RFP_Attachment_14_Section_L_R02_23Jan19.pdf
PDF 96 KB Posted
- Attached to
- T-38A/B/C Pacer Classic III (PCIII) Phase III & Talon Repair Inspection and Maintenance (TRIM) Program
- Solicitation number
- FA8220-19-R-0001
About this file
This document is a Request for Proposal (RFP) for the T-38A/B/C Pacer Classic III (PCIII) Phase III and Talon Repair Inspection and Maintenance (TRIM) Program. The RFP requires the production of structural parts/kits, fastener parts/kits, and supplemental kits compliant with the PCIII and TRIM technical data packages. Offerors must submit pricing for production kits and first articles for multiple quantity ranges and ordering periods. Fully-burdened labor rates are also required for various labor categories covering the entire period of performance. Proposals are due by the specified date in September 2019, with contract award anticipated for March 2019 and first kit delivery required by May 2021. The Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base will evaluate proposals and make the award.
Section L
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 1
SSP Attachment 3 Section L - Instructions, Conditions, and Notices to Offerors
L-900. INSTRUCTIONS TO OFFERORS
I. Proposal Format
A. General: The following instructions cover the preparation and submittal of the offeror’s proposal for this solicitation. Offerors shall follow the instructions contained herein. Offerors are cautioned that any noncompliance with the terms and conditions of the RFP may cause their proposal to be determined not eligible for award. If a joint venture arrangement exists for this acquisition, the offeror shall provide a copy of the joint venture agreement that is signed and dated by all joint venture members as part of the proposal submission. Offerors shall submit only one proposal for the T-38 Pacer Classic III (PCIII) Phase III and Talon Repair Inspection and Maintenance (TRIM) as the Government will review only one proposal per offeror. Proposals must be received by AFLCMC/WLDK, 6072 Fir Ave Building 1233 Hill AFB, UT 84056, Attn: Russell Walter and Casey Hodson, no later than the date and time specified in Block 9 on the face page of the RFP. However, offerors are requested to submit Volume III, Past Performance Information, so that it is received ten (10) calendar days prior to the required due date for proposals.
Failure to submit Volume III by the earlier date will not result in offeror disqualification.
B. Communications: Exchanges of source selection information between Government and offerors will be controlled by the Contracting Officer. Exchanges of source selection information after submission of the initial proposal packages between the Government and offerors will be controlled by the Contracting Officer. Email may be used to transmit such information only if the email can be sent encrypted, and must include “Source Selection Information – See FAR 2.101 and 3.104” in the subject line of the email. Otherwise, source selection information will be transmitted via direct mailing. In order to facilitate the sending and receiving of encrypted emails, offerors must use MS Outlook email configured to support encryption or a different email product that is S/MIME compatible and configured to support encryption. If you intend to submit your source selection information via encrypted email, you will need to contact the Buyer/Contracting Officer indicated on the face page of the solicitation prior to that first submittal in order to exchange certificates used for encryption. To ensure the process is working correctly, send a test encrypted message first (without including any source selection information). Otherwise, source selection information will be transmitted via direct mail or AMRDEC SAFE at https://safe.amrdec.army.mil/safe/guide.aspx.When submitting source selection information via email, file suppression utilities, to include but not limited to zip files, will not be accepted.
II. Volume Organization
A. General: Proposals shall be submitted to the Government in four (4) separate volumes as set forth below:
Table 1 - Proposal Organization
VOLUME VOLUME
TITLE
HARD
COPIES
ELECTRONIC
COPIES PAGE LIMIT
I Completed RFP (Cross Reference Matrix)**
II Written Technical** 4 2 50
III Past Performance** 2 2 20
IV Price** 2
2 None* https://safe.amrdec.army.mil/safe/guide.aspx
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 2
* Identification of deviations (if any) from the offeror’s standard estimating procedures for this acquisition shall not exceed one page. A summary of all significant pricing assumptions, scope limitations and qualifications shall not exceed five pages.
