Fort Hamilton Bldg 125-100_PCNT_Specification_07-31-2023.pdf

PDF 12 MB Posted

Attached to
Renovate Bldg. 125 Fort Hamilton, Brooklyn, New York
Solicitation number
W912DS23B0022
Issued by

About this file

This file contains specifications for the renovation of Building 125 at Fort Hamilton in Brooklyn, New York. The related federal contract opportunity is solicitation number W912DS23B0022 issued by the Department of the Army Corps of Engineers Engineering District New York to renovate Building 125 at Fort Hamilton. The specifications require renovations to electrical, HVAC, plumbing and fire protection systems as well as interior renovations including finishes, fixtures and equipment. The response due date for proposals was July 31, 2023, with award of the contract expected in September 2023. The contract will have a one year period of performance.

View the file

Other files

File Type Posted
C.04.01 Bid Abstract Bldg 125 Final.pdf PDF
A-605 and S-102 S-103 Amd 5.pdf PDF
B.08.03 Amendment 05.pdf PDF
09 06 00 Amd 5.pdf PDF
10 21 13 Amd 5.pdf PDF
E-002 and ED102 Amd 3.pdf PDF
LEED_v4_for_Interior_Design_and_Construction_Checklist B125 Reno Ft Hamilton.pdf PDF
Army_SustainabilityReportCard_2020 B125 Renovation LEED IDC.pdf PDF
Fort Hamilton Planning Charrete.pdf PDF
M-101 thru 107 (rev 02) and 602 (rev 01) Amd 5.pdf PDF
07 27 10 Amd 5.pdf PDF
12 50 00.13 FFE Data Sheet Item Code M4 revised.pdf PDF
01 33 29 Amd 5.pdf PDF
B.08.03 Amendment 04.pdf PDF
B.08.03 Amendment 03.pdf PDF
A-405 20230830.pdf PDF
A-408 20230830.pdf PDF
A-501 20230831.pdf PDF
1AB-101 20230830.pdf PDF
A-605 20230831.pdf PDF
A-101 A-403 A-501 AD-101 AD-403 20230829.pdf PDF
Renovation BLDG 125-Mechanical Room - Sheet - M-111 - MECHANICAL ROOM PLAN.pdf PDF
B.08.03 Amendment 02.pdf PDF
A-602 Amendment 2 20230823.pdf PDF
Amendment 2 Mechanical Drawings M102 thru 107 M601 M701.pdf PDF
A-404 Amendment 2 20230824.pdf PDF
A-601 Amendment 2 20230823.pdf PDF
B.08.03 Amendment 01.pdf PDF
B.08.03 Site Visit Sign in sheet_16 Aug 23 (002).jpg JPG image
B.08.03 Invitation for Bid W912DS23B0022.pdf PDF
JA_Hamilton_125_Simplex Signed.pdf PDF
B.08.03 Invitation for Bid W912DS23B0022.pdf PDF
B125 RTA Complete set R4 07 August 2023.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bldg. 125 1st Marine Corps District Relocation to Ft. Hamilton Fort Hamilton, New York Project No. 103259

100% SPECIFICATIONS

July 31st, 2023

UNCLASSIFIED / FOUO

THIS PAGE INTENTIONALLY LEFT BLANK

Fort Hamilton Bldg 125 HAMILTONBLDG125 100% Specification

PROJECT TABLE OF CONTENTS

DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS

00 00 01 05/22 COVER SHEET

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/22, CHG 1: 02/23 WORK RESTRICTIONS

01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND

REPORTING

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 20.00 18 NY Dist. July 2018 TESTING FOR MECHANICAL AND ELECTRICAL

SYSTEMS

01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/18, CHG 1: 11/21 FACILITY DATA REQUIREMENTS

01 91 00.15 05/23 BUILDING COMMISSIONING

01 91 19 05/23 BUILDING ENCLOSURE COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 08/22 DEMOLITION

