceola County, Florida, with KUA serving as the Utility Agency/Owner responsible for coordinating underground electric and fiber optic infrastructure modifications. The utility work schedule specifies four primary work activities: assistance with lowering 6-foot and 4-inch HDPE conduits at multiple stations and locating and protecting a 4-inch HDPE fiber optic conduit. The schedule allocates eighteen days during city project construction, with individual activities requiring between 0.5 and 15 consecutive calendar days. The project is based on City LAP plans dated December 8, 2023, with Financial Project ID 437472-2-58-01 (Phase I) and FAP Number D521 065 B. Key project representatives include Luis Garcia and Logan Murphy for KUA, Michael S. Phillips, P.E., as the AECOM Deputy Consultant Project Manager serving as Engineer of Record, and Ramy Kamal as Project Manager for the City of Kissimmee.

Special conditions outlined by KUA include provisions requiring contractors to execute Line Extension Contracts and pay Contribution in Aid Construction fees prior to installation of new transformers, with material procurement potentially requiring up to fifty-two weeks and mobilization up to twenty-one days. Utility conduit inspections are required for new installations with scheduling through KUA's website portal. Contractors must provide KUA with twenty-one days' notice prior to the start of work to allow for valid utility locates, and any unplanned relocations not specified in the schedule will require an additional sixty days for KUA evaluation, design, and execution. The City of Kissimmee assumes full responsibility for installing new four-inch conduits per KUA specifications, passing inspection, and bearing one hundred percent of costs associated with relocation of the buried fiber optic cable on Darlington Avenue. At the roundabout location, significant changes to major feeder and fiber connections may require extension work with up to twelve weeks for completion and potential seasonal outage dependencies during non-summer months.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C Page 1 of 3 UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and CITY agree to the UAO’s need for relocation or adjustment to its utilities and CITY’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on CITY plans dated in the project information box below. Any deviation by CITY or its contractor from these plans, may void this utility work schedule. Upon notification by CITY of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify CITY and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

CITY PROJECT INFORMATION

Financial Project ID: 437472-2-58-01 (PH I)
Federal Project ID: N/A
State Road Number: EMMETT/BROADWAY/MAIN ST
County: OSCEOLA
CITY LAP Plans Dated: 12/08/2023
FAP No.: D521 065 B

UTILITY AGENCY/OWNER (UAO)

Utility Company: Kissimmee Utility Authority

UAO Project Rep: Luis Garcia
Phone: 321-624-1248
E-mail: lgarcia@kua.com
UAO Field Rep: Logan Murphy
Phone: 321-624-1388
E-mail: lmurphy@kua.com

UTILITY SIGNATURE

I have reviewed the CITY plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date / / Name Title

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the CITY plans referenced above.

EOR. Date / / Name Michael S. Phillips, P.E.

Title AECOM Deputy Consultant Project Manager

APPROVAL BY CITY

This utility work schedule is complete and acceptable to CITY.

CITY Rep. Date / / Name Ramy Kamal Title Project Manager, City of Kissimmee

SECTION A: SUMMARY OF UTILITY WORK

Days during CITY project construction: 18 Days prior to CITY project construction:

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the CITY project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

A) At the roundabout, any significant changes to the exhibit 4” HDPE and 6” HDPE conduits, may require extension work on KUA’s end if relocation if required, since these conduits are mayor feeder and fiber connections to the Downton area. Such relocate work if damage or required could take up to 12 weeks to complete, and may be seasonably dependent for an outage. (May occur during non-summer months).

B) All facilities associated with the color changing up lights and DMX controller such as conduits, pull boxes, wiring, up light, control boxes, fiber, etc. are owned by the City of Kissimmee and are theirs to maintain; as well as, theirs to relocate as called forth on the plans.

C) Coordinate with KUA Engineering for new transformers and new meter request. Contractors must execute a Line Extension Contract and pay the contribution. In Aid Construction (CAIC) fees prior to KUA installing new transformers. Material procurement mas take up to 52 weeks after contract is execute. Once all is on hand, KUA may require up to 21 days to mobilize.

D) Conduits inspection are require for new installations. Visithttps://kua.com/builders-contractors-assistance-and-engineering-forms/appointment-request-form/ to schedule.

E) Should any unknown condition required unplanned relocation not specific in this Utility Work Schedule KUA will require an additional 60 days evaluated, design, prepare and execute the relocation.

F) Request to cover distribution wires or hold poles require 14 days to mobilize and subject to KUA availability.

G) KUA will not perform any URD work without valid location, contractor must notify KUA at least 21 days prior to expected start of KUA work so that valid locates can be obtained.

H) Where the contractor and KUA need to coordinate activities at specific work location, the contractor shall conduct an On-Site meeting with KUA to discuss safety, timing and relevant means and method.

I) In case relocation is needed, City of Kissimmee will be responsible for installing the new 4” conduit according to KUA's specifications and passing inspection. They will also be responsible for 100% of the costs associated with the relocating project of the BFO located on Darlington Ave. This work will not affect KUA's operations. KUA will not remove any fiber optic cable until required by the City of Kissimmee.

Rule 14-46.001 F.A.C

UTILITY WORK SCHEDULE

December 14, 2016 Financial Project ID: Utility Company: CITY Plans Dated:

437472-2-58-01 (PH-1)

Kissimmee Utility Authority 12/08/2023

SECTION C: UAO’s WORK ACTIVITIES

Act. No.

Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset

Utility Work Activity Description

Dependent Activity

TCP Phase Consecutive Calendar Days Prior to During Const. Const.

1
UG electric 6' and 4" HDPE conduit
36+22
63 RT
Assist if needed to be lowered
Other - Describe under comments
1

0.5*

2
UG electric 6' and 4" HDPE conduit
36+36
82 RT
Assist if needed to be lowered
Other - Describe under comments
1

0.5*

3
UG electric 6' and 4" HDPE conduit
36+76
85 RT
Assist if needed to be lowered
Other - Describe under comments
1

0.5*

4
UG fiber optic 4" HDPE conduit
40+21
81.7 LT
Locate and protect
Other - Describe under comments (I)
1

* TIMES ALLOCATED TO ASSIST IN PROTECT THE FACILITIES THAT ARE IN PLACE