This is a Florida Department of Transportation (FDOT) Utility Work Schedule document establishing the timeline and conditions for Comcast Communications, LLC to relocate and adjust its utility facilities in conjunction with the Connect Kissimmee Complete Streets Phase 1 project. The project involves work along Broadway Avenue from Orlando to Neptune in Osceola County, based on FDOT plans dated April 25, 2026. Comcast is required to complete utility work activities during the FDOT project construction phase, with a total of 10 consecutive calendar days allocated for the relocation of existing underground Comcast facilities (from Station 33+80 to Station 31+55) and the installation of proposed underground facilities behind the proposed sidewalk. The UAO (Utility Agency/Owner) Project Representative is Jason Palmer (Construction Specialist, 305-309-1601), and the Field Representative is Sean Williams (813-992-5152). The Engineer of Record is Michael S. Phillips, PE, and FDOT district approval is managed by Victor M. Mercado Vazques, PE (City of Kissimmee Project Manager).
Comcast must comply with the 2017 Utility Accommodation Manual and Rule Chapter 14-46.001 F.A.C. All work must be performed during Comcast's normal daytime hours of 8:00 AM to 4:00 PM Monday through Friday, with any outside-hours work requiring 14 days' advance notice. Comcast representatives must provide 72 hours' advance notice prior to construction and must be present when work occurs within two feet of buried fiber lines. Sunshine State One Call, Inc. must be contacted at least 48 hours prior to construction (1-800-432-4770). Comcast representatives will present means and methods at a preconstruction meeting. The utility work schedule is contingent upon the proposed sidewalk being staked and is dependent on no deviations from the referenced FDOT plans; any plan changes may require renegotiation of the schedule.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rule 14-46.001 F.A.C
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.
FDOT PROJECT INFORMATION
Financial Project ID: 5 Federal Project ID: N/A State Road Number: Broadway Ave from Orlando to Neptune County: Osceola FDOT Plans Dated: 4/25/2026 District Document No.: D521 065 B
UTILITY AGENCY/OWNER (UAO)
Utility Company: Comcast Communications. LLC UAO Project Rep: Jason Palmer Phone: 305-309-1601 E-mail:
UAO Field Rep: Sean Williams Phone: 813-992-5152 E-mail: swilliams@truenetcommunications.com
UTILITY SIGNATURE
I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.
UAO Rep. Date 5 / 14 / 2026 Name Jason Palmer Title Construction Specialist
ENGINEER OF RECORD SIGNATURE
I attest this utility work schedule is compatible with the FDOT plans referenced above.
EOR. Date / / Name Michael S. Phillips , PE Title Engineer of Record
APPROVAL BY DISTRICT UTILITIES
This utility work schedule is complete and acceptable to FDOT.
FDOT Rep. Date / / Name Victor M. Mercado Vazques, PE Title City of Kissimmee Project Manager
SECTION A: SUMMARY OF UTILITY WORK
The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.
Days prior to FDOT project construction: 0 Days during FDOT project construction: 10
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 5 Utility Company: Comcast Communications. LLC FDOT Plans Dated: 4/25/2026
SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS
1. Please contact Comcast Construction Specialist Jason Palmer at least 72 hours prior to construction.
2. Comcast requests a copy of the FDOT Contractor’s construction schedule upon approval.
3. Comcast has facilities in the area of your proposed construction that do not appear to be in conflict. Please maintain caution when working near our facilities. If facilities are damaged, please call Jason Palmer @ 305-319-1601 immediately.
4. All Comcast work is to be performed during Comcast normal daytime working hours of 8:00AM to 4:00PM Monday through Friday. Any work requested outside these hours by the FDOT, their consultant or roadway contractor must be requested 14 days in advance.
5. Comcast will discuss at the preconstruction meeting the means and methods they will use near tasks shown in Section C.
time is inlcluded in the work schedule to perform work with the contractor for these tasks.
Please contact Sunshine State One Call, Inc. at least 48 hours prior to construction service by calling toll free 1-800-432-4770 Comcast representatives must be present when construction is being done within 2 feet of the buried fiber lines. Please provide 72 hour advance notice of such construction
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 5 Utility Company: Comcast Communications. LLC FDOT Plans Dated: 4/25/2026
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
1 Existing Underground Comcast Facilities
33+80
44’ LT
31+55 27’ LT To Be Removed None N/A 0 5
2 Proposed Underground Comcast Facilities
33+80
44’ LT
31+55
27’ LT
To Be Installed Behind Proposed
Sidewalk
Proposed Sidewalk Staked N/A 0 5