02 42 51 11/19 CARPET REMOVAL AND RECLAMATION

02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF

HAZARDOUS MATERIALS

02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION

02 83 00 11/18 LEAD REMEDIATION

02 85 00 11/18, CHG 1: 05/22 MOLD REMEDIATION

DI VI SI ON 03 - CONCRETE

03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE

DI VI SI ON 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DI VI SI ON 05 - METALS

05 51 00 02/17, CHG 1: 05/17 METAL STAIRS

05 51 33 02/16, CHG 2: 02/18 METAL LADDERS

05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS

PROJECT TABLE OF CONTENTS Page 1

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

06 20 00 08/16, CHG 2: 11/18 FINISH CARPENTRY

06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION

07 27 36 05/17, CHG 3: 02/23 SPRAY FOAM AIR BARRIERS

07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

08 51 13 05/19 ALUMINUM WINDOWS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL AND DOOR LOUVERS

DI VI SI ON 09 - FI NI SHES

09 06 00 08/22 SCHEDULES FOR FINISHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/20 ACOUSTICAL CEILINGS

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 68 00 11/17, CHG 2: 08/20 CARPETING

09 90 00 02/21 PAINTS AND COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

DI VI SI ON 12 - FURNI SHI NGS

12 24 13 08/20 ROLLER WINDOW SHADES

12 48 13 08/17 ENTRANCE FLOOR MATS AND FRAMES

12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION

12 59 00 08/17, CHG 1: 08/18 SYSTEMS FURNITURE

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 48 73 05/22 SEISMIC CONTROL FOR MISCELLANEOUS

EQUIPMENT

PROJECT TABLE OF CONTENTS Page 2

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

DI VI SI ON 22 - PLUMBI NG

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 11 20 05/20 FACILITY GAS PIPING

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 08/21 REFRIGERANT PIPING

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 52 00 04/08, CHG 5: 11/19 HEATING BOILERS

23 57 10.00 10 11/19 FORCED HOT WATER HEATING SYSTEMS USING

WATER AND STEAM HEAT EXCHANGERS

23 81 29 02/20 VARIABLE REFRIGERANT FLOW HVAC SYSTEMS

DI VI SI ON 25 - I NTEGRATED AUTOMATI ON

25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS-BUILDING AUTOMATION

25 05 11.02 11/17 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS – FIRE ALARM

25 05 11.03 11/17 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS – ELECTRONIC SECURITY

SYSTEMS

25 05 11.04 11/17 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS – POWER MONITORING

SYSTEM

25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM

TESTING

DI VI SI ON 26 - ELECTRI CAL

26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL

EQUIPMENT

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED

TRANSFORMERS

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

PROJECT TABLE OF CONTENTS Page 3

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 13.43 05/20 TELEVISION DISTRIBUTION SYSTEM

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DI VI SI ON 31 - EARTHWORK

31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 31 13 11/21 CHAIN LINK FENCES AND GATES

DI VI SI ON 33 - UTI LI TI ES

33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

PROCUREMENT AND

CONTRACTING

REQUIREMENTS

SECTION 00 00 01

COVER SHEET

05/22

PART 1 GENERAL

NEW YORK DI STRI CT

CORPS OF ENGI NEERS

NEW YORK, NEW YORK 10278- 0090

I NVI TATI ON FOR BI DS

FOR

Bl dg. 125 1st Mar i ne Cor ps Di st r i ct Rel ocat i on t o Ft . Hami l t on For t Hami l t on, New Yor k

PN 103259

1. Attached is INVITATION FOR BIDS (IFB) NO. W912DS-23-B-0022

2. BIDS MUST BE SET FORTH full, accurate, and complete information as required by this Invitation for Bids, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF BIDS: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS TO BIDDERS (Section 00 21 13).

4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation. (See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00 72 00 of this IFB).

5. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

6. GENERAL CONDITIONS - SECTION 00 72 00, note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause.

7. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to being affixed to the document after its generation, will not be accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.

8. Sections indicated in this Cover sheet are part of the Solicitation.

DOCUMENT 00 00 01 Page 1

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 01 Page 2

TECHNICAL

SPECIFICATIONS

SECTION 01 11 00

SUMMARY OF WORK

08/ 15, CHG 2: 08/ 21

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor must be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed (NTP), (ii) prosecute the work diligently, and (iii) complete the entire work ready for use, not later than 365 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion must include final cleanup of the premises. (FAR 52.212-3). Optional item must be excercised within 150 calendar days after the NTP.

b. The Contractor must furnish all labor, materials, equipment, and services for the following work covered under this contract.

c. All work must be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan ; G, RO

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

The work includes renovation of mixed use/warehouse space to hold the 1st Marine Corps District (1MCD) as their recruiting command center for all Marine Corps Recruiting Operations in the Northeast U.S. This includes demolition and replacement of partial HVAC system, plumbing, fire protection system, electrical, interior walls and incidental related work.

There will be an existing Logistics tenant in the back portion of the facility that will remain in their current location and all construction must account for construction to be done around continuing operations.

1.3.2 Location

The work is located at the Fort Hamilton, New York, approximately as indicated in the drawing plan. The exact location will be shown by the

SECTION 01 11 00 Page 1

Contracting Officer.

1.4 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $5,000,000 and $10,000,000.

1.5 OCCUPANCY OF PREMISES

Building(s) will be partially occupied during performance of work under this Contract. Occupancy notifications must be posted in a prominent location coordianted with the COR in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.6 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING

Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with other parties, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy must be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.

1.7 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

c. The responsibility for damage to the permanent work must be as set forth in the article of the contract clause entitled "PERMITS AND RESPONSIBILITIES". However, if in the judgment of the Contracting Officer, the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, severe coastal storm or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor must make the repairs as ordered by the Contracting Officer and full compensation for repairs will be made at the applicable Contract unit or lump-sum prices as fixed and established in the Contract. If, in the opinion of the Contracting Officer, there are no Contract unit or lump sum prices applicable to the work, an equitable adjustment, pursuant to Contract Clause entitled CHANGES, will be made as full compensation for the repairs of that part of the permanent work for which there are not applicable Contract unit or lump-sum prices. Except as herein provided, damage to all work, utilities, materials, equipment, and

SECTION 01 11 00 Page 2 plant, including temporary construction and utilities, pavements, and other property along the routes used by the Contractor's pipelines and/or land vehicles, must be repaired to the satisfaction of the Contracting Officer, the State of New York, and the utilities companies, at the Contractor's expense regardless of the cause of such damage.

1.8 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

Under the New York State Public Service Commission "Call Before you Dig" regulations, the Contractor must provide at least two calendar days' notice prior to begining mechanized work. The day of the call does not count toward the two calendar days requirements. The Contractor must budget extra time if the call is placed after a Holiday or other pandemic related events. The Contractor must refer to the following website for complete "Call Before you Dig" information. https://newyork-811.com/ and https://www.digsafelynewyork.com/

1.9 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the storage area directed by the COR.

Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

SECTION 01 11 00 Page 3

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 4

SECTION 01 14 00

WORK RESTRICTIONS

11/ 22, CHG 1: 02/ 23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel ; G, RO

Construction Plan ; G, RO

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. The part of the building will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity. Coordinate with COR for any interruption or disruption to the existing systems.

b. Contractor is required to submit a construction plan for the work required to be completed under this contract. This includes but not limited to disconection and operation of the mechancial, fire, communication and electrical system in the existing part of the building.

c. Permission to interrupt any Activity roads or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and

SECTION 01 14 00 Page 1 security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 Identification of Employees

The Contractor is responsible for providing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification must immediately be delivered to the Contracting Officer for cancellation upon the release of any employees. When required by the Contracting Officer, the Contractor must obtain and submit fingerprints of all persons employed or to be employed on the project.

