Request for White Paper - ICD 705 Compliant Trailers
Solicitation number
FA9101279ICD705
Issued by

About this file

This is a Request for Whitepapers (RWP) issued by the Department of the Air Force, Headquarters Air Force Test Center (AFMC) at Edwards Air Force Base, California, seeking innovative proposals from AEDC Velocity Alliance Consortium members and industry partners via SAM.gov to design, procure, site, install, integrate, and accredit temporary secure working areas (TSWAs) for ICD-705 compliant trailers. The contracting organization is AFTC/PZIA (Arnold), with applicable NAICS code 541330 (Engineering Services) and PSC code 5410 (Prefabricated and Portable Building). The acquisition is authorized under 10 U.S.C. § 4022 Other Transaction Authority (OTA), with offerors permitted to recommend alternative NAICS and PSC codes.

The project is structured in two phases: a base Design & Feasibility Phase requiring business process validation, feasibility demonstration, utility routing planning, and TEMPEST compliance strategy, culminating in an approved design package meeting Preliminary Design Review (PDR) and Critical Design Review (CDR) standards; and an optional Procurement & Execution Phase for procuring, delivering, siting, installing, and accrediting the trailers upon successful design completion and fund availability. Performers must demonstrate technical competency in ICD-705 and TEMPEST design expertise, soundproofing engineering to achieve STC-55 ratings, utility and systems integration within Building B876, cybersecurity compliance per DoD and NSA standards, and quality control and project management capabilities. The whitepaper submission is limited to 15 pages and must address five core technical criteria and include a Technical Capability Statement. Performers must meet 10 U.S.C. § 4022(d) eligibility requirements by satisfying at least one condition: participation of a nontraditional defense contractor or nonprofit research institution; all significant participants being small businesses or nontraditional contractors; at least one-third cost-sharing from non-Federal sources; or exceptional circumstances justification from the senior procurement executive. Pricing must separate firm-fixed-price milestones (Milestones 1–5 for design and feasibility) from Rough Order of Magnitude estimates and schedules for optional milestones (Milestones 6–9 for procurement and execution). The Government intends to negotiate Unlimited Data Rights to all technical data, drawings, software, and code produced; performers must formally confirm agreement or justify any restricted data rights assertions. All submissions must reference cybersecurity and CMMC requirements and demonstrate CMMC Level 2 compliance for SAM.gov submissions. Evaluation will proceed through compliance screening, technical evaluation of demonstrated capability (not active prototype designs), and price/business evaluation. The submission deadline is 20 November 2026 at 4:00 PM Central Standard Time, with electronic submission via PDF to Haley Smith (haley.smith.10@us.af.mil) or Paytonne Szatkowski (paytonne.szatkowski@us.af.mil) for SAM.gov submissions or through AcqBot portal for VAC members.