**Completed RFP, Written Technical, Past Performance, and Price proposals shall be submitted in written form (number of copies are identified in Table 1) and CD-R or DVD-R (write once/read only) (number of copies are identified in Table 1) that is “closed” so that no further writes can be made to the media. CD-R/W or DVD-R/W media types are not acceptable. Media must be virus scanned by the offeror prior to submitting to the Government.
Offerors shall use the instructions set forth in RFP Attachment 1, Past Performance Information (PPI) Instructions for Offerors, to electronically submit the Past Performance information into the PPI Tool. The link to the PPI Tool is attached, as a link, to the solicitation posting.
In addition to the page limitations set forth above, proposal volumes shall comply with the following format:
1. The sealed package used to submit the proposal package must show the time and date specified for receipt. Each volume shall be marked with the RFP number and the offeror’s name and address, and the number of the Volume, i.e.
I, II, III, etc. Proposals shall be in the English language and all monies shall be proposed in United States dollars.
2. Print shall be no smaller than a font size of 10. Paper size shall be 8 1/2” x 11,” excluding any drawings, diagrams, and/or supporting illustrations, spreadsheets, etc. Charts, graphs, drawings, diagrams, supporting illustrations, or spreadsheets shall not be greater than 11” x 17.” Each volume within the proposal notebook shall be separately tabbed and identified. Margins shall be no smaller than 1 inch and each page within a volume shall be numbered consecutively. Elaborate formats, bindings, and color presentations are not desired or required.
3. The page limitation for Volume II, Written Technical Proposal, is 50 pages. The page limitation for Volume III, Past Performance is 20 pages. The page limitation for Volume IV, Cost/Price Proposal is unlimited pages. The page limitations include any charts, graphs, drawings, diagrams, supporting illustrations, spreadsheets, etc., but excludes any table of contents or list of acronyms (if utilized). Any deviations from the identified page limitations, will only be allowed if it has been specifically identified/approved within this document. In paragraph II C 3.3.1, the draft Integrated Master Schedule (IMS) will not be counted towards the page limitations. In paragraph II D 7, the Past Performance Information Sheet is limited to 6 pages total for each submission, however it will not be counted towards the page limitations. Offerors are cautioned that any pages that exceed the page limitations shall not be read but shall be removed and either retained in the contract file without being considered in the evaluation, or, sent back to the offeror.
4. Page limitations may be placed on responses to Evaluation Notices (ENs), if issued. The specified page limits for EN responses will be identified in the letters forwarding the ENs to offerors or on the EN form itself.
5. Each page containing proprietary information should be so marked.
6. Each page should contain the following legend at the bottom of each sheet:
SOURCE SELECTION INFORMATION--SEE FAR 2.101 and 3.104
FOR OFFICIAL USE ONLY
7. Submission of the initial proposal packages via electronic mail will not be accepted. Initial proposal packages shall either be mailed or hand-delivered. Offerors are cautioned that Hill Air Force Base has visitor control procedures requiring individuals not affiliated with the installation to obtain a visitor pass prior to entrance. Some delay should be anticipated when hand-delivering proposal packages. Offerors should allow for sufficient time to obtain a visitor pass and arrive at the specified office PRIOR to the time specified for receipt of proposals.
8. Classified Information: Do not provide classified material.
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 3
B. Volume I, Completed RFP
1. General: Volume I, Completed RFP (reference Table 1) shall consist of the completed and signed RFP, to include any amendments issued, with a cover letter delineating any exceptions taken to the RFP terms and conditions with accompanying rationale. However, offerors are cautioned that any noncompliance with the terms and conditions of the RFP may cause their proposal to be determined not eligible for award. Offerors shall ensure that all clauses and provisions that require “fill-in” information are appropriately completed, including the proposed prices associated with the contract line items in the Schedule of the RFP.