1.4.1.3 Contractors Cops and MOBILISA Passes Forms

At the end of this section are the COPS Pass REQUEST and Statement of Responsibility for Contractors/Applicants forms to be completed by the Contractor and personnel for access into Fort Hamilton. Complete and submit these forms for approval no more than five calendar days after Notice to Proceed is issued. Fort Hamilton will not provide base access to the Contractor or subcontractors without successfully submitting and processing the attached forms.

1.4.1.4 Contractor Antiterrorism/Operations Security Review

The Contractor must complete "OPSEC" training within 30 calendar days of the start date. The attached AT-OPSEC Form ENG 6055 must be returned to OPSEC (kira.a.kazmi.civ@mail.mil (718)630-4814). Contractors will be provided with an "i watch" slide deck as a form of training. Complete and submit these forms for approval no more than five calendar days after Notice to Proceed is issued. Fort Hamilton will not provide base access to the Contractor or subcontractors without successfully submitting and processing the attached forms.

1.4.1.5 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 5 p.m., Monday through Friday, , excluding Government holidays. Scheduling of major demolition activities that are particularly noisy or involve excessive vibration must be

SECTION 01 14 00 Page 2 coordinated with the Contracting Officer 14 days in advanced.

1.4.3 Working Conditions

Comply with paragraph Fatigue Management Plan (FMP) of EM 385-1-1 .

(1) Open trenches or road restrictions will not be permitted without the approval of the Contracting Officer.

(2) Access ways must be fully usable.

(3) All cost for conformance with the above stated requirements must be included with the lump sum contract amount and no claim for extra cost must be considered.

1.4.4 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.4.5 Occupied Building

The Contractor shall be working in an existing building which is occupied.

Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains, and Government material located during the construction period.

1.4.6 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 4 hours. This time limit includes time for deactivation and reactivation.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal

SECTION 01 14 00 Page 3 conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.5 Contractor Vehicles

The local general, visitor, and government designated parking areas must not be used by the contractor. No general contractor or subcontractor employee parking is available near the immediate site. The contractor must identify and locate parking facilities for general and subcontractors.

Contractors and construction vehicles can only park in pre-approved designated staging areas or as identified in their contract. Parking is reserved for Staff and requires a special pass. In accordance with AR 190-5, persons who operate a motor vehicle on Fort Hamilton must be deemed to have given consent for the removal and temporary impoundment of the privately owned vehicle (POV) and construction equipment when it is:

a. Parked illegally

b. Interfering with operations

c. Creating a safety hazard

d. Left unattended in a restricted or controlled area

e. Parked in a reserved space authorized by the Installation Commander

The Contracting Officer Representative (COR) overseeing the contract will review and coordinate all contractor pass requests.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 4 iWATCH Army Training for Contractors “See Something -- Say Something”

Unclassified

Always Ready. Always Alert.

Because someone is depending on you.

Unclassified date

Always Ready. Always Alert.

Training Objective

2Unclassified date

• Contractors and all associated subcontractors performing work on Army contracts must receive this training on the local iWATCH Army program.

• The objective of this training is to inform employees of the types of suspicious activity or behavior to watch for and instruct employees to report suspicious activity or behavior to the Contract Officer Representative (COR), military police, or local law enforcement.

• Training should be completed within 30 calendar days of contract award and within 5 calendar days of new employees’ commencing performance on active contracts (in the case of personnel changes).

• The results of the training shall be reported to the COR.

