About this file

This document outlines requirements for environmental remediation and monitoring services at the former Grissom Air Force Base in Indiana under Solicitation Number FA890320R0015 for Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) in the Midwest Region. Key activities include monthly contractor-hosted teleconferences and three annual onsite BCT meetings. Annual Restoration Advisory Board meetings are held in August along with inspections of land use controls and five-year reviews of sites. The contractor will also support computer-aided design and geographic information system updates. Remediation is ongoing at several sites including landfills, fire training areas, and hangars, with monitoring of groundwater and vadose zone soils.

View the file

Other files for this federal contract opportunity

Other files attached to BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Midwest Region, newest first.
File Type Posted
Solicitation Amendment FA890320R00150002 SF 30 (2).pdf PDF
05182020_Amendment 02_Question_Website Response 20R0015 Midwest.xlsx XLSX spreadsheet
20200501_FA890320R0015_BECOS_Midwest_Section_M_Amendment_01.docx DOCX document
20200501_Midwest TO2 Price Model_Amendment_01.xlsx XLSX spreadsheet
TO 2 PWS Attch 1 Midwest Base Site List BECOS_Amendment_01.xlsx XLSX spreadsheet
IDIQ PWS Attch 1 Midwest Base Site List BECOS_Amendment_01.xlsx XLSX spreadsheet
20-R-0015 Midwest RFP QAs 1 of 2.xlsx XLSX spreadsheet
FA890320R0015 Midwest Amendment Changes.docx DOCX document
20200501_FA890320R0015_BECOS_Midwest_Section_L_Amendment_01.docx DOCX document
20200203_FA890320R0015_Midwest_BECOS_Section_M v4.docx DOCX document
OH20190001 25Oct2019 Statewide Heavy.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A007-A008-A009 (ENVR) Midwest BECOS vf1.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A014 (DRPR) Midwest BECOS vf1.pdf PDF
TO 2 PWS Midwest BECOS vf3.docx DOCX document
TO 2 PWS Attch 2 Newark Base Spec Req Midwest BECOS vf2.docx DOCX document
OH20190096 22Nov2019 Pickaway Building.pdf PDF
20201217_Compensation Plan Model.xlsx XLSX spreadsheet
MI20190048 1Nov2019 Marquette Heavy.pdf PDF
MO20190001 8Nov2019 Statewide Missouri.pdf PDF
TO 2 PWS Attch 1 Midwest Base Site List BECOS vf9.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT A001-A002-A004 (MISC) Midwest BECOS vf1.pdf PDF
MI20190135 1Nov2019 Marquette Building.pdf PDF
MO20190038 8Nov2019 Cass Building.pdf PDF
TO 2 PWS Attch 2 OHare Base Spec Req Midwest BECOS vf2.docx DOCX document
OH20190078 22Nov2019 Franklin Building.pdf PDF
WI20190015 13Dec2019 Statewide Heavy.pdf PDF
20200131_FA890320R0015_BECOS_Relevancy_PPQ v2.docx DOCX document
Solicitation FA890320R0015 Midwest.pdf PDF
20200122_Midwest FFP FBLR Tables.xlsx XLSX spreadsheet
TO 2 PWS Attch 2 Rickenbacker Base Spec Req Midwest BECOS vf2.docx DOCX document
IN20190002 1Nov2019 Cass Building.pdf PDF
TO 2 PWS Attch 2 KI Sawyer Base Spec Req Midwest BECOS vf2.docx DOCX document
MI20190126 25Oct2019 Building Iosco.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT B001 (MISC) Midwest BECOS vf1.pdf PDF
TO 2 CDRLs Exhibit A B Midwest BECOS vf1.docx DOCX document
IDIQ PWS Attch 2 Midwest Acr and Def BECOS vf3.docx DOCX document
20200131_FA8903-20-R-0015_BECOS RFP Questions and Answers Template v2.xlsx XLSX spreadsheet
IL20190015 6Dec2019 Champaign Heavy.pdf PDF
20200109_Midwest TO2 Price Model.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT A005-A006-A011 (CMAN) Midwest BECOS vf1.pdf PDF
IDIQ PWS Attch 4 Midwest Perf Obj Def and Req BECOS vf2.docx DOCX document
TO 1 CDRLs Exhibit A B Midwest BECOS vf1.docx DOCX document
OH20190093 25Oct2019 Montgomery Building.pdf PDF
IDIQ PWS Attch 3 Midwest Del Rev Process BECOS vf2.docx DOCX document
TO 2 PWS Attch 2 General Mitchell Base Spec Req Midwest BECOS vf2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT B002-B003 (MGMT) Midwest BECOS vf1.pdf PDF
IL20190002 6Dec2019 Champaign Building.pdf PDF
MI20190042 27Sep2019 Heavy Iosco.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A003-A012 (MGMT) Midwest BECOS vf1.pdf PDF
MI20190116 1Nov2019 Delta Building.pdf PDF
Show all 50

BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Midwest Region has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