2. Cross Reference Matrix: The offeror shall fill out the cross reference matrix at RFP Attachment 7 indicating where in their proposal the information can be found as it relates to the RFP. The cross reference matrix will be utilized as a tool to show critical interrelationships and dependencies among the technical requirements documents:
the Statement of Work (SOW), the Contract Line Item Number (CLIN), the Contract Data Requirements List (CDRL), Section L (Instructions to Offerors), and Section M (Evaluation Basis for Award). The cross reference matrix will help an offeror ensure it has responded to all the evaluation criteria and proposal submittal requirements identified in the solicitation. If the matrix conflicts with any other requirement, direction, or provision of this solicitation, the other reference shall take precedence over the matrix. Additionally, to the extent the matrix discloses details as to the manner by which the Government intends to evaluate the offeror’s proposals for award, Section M references in the matrix are for informational purposes only, and the Government shall be obligated to evaluate proposals solely in conformance with Section M of the solicitation.
C. Volume II, Written Technical Proposal
1. General: The written technical proposal shall be clear, concise, and include all the information required by this provision in sufficient detail for effective evaluation. The proposal should not simply rephrase or restate the Government’s requirements, but rather shall provide convincing rationale to address how the offeror intends to meet these requirements. Offerors shall assume the Government has no prior knowledge of their capabilities, work processes, facilities, and experience and will base its evaluation on the information presented in the offeror’s technical proposal.
2. Format and Specific Content: The following information shall be provided in the written technical proposal and will be evaluated to assess the proposed technical approach in accordance with Section M-900, Evaluation Basis for Award. The written technical proposal shall address each of the following subfactors to describe the offeror’s proposed approach to performing the requirements set forth in the Statement of Work (SOW) and Technical Data Packages (TDP).
3. Technical Factor
3.1 Subfactor A: Parts Manufacturing and Procurement Plan
3.1.1 The proposed approach shall demonstrate the offeror’s ability to produce structural parts/kits and fastener parts/kits compliant with the PCIII and TRIM TDPs. The proposal shall include a detailed description of facilities, equipment, existing and planned manufacturing tooling, and how each pertains to the processes associated with the manufacturing and integration of PCIII and TRIM structural parts/kits and fastener parts/kits. The offeror’s proposal shall include sources for all required forgings and extruded parts in the TDP. The Offeror’s proposal shall include sources for all items in the Bill of Material. The Offeror shall list the items which do not have a source, and provide a plan to obtain an alternate part and source, and why the Offeror deems the alternate part and source as suitable.
3.1.2 For the parts listed in Table 2, the offeror shall provide a more detailed manufacturing plan to include:
a. Obtain required materials with applicable material certifications
b. Design/build/obtain specialized tooling to aid in manufacturing of parts
c. Machine parts
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 4
d. Form/contour/manipulate large and small extrusions and unformed stock
e. Post process (i.e. heat treat, peen, anodize, plate, coat)
f. Apply metrology and inspection for dimensional conformity
g. Perform nondestructive testing
Table 2 - Evaluated Components
Part Number Nomenclature 2-11756-523/-524 Bulkhead Assembly at FS 388.75 3-11493 -1/-2 Dorsal Shim 3-11613-19 Upper Skin, FS 445.00 to 531.00 40S101-100 Tapered Shim 2-11668-5 Bolt
3.2 Subfactor B: Drawing Interpretation
3.2.1 Using the 3-11611 drawing and associated dimension data for the CFS 505.075 Former Assembly, P/N 3-11611-503, the offeror shall provide a narrative with illustrations to demonstrate the ability to correctly determine the following characteristics:
3.2.1.1 In the plane of the CFS 505.075 and below the Horizontal Reference Plane (HRP), what is the distance between the trace of the Firewall Moldline on CFS 505.075 and the Fuselage Moldline at a distance of 12.5 inches outboard of the airplane centerline?
3.2.1.2 Determine the number of cooling holes, the corresponding diameter, and their locations above the Horizontal Reference Line (HRL) in the 3-11611-31/-32 Formers for this assembly configuration.