Training Topics

3Unclassified date

• Origin of iWATCH Army

• iWATCH Army Public Service Announcement (PSA)

• Indicators of Suspicious Activity or Behavior

• “See Something Say Something”

• What to Report

• How to Report

• Source for Other Important Information

• Local Point of Contact

Origin of iWATCH Army

4Unclassified date

Origin: Headquarters, Department of the Army, ALARACT Message 110/2010, Army Implementation of iWATCH (Terrorist Watch Program), 15 April 2010

• iWATCH Army is a nation-wide modern version of neighborhood watch designed to encourage and enable members of the Army community to help protect their community by identifying and reporting suspicious activity or behavior that may be associated with terrorist activities.

• The Passive element of iWATCH Army is individual situational awareness of the surroundings.

• The Active element of iWATCH Army involves individuals taking action to report suspicious activity or behavior to military police or local law enforcement for investigation.

IWATCH Army PSA

5Unclassified date

Place cursor inside black screen area. Control/play will appear at the bottom of the screen. Click (Play/Pause) to view the video.

Indicators of Suspicious Activity or Behavior (What to Report)

6Unclassified date

• Individuals drawing pictures or taking notes in an area not normally of interest to a tourist or showing unusual interest in or photographing security cameras, guard locations, or watching security reaction drills and procedures

• Multiple sightings of the same suspicious person, vehicle, or activity, separated by time, distance, or direction

• Individuals who stay at bus or train stops for extended periods while buses and trains come and go

• Individuals who order food at a restaurant and leave before the food arrives or who order without eating

Indicators of Suspicious Activity or Behavior (What to Report)

7Unclassified date

• Joggers who stand and stretch for an inordinate amount of time

• Individuals sitting in a parked car for an extended period of time

• Individuals who don't fit into the surrounding environment because they are wearing improper attire for the location or season

• Individuals who exhibit suspicious behavior, such as staring or quickly looking away from individuals or vehicles as they enter or leave facilities or parking area

• People asking questions about security forces, security measures, or sensitive information

Indicators of Suspicious Activity or Behavior (What to Report)

8Unclassified date

• Briefcase, backpack, suitcase, or package left unattended

• Vehicle parked in NO PARKING ZONES in front of an important building

• People in restricted areas where they are not supposed to be

• Chemical smells or fumes that worry you

• People purchasing supplies or equipment that can be used to make bombs

• People purchasing weapons or uniforms without proper credentials

“See Something Say Something”

9Unclassified date

How to Report:

• Date and time activity occurred

• Where activity occurred

• Physical descriptions of the people involved

• Description of the vehicle(s) involved

• What type of activity

• Describe what you saw or heard

• Provide pictures if you took any

Where to Report:

• Military Police

• Local law enforcement

• Security forces

• Chain of Command

• Army Counterintelligence

• Contracting Officer

Representative

Source for Other Information

10Unclassified date

Army OneSource (AOS) Website (select iWATCH Army / Antiterrorism logo on website) http://www.myarmyonesource.com

Examples of Information:

• Antiterrorism Awareness Training

• Individual Protective Measures

• Individual Awareness Tips

• Insider Threats

• Active Shooter

• Cyber Threats

• Risks Associated with Social Media

Point of Contact Information

11Unclassified date

Imminent Danger / Threat:

☎ 911

Local to USAG-FH Suspicious Activity Reporting:

DES Desk Officer:

☎ 718 630 4357 (HELP)

Continental United States Suspicious Activity Reporting:

iSALUTE

☎ 1-800-CALL-SPY (1-800-225-5779)

USAG-FH Antiterrorism Officer:

Kira A. Kazmi ☎ 718.630.4814 (Office) kira.a.kazmi.civ@mail.mil

Please add these numbers into your phone:

Questions

12Unclassified date iWATCH Army Training for Contractors “See Something -- Say Something”

Unclassified

Always Ready. Always Alert.

Because someone is depending on you.

Unclassified

United States Army Garrison Fort Hamilton presents a Certificate of Completion to for iWATCH Training for Contractors conducted on

__________ (DDMMYYY)

iWATCH Army Training for Contractors “See Something -- Say Something”

Unclassified

Always Ready. Always Alert.