View the file

Other versions and copies of ICD 705

File Revision Posted Attached to
ICD 705 Tech Specs Ver 1.5.1_26 Jul 2022PDF.pdf Version 1.5.1, Jul 26, 2022 Access Control System
Sources_Sought_ICD705_Osan_PDB_OTA_27Oct26_V1.pdf Oct 27, 2026 ICD-705 Controlled Spaces Modernization and Sustainment Program - (Progressive Design-build (PDB) Other Transaction Agreement (OTA)
ICD 705 v1.5.1 Tech_Specs_for_Construction_and_Management_of_SCIFs_v1.5.1_ July 26, 2021.pdf Jul 1, 2026 IDS/ACS System
ICD 705 v1.5.1 Tech_Specs_for_Construction_and_Management_of_SCIFs_v1.5.1_ July 26, 2021.pdf Jul 1, 2026 Request for Information - IDS/ACS System
(CUI) ICD 705 v1.5.1 Tech_Specs_for_Construction_and_Management_of_SCIFs_v1.5.1_ July 26, 2021.pdf Jul 1, 2026 Request for Information - IDS/ACS System
RFI_N40080RFI24RP00048_Souces Sought ICD 705 Space NSA Washington 01.24.2024.pdf Jan 24, 2024 REQUEST FOR INTEREST (RFI) N40080RFI24RP00048 - SOURCES SOUGHT ONLY
Attachment 5 - ICD-705-Technical-Specifications 1.4 Sep 2017.pdf Sep 4, 2017 MA MERS SCIF Door Replacement at the FEMA, MERS, VSAB, Bldg. B
USEB262315 - 5h. - ICD 705 Tech Specs.pdf Revision not stated USEB262315 - B302 ISRG Ops HVAC Increase
ICD 705 Manual.pdf Revision not stated Combo - FY26 Wargamming Secure (Vault) Door
ICD 705 Technical Specifications v1.5.1.pdf Revision not stated Maintenance SCIF Alarm Systems Recompete
ICD 705 Technical Specifications v1.5.1.pdf Revision not stated SCIF MAINTENANCE FOR MSC
CDRL-009_Ph2-ICD705ComplianceReport.pdf Revision not stated FA248624RB004- Mobile SAPF Trailer
Attachment 1a - ICD 705.pdf Revision not stated 3TES SCIF Door Installation
ICD 705.pdf Revision not stated 3TES SCIF Door Installation
ATTACH07_ICD705_Construction and Management_SCIF.PDF Revision not stated Robins AFB Mechanical/Electrical II IDIQ
ICD 705 Chapter 9 Acoustic Mitigation.pdf Revision not stated A032005 - RFI Acoustic Mitigation
ICD_705_SCIFs.pdf Revision not stated HNJ Lundy Conference Room A/V Upgrade
AppD6. ICD 705.pdf Revision not stated Install Beacon Lighting
Bidders Library Security - ICD 705.pdf Revision not stated TEC II Services RFP
Attachment 3 ICD 705 Door Criteria - Addl salient characteristics.pdf Revision not stated Specialized Acoustic Doors
Show all 20

Who attaches ICD 705

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS AIR FORCE TEST CENTER (AFMC)

EDWARDS AIR FORCE BASE CALIFORNIA

REQUEST FOR WHITEPAPERS (RWP)

To: AEDC Velocity Alliance Consortium Performers and Industry Partners via SAM.gov

Project Title: ICD-705 Compliant Trailers

Contracting Organization: AFTC/PZIA (Arnold)

Applicable NAICS Code: 541330 – Engineering Services

Applicable PSC Code: 5410 – Prefabricated and Portable Building

Acquisition Authority: 10 U.S.C. § 4022 Other Transaction Authority (OTA)

Offerors may recommend alternative NAICS and PSC for consideration.

1.0 Introduction and Purpose

The Arnold Engineering Development Complex (AEDC) is seeking innovative whitepapers from members of the AEDC Velocity Alliance Consortium and industry partners via SAM.gov to design, procure, site, install, integrate, and accredit temporary secure working areas (TSWAs).

2.0 Project Scope and Key Objectives

The project's key objectives are organized into structured phases to transition from feasibility and business process validation to physical execution and accreditation.

• Design & Feasibility Phase (Base Effort): Performers will conduct a business process validation to define the total physical footprint needed for two (2) OEMs in secure, separated spaces. Performers will demonstrate the feasibility of the proposed configuration, utility routing, and initial TEMPEST compliance strategy, culminating in a complete and approved design package (including fabrication plans and site preparation drawings) that meets

Preliminary Design Review (PDR) and Critical Design Review (CDR) expectations.

• Procurement & Execution Phase (Optional Effort): Upon successful completion and approval of the design, and subject to the availability of funds, the Government may exercise options to procure, deliver, site, install, integrate utilities for, and obtain full accreditation for the trailers/prefabricated facilities.

3.0 Instructions for Performer's Response

3.1 Technical Competency

Performers must submit a Technical Capability Statement within their Whitepaper that details their ability to execute this project. Performers will be evaluated on their demonstrated capability, rather than submitting final designs. The Whitepaper must address the following technical criteria:

1. ICD-705 and TEMPEST Design Expertise: Demonstrated capability to design, construct, and secure accreditation for facilities meeting ICD-705 compliance and full TEMPEST certification standards.

2. Soundproofing Engineering: Demonstrated experience or capability to meet a Sound

Transmission Class (STC) rating of STC-55 within the integrated conference rooms.

3. Utility and Systems Integration: Capability to site and integrate complex utilities (including high-reliability power, fiber-optic network cabling, and HVAC systems) into prefabricated structures, specifically within an existing facility environment (Building B876).