3.2.2 The offeror shall provide a narrative with illustrations to demonstrate the ability to correctly interpret drawing 3-11805 located in the PCIII TDP. The technical proposal shall:
3.2.2.1 Provide the configuration to be produced and identification of the components of the 3-
11805-49 assembly
3.2.2.2 Provide the dimension (in inches) from the bottom edge of the doubler to the Horizontal Reference Line
3.2.3 The offeror shall provide a narrative with illustrations to demonstrate the ability to correctly interpret drawing 3-11613 located in the TRIM TDP. The technical proposal shall:
3.2.3.1 List all of the final skin thicknesses required to make the -19 configuration.
3.2.3.2 Identify number and location of all cutouts (including circular) and provide dimensions for each on the -19 configuration.
3.2.4 Using the 2-11668 drawing and associated specifications. Please identify and explain how the answer was determined for the following:
3.2.4.1 What is the minimum allowable distance from the forging flow lines between the intersection of the longitudinal axis of the bolt and the approximate transverse axis of the flow lines to the bearing surface of the bolt?
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 5
3.2.4.2 What is the minimum number of fatigue cycles that should be conducted in the fatigue test for a passing condition?
3.2.4.3 For a lot or batch size of 30, what is the required number of samples for fatigue testing?
3.3 Subfactor C: Program Management
The offeror shall provide its supply chain management approach, risk management approach and a description of its logistical capacity for obtaining modification components. The technical proposal shall include:
3.3.1 Resource Management
The prime contractor’s organizational structure which identifies key personnel. The proposal shall clearly document the primary roles and lines of responsibility, and technical interface with subject matter experts. The proposal shall illustrate all planned subcontractor relationships to include name and Commercial, and Government Entity (CAGE) code with a letter of intent between prime and subcontractor agreeing to be on contract within 90 days after contract award.
The proposal shall include a draft Integrated Master Schedule (IMS) that details the offeror’s proposed process for material purchase (to include long lead items), first article production (manufacture, inspection, and testing) and a manufacturing plan to meet full-rate production. A detailed IMS depicting program execution from contract award to completion of all deliverables. The IMS shall address lead times for the delivery of First Article Test components and subsequent production kits. Include PCIII, TRIM, and Fastener Kits. Assume a contract award of March 2019 with a need date of the first kit(s) of May 2021. First Article Testing takes between 30 to 120 days.
The kit(s) must be FAT approved and ready 60 days prior to need date to allow for transportation.
3.3.2 Subcontractor Management
A clear and feasible approach to managing all subcontractors, partners, and sub-tier subcontractors/partners to meet quality system requirements, as well as supply chain partners and the process in which these partners are evaluated and selected. This includes supplier’s commitments to adequately demonstrate their ability to achieve Government desired full rate production.
3.3.3 Risk Management
A complete description of risk management processes, explaining the criteria, methods, and procedures that would be used to identify the critical items associated with the implementation of this contract.
D. Volume III, Past Performance
1. General: Offerors must use the Past Performance Information (PPI) Tool (Use the latest version from https://www.fbo.gov) in order to electronically submit the PPI portion of the Past Performance Volume. Offerors shall submit present and past performance information for itself and any joint venture member, as well as each proposed critical subcontractor in accordance with the format contained in the “Past Performance Information Instructions” (See RFP Attachment 1) and the following paragraphs. A critical subcontractor is defined as an entity (subcontractor and/or teaming contractor), other than the offeror itself that will perform at least 20% of the manufacturing and/or assembly work by part quantity or weight. Offerors are cautioned that the Government will use data provided by each offeror in this volume and data obtained from other sources in the evaluation of past performance.