Because someone is depending on you.

Unclassified

Date (DDMMYYYY) Name (First Last) Company Position / Job Title

United States Army Garrison - Fort Hamilton iWATCH Training for Contractors presented by _____________

Page 1 of 5ENG FORM 6055, JUN 2015 PREVIOUS EDITIONS ARE OBSOLETE.

U.S. Army Corps of Engineers

CONTRACT REQUIREMENTS PACKAGE

ANTITERRORISM/OPERATIONS SECURITY REVIEW COVER SHEET

For use of this form, see AR 525-13, ALARACT 015/2012; and USACE OPORD 2013-74; the proponent agency is CECO-P.

SECTION I - CONTRACT INFORMATION

1. CONTRACT TITLE 2. LOCATION

3. SOLICITATION/CONTRACT NO. 4. CLASS APPROVAL REQUEST NUMBER

5. CONTRACT TYPE

Construction IDIQ MATOC SATOC Service Supply Task Order

Other (specify)

SECTION II - PURPOSE

Part A. Purpose of cover sheet is to document the review of the requirements package performance work statement (PWS)/statement of work (SOW)/ statement of requirements (SOR) for antiterrorism (AT) and other related protection matters to include, but not limited to: operation security (OPSEC), information assurance (IA), physical security, law enforcement, intelligence and foreign disclosure. Army policy requirement: A Signed AT/OPSEC cover sheet is required to be included in all requirements packages except for supply contracts under the simplified acquisition level threshold ($150K), field ordering officer actions and Government purchase card purchases. Local policy may require this form for supply contracts under the simplified acquisition level threshold based on risk and threat. Mandatory review and signatures: The organizational Antiterrorism Officer (ATO) and OPSEC Officer must review each requirements package, unless a signed class approval request form is completed, prior to submission to the supporting contracting activity to include coordination with other staff review as appropriate. If the requiring activity (RA) does not have an ATO or OPSEC Officer, the first ATO and OPSEC Officer in the chain of command will review the contract for AT/OPSEC considerations.

SECTION III - STANDARD CONTRACT LANGUAGE

Part B. Standard Contract Language and/or Additional PWS/SOW/SOR Language. The applicability of each requirement must be considered and each block must be checked "Yes" or "N/A". If the standard PWS/SOW/SOR language text found in Section VIII. of this form is sufficient to meet specific contract request requirements, check "Yes" in block below and include this language in the PWS/SOW/SOR. If the standard PWS/SOW/SOR language applies, but is not in of itself sufficient, check "Yes" and include both the standard language and additional contract specific language in the PWS/SOW/SOR. If standard PWS/SOW/SOR language text does not apply, check "N/A".

SECTION IV - REQUIRED CLAUSES

Required Clause(s) (see Section VIII for sample language) YES N/A

1. AT Level I training (general).

3. AT Awareness training for contractor personnel traveling overseas.

2. Access and General Protection/Security Policy and Procedures.

2a. Contractors requiring Common Access Card (CAC).

2b. Contractors who do not require CAC, but require access to a Department of Defense (DoD) facility or installation.

4. iWATCH and/or CorpsWatch training.

5. Access to government information systems.

6. OPSEC SOP/Plan requirements.

7. Requirement for OPSEC training.

8. Information assurance/information technology training.

9. Information assurance/information technology training certification.

10. Contractors Authorized to Accompany the Force (OCONUS).

11. Contract requires performance or delivery in a foreign country (OCONUS).

12. Handling/Access to Classified Information.

13. Will be escorted in areas where they may be exposed to classified and/or sensitive materials.

14. Contractor Company to obtain a Facility Clearance and individual clearances at the appropriate level.

Page 2 of 5ENG FORM 6055, JUN 2015

SECTION V - REMARKS

1. CONTRACT TITLE 2. LOCATION

3. SOLICITATION/CONTRACT NO. 4. CLASS APPROVAL REQUEST NUMBER

5. CONTRACT TYPE

Construction IDIQ MATOC SATOC Service Supply Task Order

Other (specify)

15. Pre screen candidates using E Verify Program.

16. For contracts requiring armed security guards.

17. Threat Awareness Reporting Program (TARP) training.

SECTION VI - ANTITERRORISM REVIEWER'S SIGNATURE

I am ATO Level II certified and I have reviewed the requirements package and understand my responsibilities IAW Army Regulation 525 13, Antiterrorism.