4. Cybersecurity Compliance: Demonstrated capability to integrate automated information systems and encryption/cryptologic devices in strict compliance with current Department of

War (DoW) information assurance, cybersecurity, and Risk Management Framework (RMF) certification standards, as well as National Security Agency (NSA) guidelines.

5. Quality Control and Project Management: Proven approach to managing complex schedules, minimizing disruptions to ongoing facility operations (including executing utility/network outages in coordination with the Government), and delivering a robust

Quality Control Plan (QCP).

3.2 Intellectual Property (IP) & Data Rights

The Government intends to negotiate Unlimited Data Rights to all technical data, drawings, software, code, and programming produced in performance of this effort. All whitepaper submissions must reference "Article: Intellectual Property Rights in accordance with part 3 of the AEDC Velocity

Consortium Request for Whitepaper." Performers must provide a formal, written confirmation in their submission stating that they agree to the Government's IP and data rights expectations, or explicitly state and justify any proposed assertions of restricted data rights.

3.3 10 U.S.C. 4022(d) Appropriate Use of Authority

To be eligible for award of an Other Transaction (OT) Agreement under 10 U.S.C. § 4022, the

Performer must meet at least one of the following conditions:

(1) There is at least one nontraditional defense contractor or nonprofit research institution participating to a significant extent in the prototype project.

(2) All significant participants in the transaction other than the Federal Government are small businesses (including small businesses participating in a program described under section 9 of the

Small Business Act (15 U.S.C. 638)) or nontraditional defense contractors.

(3) At least one-third of the total cost of the prototype project is to be paid out of funds provided by sources other than the Federal Government.

(4) The senior procurement executive for the agency determines in writing that exceptional circumstances justify the use of a transaction that would otherwise not be feasible or appropriate.

Note 1: "Nontraditional Defense Contractor" (NDC) is defined in 10 U.S.C. § 3014 as an entity that is not currently performing and has not performed, for at least the one-year period preceding the solicitation of sources by the Department of Defense for the procurement or transaction, any contract or subcontract for the Department of Defense that is subject to full coverage under the cost accounting standards prescribed pursuant to section 1502 of title 41 and the regulations implementing such section.

Note 2: "Significant extent" participation is determined based on factors including, but not limited to, the technical contribution, critical technologies developed, risk shared, or other factors that show the entity’s participation is vital to the success of the prototype project.

Note 3: Small business is defined under section 3 of the Small Business Act (15 U.S.C. 632).

Performers MUST explicitly state in their Whitepaper which of the above criteria they satisfy and provide detailed supporting documentation (e.g., description of the significant participant’s role and contribution, or cost-sharing plan) to justify their eligibility.

3.4 Pricing and Schedule

Performers must structure their pricing and schedule response into two distinct parts:

• Base Milestones (Design & Feasibility): Performers must provide a firm-fixed-price proposal and a detailed schedule for Milestones 1 through 5.

• Unpriced Options (Procurement & Execution): For Milestones 6 through 9, Performers are not required to provide firm-fixed-price milestones at this stage. However, Performers are required to provide a Rough Order of Magnitude (ROM) cost estimate and an estimated execution schedule to support the Government's planning.

3.5 Cybersecurity and CMMC Compliance

Performers must comply with all Department of Defense cybersecurity and information assurance requirements. All VAC whitepaper submissions must reference "Article: Cybersecurity

Requirements (CUI and CMMC)," while SAM.gov submissions must provide evidence of CMMC

Level 2 compliance. Compliance with these cybersecurity and RMF standards must flow down to all subcontractors and team partners. Ensuring complete subcontractor compliance is the sole responsibility of the prime Performer.

4.0 Evaluation Details

The Government will evaluate the Performer's response using a multi-step evaluation process based on the following criteria:

4.1 Compliance Screen

The Government will conduct an initial compliance check to verify:

(A) Completeness of the submission, including all required technical and pricing/schedule components.

(B) Verification that the Performer meets the statutory requirements of 10 U.S.C. § 4022(d) as detailed in Section 3.3.

Submissions that do not meet these threshold requirements may be excluded from further evaluation.

