This is a signed agreement document for UWS Uniti Fiber LLC related to the Connect Kissimmee Complete Streets Phase 1 project in Kissimmee, Florida. The document pertains to professional services for Construction Engineering and Inspection (CEI) along Emmett Street and Broadway, extending from Orlando Avenue to Neptune Road. The City of Kissimmee issued a Request for Qualifications seeking one FDOT pre-qualified consulting firm to provide comprehensive construction engineering and inspection services under work type 10.0, in accordance with Florida Administrative Code Rule Chapter 14-75. Proposers were required to notify the Procurement Services Representative in writing within ten calendar days prior to the proposal closing date if any language, requirements, or combinations thereof were deemed to restrict or limit completion or appeared to limit the solicitation to a single source.
The signed document confirms UWS Uniti Fiber LLC's engagement as the selected consultant for CEI services on this project. The agreement is dated May 27, 2026, indicating the contract award and execution. Detailed scope of services, project information, deliverables, and applicable requirements are referenced in Exhibit A of the solicitation documents. No specific pricing, contract term, renewal options, or funding source information is visible in this signature page, though such details would typically be contained in the complete contract documents and exhibits accompanying this execution.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rule 14-46.001 F.A.C
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Sensitivity: Internal
Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.
FDOT PROJECT INFORMATION
Financial Project ID: 437472-2-58-01(PH I) Federal Project ID: N/A State Road Number: Broadway Ave from Orlando to Neptune County: Osceola FDOT Plans Dated: 4/25/2026 District Document No.: D521 065 B
UTILITY AGENCY/OWNER (UAO)
Utility Company: Uniti Fiber UAO Project Rep: James Mosley Phone: 251-654-8216 E-mail: James.Mosley@uniti.com UAO Field Rep: James Mosley Phone: 251-654-8216 E-mail: James.Mosley@uniti.com
UTILITY SIGNATURE
I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.
UAO Rep. Date 5 / 28 / 2026 Name James Mosley Title Construction Manager
ENGINEER OF RECORD SIGNATURE
I attest this utility work schedule is compatible with the FDOT plans referenced above.
EOR. Date / / Name Michael S. Phillips , PE Title Engineer of Record
APPROVAL BY DISTRICT UTILITIES
This utility work schedule is complete and acceptable to FDOT.
FDOT Rep. Date / / Name Victor M. Mercado Vazques, PE Title City of Kissimmee Project Manager
SECTION A: SUMMARY OF UTILITY WORK
The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.
Days prior to FDOT project construction: 60 Days during FDOT project construction: 3
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 437472-2-58-01(PH I) Utility Company: Uniti Fiber FDOT Plans Dated: 4/25/2026
SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS
1) Uniti Requests to be notified 3 days prior to start of construction and when work is being performed within 2’ of Uniti Facilities.
2) A Uniti Representative is to be on-site when work is being performed within 2’ of Uniti Facilities.
Protect: Shall include, but not be limited to, permittee’s use of an onsite representative during active construction operations. During Excavation Operations, Representative may be required to physically expose underground facilities, provide any necessary support to the facilities, and/or cover aerial facilities as deemed necessary to aid construction.
Locate: The use of sonde equipment to designate a accurate facility’s path thus exposing the underground facility and allowing the precise measurements of the depth and horizontal position to be made.
Uniti Fiber Contacts Tampa FL:
James Mosley 251-654-8216 James.Mosley@uniti.com
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 437472-2-58-01(PH I) Utility Company: Uniti Fiber FDOT Plans Dated: 4/25/2026
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
1. Engineering & Permitting 30
2. Materials Procurement Completion of Engineering & Permitting 30
3. (1) HANDHOLE 53+47
3’ LT “ To Be Removed Act. No 4 I 0 1
4. (1) HANDHOLE 53+47
6’ LT “ To Be Placed Median Construction I 0 2