1. TYPED OR PRINTED NAME 2. RANK/CIVILIAN GRADE 3. PHONE NUMBER

5. DATE4. SIGNATURE

SECTION VII - OPERATIONS SECURITY REVIEWER'S SIGNATURE

I am OPSEC Level II certified and have reviewed the requirements package to ensure that there are no OPSEC concerns regarding the release and/or publication of attached documentation to public forums as well as to determine OPSEC requirements for the Contractor, and understand my responsibilities IAW Army Regulation 530 1, Operations Security.

3. PHONE NUMBER2. RANK/CIVILIAN GRADE1. TYPED OR PRINTED NAME

4. SIGNATURE 5. DATE

Page 3 of 5ENG FORM 6055, JUN 2015

SECTION VIII - STANDARD CONTRACT PROVISION AND CLAUSE TEXT APPLICABILITY AND/OR ADDITIONAL PWS/SOW/SOR LANGUAGE

(To access a Word version of page 3 and 4 for this form please click on the attachment icon on the left of the form)

1. AT Level I Training. This provision/contract text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language: "All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum."

2. Access and General Protection/Security Policy and Procedures. This standard language text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language: "All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by

DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection

Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes."

2a. For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05 and

Homeland Security Presidential Directive-12 (HSPD-12). Proposed language: “The contractor and all sub-contractors employees will be issued a

CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely;

(2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an interim CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the

Office of Personnel Management.”

2b. For contractors who do not require CAC, but require access to a DoD facility or installation. Proposed language: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate

Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3. AT Awareness Training for Contractor Personnel Traveling Overseas. This standard language text required US based contractor employees and associated sub-contractor employees to make available and to receive government provided area of responsibility (AOR) specific AT awareness training as directed by AR 525-13 (Antiterrorism). Specific AOR training content is directed by the combatant commander with the unit ATO being the local point of contact. Proposed language: "All US based contractor employees and associated sub-contractor employees traveling overseas will receive the government provided AOR specific AT awareness training. The documentation of training completion must be provided to the COR prior to departure.”

5. Contractor Employees Who Require Access to Government Information Systems. This standard language text is for contractor employees with access to government info system. Proposed language: "All contractor employees with access to a government info system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete the DOD Information

Assurance Awareness prior to access to the information systems and then annually thereafter in accordance with personnel security standards listed in

AR 25-2 (Information Assurance), an appropriate background investigation will be conducted prior to accessing the government information systems."

4. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language: "The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training."

Page 4 of 5ENG FORM 6055, JUN 2015

6. For Contracts that Require an OPSEC Standing Operating Procedure/Plan. This standard language text is for contractor employees with an area of performance for classified contracts or if the contract employee has access or responsibility to protect critical information. The Contractor, in collaboration with RA OPSEC Officer, shall develop an OPSEC Standard Operating Procedure (SOP)/Plan within 90 calendar days of contract award per AR 530-1 (Operations Security). Proposed language: "The Contractor shall develop an OPSEC SOP/Plan within 90 days of contract award. The

OPSEC SOP/Plan must be reviewed and approved by the RA OPSEC Officer. The SOP/Plan will include the government's critical information, why it needs to be protected, where it is located, who is responsible for it and how to protect it. In addition, the contractor shall identify an individual who will be an OPSEC Coordinator."