FA8903-20-R-0015

Attachment 2 Midwest Region - Grissom 5 December 2019

1.1 Scope

Former Grissom AFB is located approximately 15 miles north of Kokomo in Cass County, Indiana and was established in July 1942 by the United States Navy as Naval Air Station (NAS) Bunker Hill. NAS Bunker Hill was closed at the end of World War II and the U.S. Air Force (USAF) obtained right of entry to 25 buildings in November 1951, reactivating Bunker Hill as an Air Force Base in 1954. The installation was renamed in 1968 to Grissom AFB and the Air Force Reserve began using the base in the early 1970s. In 1984, the USAF initiated the Installation Restoration Program (IRP) to identify and evaluate environmental issues associated with past waste, disposal practices and spills. The former Grissom AFB is a non-National Priorities List installation and IRP activities are not currently under a Federal Facility Agreement or Interagency Agreement with the lead regulatory agency, the Indiana Department of Environmental Management (IDEM), or United States Environmental Protection Agency (USEPA).

In 1993, the BRAC Commission directed realignment of Grissom AFB to the Air Force Reserve (ARB) and on 1 October 1994 Grissom AFB ceased all active-duty operations. In 2008, Grissom ARB entered into a joint-use agreement with Miami County Economic Development Authority to have Montgomery Aviation managing day-to day civil operations. The Air Reserve Base occupies 1,233 acres of the former installation with the remaining 1,489 acres being maintained by private entities, the State of Indiana, or by the Miami County Economic Development Authority. Currently, IDEM is the regulatory authority, and USEPA is not involved in the environmental program.

In addition to the requirements presented in this PWS, this scope includes the following:

· No base-specific requirements in addition to those in the PWS.

Contractors are not responsible for the following:

· Investigation and remediation of PFAS, except as noted in Attachment 1.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1.
Final Annual 2017 Groundwater Monitoring Report for Installation Restoration Program Site SS190
AR # 579007
September 2018
2.
Final Third Five-Year Review Report
AR # 592125
June 2018
3.
Final Land Use Controls Inspection Report
AR # TBD
April 2018
4.
Draft Groundwater Investigation and Work Plan Memorandum for Installation of Additional Groundwater Monitoring Wells at Installation Restoration Program Site SS053
AR # 557111
August 2017
5.
Final Addendum to the Groundwater and Vadose Zone Soil Remediation Work Plan for Installation Restoration Program Site SS190
AR # 573440 & 557114
April 2017
6.
Final Groundwater Monitoring Report for Installation Restoration Program Sites SS035, SS053, and SS058
AR # 557415
February 2017
7.
Addendum to the Groundwater and Vadose Zone Soil Remediation Work Plan for Instalaltion Restoration Program Site SS190
AR#573440 and 557114
April 2017
8.
Final Annual 2016 Groundwater Monitoring Report for Installation Restoration Program Sites FT001 and FT002
AR # 557104
September 2016
9.
Final Quality Program Plan for the Data Gap Investigation at Sites SS035, SS053, and SS058, Former Grissom Air Force Base, Indiana
AR#581352
November 2018
10.
Final Quality Program Plan for the Interim Removal Action at Site SS190
AR#592292
June 2019
11.
Final Annual 2017 Groundwater Monitoring Report for Installation Restoration Program Sites FT001 and FT002
AR#592289
May 2018
12.
Memorandum for Changes to the November 2001 Decision Document for the Fire Protection Training Areas 1 and 2
AR # 381
July 2005
13.
Final Record of Decision for Area of Concern 53 at Hangar 200
AR # 367
October 2003
14.
Final Decision Document Fire Protection Training Areas 1 and 2
AR # 382
November 2001
15.
Final Decision Document for Landfill 2 (LF004)
AR # 359
May 2001
16.
Final Decision Document for Landfill 1 (LF003)
AR # 329
September 2000

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

Region 5 Bases PBR
FA8903-09-D-8565
9/24/2020
9/24/2020

2.6.1 Meeting/Teleconference Support

· Grissom BCT meetings are generally held monthly via PBR contractor-hosted teleconference calls. In addition, onsite BCT meetings are held on an as-needed basis approximately three times per year and are typically scheduled to occur the same week as other Air Force meetings (e.g., RAB meetings, public meetings, stakeholder meetings). Onsite meetings are typically held at the former base in the Grissom Reserves offices.

2.6.2 Public Meetings and Hearings

· Grissom RAB meetings are held on annually; typically, in August and is held along with the Grissom Reserves RAB. Grissom Reserves host the RAB in their offices and conduct public notices and logistics. The PBR contractor is responsible for preparing and presenting the Air Force BRAC portion of the RAB.

2.6.5 Site Access: Permits, Easements, and Work Site Access

· No base-specific requirements in addition to those in the PWS.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No base-specific requirements in addition to those in the PWS.

6.14 Land Use Controls (LUC)

· Annual LUC inspections are required.

6.15 Five-Year Reviews

· The third Five-Year Review was completed late, in June 2018, under the current PBR. The fourth Five-Year Review, due September 2020, will be delayed, and is included in this PBR TO. The subsequent Five-Year Reviews in 2025 and 2030 are also included in this PBR TO.