Closed 2702_Responses to Questions_v1.pdf
PDF 50 KB Posted
- Solicitation number
- FA890326SC001
About this file
This is a Questions and Answers document for the SPEED CSO Utility Survey at RAF Lakenheath, a federal contracting opportunity involving water and sewer utility mapping and data collection at a U.S. Air Force installation in the United Kingdom.
The Government seeks a comprehensive utility survey covering potable water and sewer assets across an administrative and dormitory pilot area of approximately 850,000 square meters. Spiral 1 responses must address both water and sewer mapping, with offerors stating their target confidence level using ASCE 38-22 quality levels as the preferred reference standard. Option A pricing should be based on total ground area surveyed with all assets inside mapped; Option B is a 60-day proof-of-concept sprint including field mapping, valve inventory, populated dataset, training, and use-case demonstration. The Government will furnish approximate installation-wide water main length and valve/hydrant counts to Spiral 2 selected offerors for scaling purposes. Current water records are maintained in ESRI ArcGIS File Geodatabase format and can be provided in multiple formats (.gdb, .shp, .dwg, PDF) subject to CUI permissions, with release possible at pilot start or prior. Deliverables must comply with SDSFIE-V 4.0.3.2, be compatible with ESRI ArcGIS, and be georeferenced in UTM Zone 31 North, WGS-84. The designated pilot area is the administration and dormitory zone. 48 Civil Engineer Squadron (48 CES) owns and operates the installation distribution network; exact demarcation between supplier main and 48 CES responsibility is at the Government point of supply. Offerors may propose minimally invasive methods such as targeted vacuum excavation or trial holes; contractor submits AF Form 103 through the Government project manager for permits, with 48 CES facilitating expedited approval and contractor responsible for reinstatement to base standards. Offeror staff may connect survey equipment under 48 CES water shop supervision. For the pilot, the solution shall be offeror-hosted with data collected on non-networked standalone field devices; offerors must provide field tablets and handle all utility data as Controlled Unclassified Information (CUI). Training shall cover approximately 10 installation personnel from Operations, Engineering, and Installation Management. Proposal closing is 5:00 PM Central Standard Time on December 16, 2026, with all answers to be published to all offerors.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPEED CSO Utility Survey at RAF Lakenheath Questions
Scope and Plot
1. Section 1.4 mentions potable water and sewer, while Sections 2 and 3 focus on water. Should Spiral 1 responses address sewer, or treat it as an optional add-on?
Spiral 1 responses should address potable water and sewer. The installation sewer is predominantly clay and is known to conflict with other utilities (for example around Yankee Loop drainage). Offerors may still propose potable-only approaches, but sewer mapping is in scope. The offer can scope it as an option in their white paper proposal.
2. Has 48 CES identified priority pilot area(s)? If so, what is their approximate size (m²) and type (housing, industrial, administrative, airside)?
The designated pilot is the admin and dormitory area so will have pipe considerations, for such spaces. Approximate size is 850,000 square meters, but we will pick a size that fits into our budget based on the offerors prices
3. For Option A, should the square-meter basis be the total ground area of the survey zone, with all water assets inside it mapped? Is there a target confidence level for the baseline price?
The square-meter basis is the total ground area of the designated survey zone. All water (and, per Q1, sewer) assets inside that boundary must be mapped. Offerors shall state the target confidence level of their proposed method; ASCE 38-22 quality levels are the preferred reference.
4. Should the Option B 60-day sprint include the full proof-of-concept in Section 3.8 (mapping, valve inventory, data set, training, use-case demo), or mainly field mapping?
The 60-day sprint is the full proof-of-concept in Section 3.8: field mapping, valve inventory, populated data set, training, and a use-case demonstration — not field mapping alone.
5. To help scale pricing installation-wide, can the Government share approximate totals: length of water main, and number of valves and hydrants?
Yes. Approximate totals for length of water main and numbers of valves and hydrants can be provided to support installation-wide scaling. The Government will furnish those figures to selected offerors during the Sprial 2 phase to help further quantify the numbers provided in Spiral 1. Offerors should not wait on those numbers to price the pilot area in Q2 for this Spiral 1.
Existing Records and Operations
6. What form are the current water records in (GIS/GeoBase, CAD, scanned drawings, paper)? Will they be released to selected offerors before Spiral 2 or at pilot start?
Current water records are maintained in an ESRI ArcGIS File Geodatabase format and can be exported/provided as File Geodatabase (.gdb), Shapefile (.shp), CAD (.dwg), or PDF/map prints as required. Release at pilot start (or prior) is possible subject to appropriate CUI permissions and agreements.
7. Are tracer wire or marker tape known to be installed with any polyethylene mains or services?
Tracer wire / marker tape. Non-tracer marker tape has been found on past excavations of polyethylene. Tracer wire has not been found during emergency repairs. Offerors should not assume a locatable tracer on PE mains or services.