4.2 Technical Evaluation

The Government will evaluate the Performer's capability to execute the project based on the following evaluation factors, which are of equal importance:

(A) Technical Competency: The degree to which the Performer demonstrates the required technical capabilities, experience, and understanding of the project's complex technical requirements based on documented past experience. This evaluation focuses strictly on the Performer's historical capability to execute similar efforts, as the Government is evaluating the capability to perform and is NOT requesting or evaluating active prototype designs within the Whitepaper submission. Key areas of past experience evaluated include:

1. Designing and building to ICD-705 standards and securing TEMPEST certification.

2. Achieving STC-55 soundproofing ratings in conference rooms.

3. Site planning, design, and utility integration within an existing facility.

4. Integration of automated information systems and cybersecurity compliance under RMF.

5. Developing and maintaining a robust Quality Control Plan (QCP).

(B) Schedule and Feasibility: The adequacy and realism of the proposed execution schedule, and the

Performer's planned approach to minimize disruptions to ongoing operations (e.g., managing utility/network outages).

4.3 Price and Business Evaluation

(A) Base Milestones (Design & Validation): The Government will evaluate the realism and reasonableness of the proposed firm-fixed-price milestones.

(B) Unpriced Options (Procurement & Execution): The Government will evaluate the realism and reasonableness of the Rough Order of Magnitude (ROM) and the estimated schedule for the optional milestones.

(C) Intellectual Property and Data Rights: The Government will evaluate any proposed assertions of restricted data rights. Performers that agree to the Government's intent to negotiate Unlimited Data

Rights will be evaluated more favorably.

5.0 Successful Prototype Definition

Pursuant to 10 U.S.C. § 4022, this project consists of two distinct prototype efforts: Prototype A

(Proof of Concept/Business Process) and Prototype E (Operational Utility).

Prototype A: Proof of Concept / Business Process

• Description of Prototype: A developmental, virtual, and administrative design prototype focused on verifying the technical and spatial feasibility of the ICD-705 compliant trailers.

This effort encompasses the business process validation, space optimization modeling, initial

TEMPEST compliance strategy, utility coordination, and the delivery of a comprehensive, approved engineering design package.

• Key Parameters & Variables integrated from the SOO:

o Siting and Footprint o Utility Coordination o Design Reviews

• Successful Completion Criteria: Prototype A is successfully completed upon the

Government's formal review, acceptance, and approval of the following deliverables:

1. Site Selection and Business Process Documentation Report.

2. Proof of Concept Results demonstrating trailer and utility configuration feasibility.

3. Final Approved Design Package (including all fabrication plans and site preparation drawings).

• Transition Path: Upon successful completion of Prototype A, and subject to funding availability, the Government intends to transition to Prototype E (Operational Utility) under this Agreement without further competition.

Prototype E: Operational Utility

• Description of Prototype: A physical, operational prototype consisting of fully manufactured, installed, integrated, and accredited trailers/prefab facilities. This prototype delivers the actual, accredited working environment required to host classified OEM activities.

• Key Parameters & Variables integrated from the SOO and Performance Parameters:

o Quantity (Threshold): Procurement and installation of two (2) trailers/prefab facilities total (one for OEM 1, one for OEM 2), each providing 30 seats and an integrated conference room.

o Quantity (Objective): Scalable procurement of up to six (6) trailers/prefab facilities total (three for OEM 1, three for OEM 2).

o Configuration: Each OEM space must feature three distinct compartmented spaces

(Area 1, Area 2, and a conference room).

o Classification & Soundproofing: Achieve full ICD-705 compliance and TEMPEST certification, alongside an STC-55 soundproof rating for all integrated conference rooms.

o Cybersecurity: Complete RMF certification and DoD information assurance compliance. Secure NSA accreditation for any housed TACLANEs or cryptologic systems.

o Site Integration & Restoration: Complete restoration of any grounds or utility infrastructure disturbed during installation to original conditions (e.g., reseeding ground areas).

o Training: On-site orientation and recorded training delivered to the Government for all physical security, HVAC, and power management systems.

• Successful Completion Criteria: Prototype E is successfully completed upon:

1. Delivery, physical installation, and utility hookup of the trailers inside the designated area.

2. Receipt of formal ICD-705 and TEMPEST accreditation for the facilities.

3. Delivery of on-site orientation and recorded training to Government personnel.

4. Submission and approval of the Final Accreditation and Validation Report and the comprehensive Final Report (containing all raw/processed project validation data, calibration records, warranty information, and operation manuals).

• Transition Path (Follow-On Production): In accordance with 10 U.S.C. § 4022(f), upon successful completion of the Prototype E operational utility requirements, the Government may transition this effort into a non-competitive follow-on production contract or transaction for additional trailers (up to the objective requirement of 6 total), facility support, or operational maintenance.