7. For Contracts that Require OPSEC Training. Per AR 530-1, (Operations Security) contractor employees must complete Level I OPSEC Training within 30 calendar days of contract award. Proposed language: "All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum."

8. For Information assurance (IA)/information technology (IT) training. This standard language text is for contract employees who need network access and/or working IA/IT functions. Proposed language: "All contractor employees and associated sub-contractor employees must complete the

DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoDD 8570.01, DoD 8570.01-M and AR 25-2 within six months of employment."

9. For information assurance (IA)/information technology (IT) certification. Per DoD 8570.01-M , DFARS 252.239.7001 and AR 25-2, the contractor employees supporting IA/IT functions shall be appropriately certified upon contract award. The baseline certification as stipulated in DoD

8570.01-M must be completed upon contract award. Proposed language: "All contractor employees supporting IA/IT functions shall be appropriately certified upon contract IAW DoD 8570.01-M, DFARS 252.239-7001 and AR 25-2. The baseline certification as stipulated in DoD 8570.01-M must be completed upon contract award."

10. For Contractors Authorized to Accompany the Force. DFARS Clause 252.225-7040, Contractor Personnel Authorized to Accompany U.S.

Armed Forces Deployed Outside the United States. The clause shall be used in solicitations and contracts that authorize contractor personnel to accompany US Armed Forces deployed outside the US in contingency operations; humanitarian or peacekeeping operations; or other military operations or exercises, when designated by the combatant commander. Proposed language: "All contractor employees shall ensure the following

AT/OPSEC requirements are met prior to deploying personnel authorized to accompany U.S. Armed Forces outside the United States; to include compliance with laws, regulations, pre-deployment requirements, and required training in accordance with combatant command guidance."

11. For Contracts Requiring Performance or Delivery in a Foreign Country. DFARS Clause 252.225-7043, Antiterrorism/Force Protection for

Defense Contractors Outside the US. The clause shall be used in solicitations and contracts that require performance or delivery in a foreign country.

This clause applies to both contingencies and non-contingency support. Proposed language: "All non-local contracting personnel will comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor's compliance with combatant commander and subordinate task force commander policies and directives."

13. Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. The contractor will coordinate with the COR and/or the facility security office for access when required. (Use when security clearances are not required, i.e.

facility repair or construction). Proposed language: "All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas."

12. For Contracts That Require Handling or Access to Classified Information. This clause involves access to classified information, i.e.

“Confidential,” “Secret,” or “Top Secret”. Proposed language: "Contractor shall comply with AR 380-67 (Personnel Security Program) and Homeland

Security Presidential Directive 12 (Policy for a Common Identification Standard for Federal Employees and Contractors) as well as FAR 52.204-2, Security Requirements. Additionally, Contractors must comply with - (1) The Security Agreement (DD Form 441), including the National Industrial

Security Program Operating Manual (DoD 5220.22-M); any revisions to DOD 5220.22-M, notice of which has been furnished to the contractor. For classified contracts, the DD Form 254 will be attached with the contract."

Page 5 of 5ENG FORM 6055, JUN 2015

14. (FOR CLASSIFIED CONTRACTS ONLY) Contractor Company to obtain a Facility Clearance and individual clearances at the appropriate level. Proposed language: "The Prime Contractor Company must have a Facility Clearance (FCL) at the appropriate level (IAW the NISPOM

DOD 5220.22-M and AR 380-49) prior to the start of the contract awarded period of performance. Contractor personnel performing work under this contract must have the required security clearance, per AR 380-67, at the appropriate level at the start of the period of performance. Security

Clearances and FCL requirements are required to be maintained for the life of the contract IAW the DD Form 254 attached to the contract. If no

FCL, the supporting Government Contracting Activity will sponsor the prime contract company in obtaining the FCL."

15. Pre-screen candidates using E-Verify Program. Proposed language: "The Contractor must pre-screen Candidates using the E-verify Program

(http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative.

This Form will…