IDIQ PWS Attch 3 Midwest Del Rev Process BECOS vf2.docx

DOCX document 42 KB Posted

Attached to
BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Midwest Region
Solicitation number
FA890320R0015
Issued by

About this file

This document outlines a deliverable review process for a federal contract. It details the review tasks, timeframes, and scope for contractors and regulators to follow for draft and final documents related to the contract. Key steps include contractors preparing working copies for review within dependent timeframes, regulators providing comments within 30 calendar days, contractors incorporating comments and preparing submittal letters, and regulators signing off on drafts within 7 calendar days or requesting further revisions. Final documents then go through regulatory acceptance, with timeframes varying according to involved agreements. The process aims to meet predetermined objectives and regulatory concurrence.

The related federal contract opportunity is a solicitation from the Air Force Materiel Command for Base Realignment and Closure Environmental Construction and Optimization Services in the Midwest Region. Additional details are provided in attachments to the solicitation.

View the file

Other files

File Type Posted
05182020_Amendment 02_Question_Website Response 20R0015 Midwest.xlsx XLSX spreadsheet
20200518_TO2 PWS Attch1 Midwest Base Site List BECOS_Amendment_02.xlsx XLSX spreadsheet
05182020_Amendment 02_Additional Question and Response 20R0015 Midwest.xlsx XLSX spreadsheet
20200518_Midwest TO2 Price Model_Amendment_02.xlsx XLSX spreadsheet
Solicitation Amendment FA890320R00150002 SF 30 (2).pdf PDF
TO 2 PWS Attch 1 Midwest Base Site List BECOS_Amendment_01.xlsx XLSX spreadsheet
Solicitation Amendment FA890320R00150001 SF 30.pdf PDF
20-R-0015 Midwest RFP QAs 2 of 2.xlsx XLSX spreadsheet
20200501_FA890320R0015_BECOS_Midwest_Section_M_Amendment_01.docx DOCX document
20200501_Midwest TO2 Price Model_Amendment_01.xlsx XLSX spreadsheet
20200501_FA890320R0015_BECOS_Midwest_Section_L_Amendment_01.docx DOCX document
IDIQ PWS Attch 1 Midwest Base Site List BECOS_Amendment_01.xlsx XLSX spreadsheet
FA890320R0015 Midwest Amendment Changes.docx DOCX document
20-R-0015 Midwest RFP QAs 1 of 2.xlsx XLSX spreadsheet
MO20190038 8Nov2019 Cass Building.pdf PDF
20200122_Midwest FFP FBLR Tables.xlsx XLSX spreadsheet
TO 2 PWS Attch 2 KI Sawyer Base Spec Req Midwest BECOS vf2.docx DOCX document
20200109_Midwest TO2 Price Model.xlsx XLSX spreadsheet
IDIQ PWS Midwest BECOS vf4.docx DOCX document
OH20190001 25Oct2019 Statewide Heavy.pdf PDF
TO 2 PWS Attch 2 Grissom Base Specific Req Midwest BECOS vf2.docx DOCX document
20200131_FA8903-20-R-0015_BECOS RFP Questions and Answers Template v2.xlsx XLSX spreadsheet
IL20190015 6Dec2019 Champaign Heavy.pdf PDF
IDIQ PWS Attch 2 Midwest Acr and Def BECOS vf3.docx DOCX document
MI20190042 27Sep2019 Heavy Iosco.pdf PDF
OH20190093 25Oct2019 Montgomery Building.pdf PDF
IL20190009 6Dec2019 Cook Building Heavy.pdf PDF
OH20190086 22Nov2019 Licking Building.pdf PDF
TO 2 PWS Attch 2 Gentile Base Spec Req Midwest BECOS vf2.docx DOCX document
IDIQ PWS Attch 4 Midwest Perf Obj Def and Req BECOS vf2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A014 (DRPR) Midwest BECOS vf1.pdf PDF
WI20190001 13Dec2019 Milwaukee Building.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT B002-B003 (MGMT) Midwest BECOS vf1.pdf PDF
TO 2 PWS Attch 2 General Mitchell Base Spec Req Midwest BECOS vf2.docx DOCX document
TO 2 PWS Attch 1 Midwest Base Site List BECOS vf9.xlsx XLSX spreadsheet
TO 2 PWS Attch 2 Richards-Gebaur Base Spec Req Midwest BECOS vf3.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A010 (QCIC) Midwest BECOS vf1.pdf PDF
IN20190006 1Nov2019 Cass Heavy.pdf PDF
TO 2 PWS Attch 2 Chanute Base Spec Req Midwest BECOS vf2.docx DOCX document
Midwest IDIQ_Sched B_CLIN Structure and Price Model_v1_02032020.xlsx XLSX spreadsheet
TO 2 PWS Midwest BECOS vf3.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT B004 (CMAN) Midwest BECOS vf1.pdf PDF
TO 1 PWS MidWest BECOS vf3.docx DOCX document
TO 1 CDRLs Exhibit A B Midwest BECOS vf1.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A003-A012 (MGMT) Midwest BECOS vf1.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT C001 (MGMT) Midwest BECOS vf1.pdf PDF
IDIQ PWS Attch 1 Midwest Base Site List BECOS vf6.xlsx XLSX spreadsheet
20201217_Compensation Plan Model.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT A001-A002-A004 (MISC) Midwest BECOS vf1.pdf PDF
MO20190001 8Nov2019 Statewide Missouri.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8903-20-R-0015

Midwest Region Attachment 3 5 December 2019

Deliverable Review Process Air Force Contractor Regulators Task: Prepare working copy document.

Timeframe: Dependent on task Scope: Dependent on task Task: Review working copy document.

Timeframe: 30 calendar days (max) Scope: Comments will focus on regulatory, factual, technical, and legal issues and should not conflict with the terms and conditions of the contract (e.g., directing the contractor on approach).

Tasks: Incorporate review comments. Prepare submittal letter.

Timeframe: Dependent on task Scope: Evaluate and incorporate all regulatory, factual, technical, and legal Air Force comments that do not conflict with the terms and conditions of the contract.

Task: Review draft document and sign submittal letter if document is acceptable. Return for further revisions if required.

Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.

Task: Obtain regulatory review of draft document.

Timeframe: TBD Scope: Distribute submittal letter and document to regulators. Provide copies to the Air Force.

Task: Provide regulatory review.

Timeframe: FFA/DSMOA/Circumstantial Scope: Provide regulatory review of submitted document.

Tasks: Resolve comments and revise document. Prepare submittal letter.

Timeframe: TBD Scope: Provide timely evaluation and resolution of regulatory comments with a goal of meeting predetermined objectives.

Task: Submit final document.

Timeframe: TBD Scope: Submit final document for regulatory acceptance/concurrence.

Task: Review final document and sign submittal letter if document is acceptable. Return for further revisions if required.

Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.

Task: Accept final document.

Timeframe: FFA/DSMOA/Circumstantial Scope: Accept final document and provide written notice.

Note: This is a generic document review process for this contract. Actual review times will be based on the Federal Facility Agreement (FFA) where applicable or the Joint Execution Plan (JEP) and associated schedules developed under the Defense State Memorandum of Agreement (DSMOA). Agencies reviewing the document may make specific requests based on complexity of the deliverable or work load of their technical review team that impact review timelines. Depending on the document, there may or may not be a draft version or there may be multiple draft versions.

File details come from the government source that posted it. Updated .