8. Is the distribution network operated and maintained wholly by 48 CES, or are parts covered by a UK MOD/DIO water services arrangement? Where are the ownership boundaries (for example, the point-of-supply meter)?
48 CES owns and operates the installation distribution network. The Anglian Water feed into the base is separate. There are two Anglian Water meters on the supply (one external to the installation, one internal). Exact demarcation between the supplier main and 48 CES responsibility is at the Government point of supply, which will be identified to the Spiral 3 selected offeror.
9. Is there any existing district metering, pressure monitoring, SCADA or leak-detection equipment on the network?
Electronic metering is installed at the reservoir. Some buildings have local meters, and there are line meters in the housing district. There is no installation-wide district metering, pressure-monitoring, SCADA, or leak-detection system covering the network.
Field Operations
10. May offerors propose targeted vacuum excavation or trial holes to verify segments?
Who would obtain dig permits (AF Form 103) and perform reinstatement?
Yes. Minimally invasive methods such as targeted vacuum excavation or trial holes are permitted and preferred (safer around other utilities). The contractor submits AF Form 103 through the Government project manager; 48 CES will facilitate and expedite the permit.
The contractor is responsible for reinstatement to base standards.
11. For survey methods that need access to the water system (hydrants, valves, meter points), may offeror staff connect equipment under 48 CES supervision, or must Water Management staff do all operation?
Offeror staff may connect survey equipment to hydrants, valves, and meter points under supervision of the 48 CES water shop (WFSM). Water Management staff will not be required to perform every operation, but they retain control of the live system.
12. Does the installation require a UXO risk assessment, archaeological watching brief, or ecological clearance before intrusive work? Are any areas restricted for habitat reasons?
Some areas have habitat and protected wildlife that must be considered. UXO, archaeological, and environmental restrictions apply. If intrusive work is proposed, 48 CES will coordinate base-level clearance approvals with Defense Infrastructure Organisation.
Offerors should plan the Spiral 3 to avoid known UXO and archaeological restriction areas.
Additionally a map will be provided in Spiral two for better understanding of the environment needed for a more detailed plan.
13. Please provide 48 SFS Lakenheath Instruction 31-101. What is the typical lead time for contractor access processing and escort requirements for airside or controlled areas?
Typical processing at the gate is 30 minutes to one hour once credentials are in order.
Escorts are required in controlled areas and must maintain line of sight at all times. 48 SFS Lakenheath Instruction 31-101 will be provided prior to Spiral 3, if requirement for the offeror to come on base before that time, 48 CES in conjunction with 48 CONs will work the requirements with 48 SFS; the current contractor-access implementation plan is still being finalized with Security Forces. Airside / controlled-area access will be coordinated case-by-case.
IT, Data and Hosting
14. For the pilot, should the solution be hosted on an AF network/NexGen IT, run as a standalone government-owned system, or be offeror-hosted? Can pilot data be collected on non-networked devices?
For the pilot, the solution shall be offeror-hosted. Pilot data shall be collected on non-networked, standalone field devices. Offerors are prohibited from connecting non- Government Furnished Equipment (non-GFE) directly to the Air Force Network. Any system storing or processing Air Force water-utility data must meet DoD CUI protection requirements. The Government’s desired long-term end-state (not a pilot requirement) is a 48 CES-owned standalone system that limits recurring licensing, or a solution that integrates directly with GeoBase / NexGen IT. The 48 CES does have the capability of taking data on stored media device such as a DVD or Blu-ray and uploading to the existing authoritative system for pilot information.
15. Which systems hold water utility data at Lakenheath today (GeoBase, NexGen IT modules, other), and which SDSFIE version or data standard should deliverables follow?
GeoBase (ArcGIS Enterprise) is the authoritative system of record for installation utility data. NexGen IT (TRIRIGA) holds associated real-property records. Deliverables shall comply with SDSFIE-V 4.0.3.2, be compatible with ESRI ArcGIS, and be georeferenced in UTM Zone 31 North, WGS-84. Surveyed benchmarks should be used whenever possible.
The Government can supply a blank, schema-compliant File Geodatabase template. For offerors without ESRI capability, alternative delivery (CAD or Shapefiles) mapped to the SDSFIE schema can be coordinated.
16. Will the Government furnish field tablets, or should offerors provide them? Should utility data be handled as CUI?
The Government will not furnish field tablets or mobile hardware; offerors shall provide them. All water-utility data sets are Controlled Unclassified Information (CUI) and shall be handled and stored as such.
Process
17. What is the closing time and time zone on 16 Dec 2026? Is there a deadline for questions, and will answers be published to all offerors?
The closing time will be 5pm Central Standard Time in the US on the 16th of December 2026 and yes all answers will be published to all offerors.
18. How many installation personnel should the proof-of-concept training cover?
Plan to train approximately 10 installation personnel drawn from Operations (CEO), Engineering (CEN), and Installation Management (CEI).