6.0 Program Milestones

The Performer shall execute the project in accordance with the following structured milestones. To allow maximum scheduling flexibility, target dates are omitted. Each milestone represents a distinct, sequential deliverable mapping directly to the successful prototype definitions in Section 5.0.

Milestone Milestone Name & Description Prototype Association Funding

Status

Project Kickoff Meeting: Establish communication channels, review technical requirements, and coordinate initial planning activities.

Prototype A (Proof of

Concept/Business

Process)

[Base

Milestone]

Business Process Review and Siting Strategy

Approved: Validate total footprint for two (2)

OEMs, identify location, coordinate utilities with

AEDC, and deliver Site Selection Report.

Prototype A (Proof of

Concept/Business

Process)

[Base

Milestone]

Proof of Concept Review: Demonstrate trailer configuration feasibility, utility routing, and initial

TEMPEST compliance strategy, and deliver Proof of Concept Results.

Prototype A (Proof of

Concept/Business

Process)

[Base

Milestone]

Preliminary Design Review (PDR): Present initial design package including draft fabrication plans and site preparation drawings.

Prototype A (Proof of

Concept/Business

Process)

[Base

Milestone]

Critical Design Review (CDR): Finalize design package, fabrication plans, and site preparation drawings for the ICD-705 compliant trailers/prefab facilities.

Prototype A (Proof of

Concept/Business

Process)

[Base

Milestone]

Material Procurement and Readiness Review:

Procure trailers/prefab facilities, physical security systems, HVAC, and power management systems.

Prototype E

(Operational Utility)

[Unfunded

Option]

Trailer Delivery and Installation Completed:

Deliver and install trailers/prefab facilities inside

B876, ensuring three compartmented spaces for each of the two (2) OEM spaces (Threshold

Requirement).

Prototype E

(Operational Utility)

[Unfunded

Option]

Utility Integration Completed: Integrate power, fiber, HVAC, and information systems complying with DoD cybersecurity/RMF. Complete on-site orientation and training.

Prototype E

(Operational Utility)

[Unfunded

Option]

Final Accreditation and Validation Report

Delivered and Approved: Secure full ICD-705 accreditation and deliver Final Accreditation and

Prototype E

(Operational Utility)

[Unfunded

Option]

Validation Report and the comprehensive Final

Report.

7.0 Submission Details

• Submission Deadline: 20 November 2026, 4:00pm Central Standard Time (CST)

• Submission Format: Electronic submission may be made in PDF format via email to the

Agreements Officer for offerors responding to the SAM posting or through the AcqBot portal for VAC members. White papers should be no more than 15 pages.

• Government Point of Contact: Haley Smith at haley.smith.10@us.af.mil and Paytonne

Szatkowski at paytonne.szatkowski@us.af.mil

8.0 Attachments

The following source documents govern this requirement and are incorporated by reference:

1. Statement of Objectives (SOO) – AEDC-Arnold AFB: ICD-705 Compliant Trailers

2. Attachment 1 – Performance Parameters

3. Appendix A – SEA and Design Flow

4. Appendix B – AEDC Engineering and Safety Standards

HALEY M. K. SMITH

Agreements Officer mailto:haley.smith.10@us.af.mil mailto:paytonne.szatkowski@us.af.mil

REQUEST FOR WHITEPAPERS (RWP)
To: AEDC Velocity Alliance Consortium Performers and Industry Partners via SAM.gov Project Title: ICD-705 Compliant Trailers Contracting Organization: AFTC/PZIA (Arnold) Applicable NAICS Code: 541330 – Engineering Services Applicable PSC Code: 5410 ...
1.0 Introduction and Purpose
2.0 Project Scope and Key Objectives
3.0 Instructions for Performer's Response
3.1 Technical Competency
3.2 Intellectual Property (IP) & Data Rights
3.3 10 U.S.C. 4022(d) Appropriate Use of Authority
3.4 Pricing and Schedule
3.5 Cybersecurity and CMMC Compliance
4.0 Evaluation Details
5.0 Successful Prototype Definition
Prototype A: Proof of Concept / Business Process
Prototype E: Operational Utility
6.0 Program Milestones
7.0 Submission Details
8.0 Attachments