2. Past Performance Format: The requested present and past performance information shall be provided in a separate volume (i.e., 3-ring binder) labeled "Volume III - Past Performance". A summary page shall be provided for this acquisition, describing the proposed role of the offeror, any joint venture member and critical subcontractor (nature of work and percentage of overall work). The summary page does not count toward the page limit. Summary page information must clearly communicate that proposed critical subcontractor(s) meet the definition of a critical subcontractor established above. Efforts submitted for proposed critical subcontractors not meeting the established definition will not be evaluated. Each offeror/joint venture member shall complete a separate Past Performance Information Sheet (See RFP Attachment 2) for three (3) active or completed contracts (with at least one year of https://www.fbo.gov/
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 6 performance history) in the past five (5) years from the issuance date of the RFP, that the offeror/joint venture member considers relevant in demonstrating its ability to perform the proposed effort. If the total number of such contracts exceeds three (3), each offeror/joint venture member shall address its three (3) most recent and relevant contracts. For each critical subcontractor included in the offeror's proposal, a Past Performance Information Sheet for three (3) of their most recent and relevant contracts shall also be included. The offeror's/joint venture member’s or critical subcontractor’s present and past performance information may include data on efforts performed by other predecessor companies, affiliates, other divisions or corporate management if such was provided for evaluation and if the offeror’s past performance volume demonstrates the company, affiliate, or division will provide the offeror with resources for the instant proposed effort, such as workforce, management, facilities, or other capabilities demonstrating direct and meaningful involvement in the performance of the instant proposed effort. The Past Performance Information Sheet (and PPI Tool) shall clearly indicate the division or corporate organization that performed or is presently performing the contract. Contracts listed may include those with the Federal Government, state and local governments or their agencies, and commercial customers.
3. Ordering Type Contracts Submission: If the contract you are submitting is an ordering type contractual vehicle (for example, including but not limited to an Indefinite Delivery “D” type contract per FAR 16.5), only after issuance of a delivery/task order does performance occur. Given this, an individual order (or series of orders) under the basic ordering contract shall be submitted, in lieu of just the basic ordering contract itself. All information provided to the Government, for an ordering type contractual vehicle, shall be at the order level (i.e. a delivery/task order). When determining what order (or series of orders) to submit for evaluation, please reference Section M, Paragraph II.D for details on how the Government will evaluate each submitted effort for recency, relevancy, and quality. In order to achieve optimal programmatic/logistical scope and magnitude of effort and complexities, as described in Section M paragraph II.D.4 Note and paragraph 4.1, the offeror should consider submitting a series of orders, if possible.
However, a series of orders should only be submitted if the series of orders is for continuous technical scope demonstrating relevancy to the instant acquisition. Not all ordering type contractual vehicles will have series of orders that meet this criteria. In this instance, only the single order demonstrating relevant technical scope should be submitted for evaluation.
When submitting an individual order (or series of orders) under an ordering type contractual vehicle, it is important that the offeror’s past performance information be accurate, complete, and in the correct format. If the information is not submitted in the correct format, the Government will not be able to evaluate the effort for recency, relevancy, and quality. There are specific places for submission of this information in the Past Performance Information Sheet RFP Attachment 2. Please ensure the information submitted, in the Past Performance Information Sheet RFP Attachment 2, is for each order (or series of orders), in lieu of just the basic ordering contract itself. This includes but is not limited to information such as the estimated total dollar value, period of performance, quantity produced/managed, and complexity/type of data deliverables, for each order or series of orders. See paragraph 3.1 for further information on how to submit series of orders.
3.1 Series of Orders: When submitting a series of orders for evaluation, the offeror should list the orders under the basic ordering type contractual vehicle that demonstrate relevancy, as defined in the Relevancy Definitions in Section M paragraph II.D.4. Per the Note in Section M paragraph II.D.4, Relevancy consists of not only technical complexities, but programmatic/logistical considerations. The programmatic/logistical considerations include but are not limited to information such as the estimated total dollar value, period of performance, quantity produced/managed, and complexity/type of data deliverables If an offeror submits a series of orders for evaluation, the total dollar value of each order (in the series of orders), the period of performance dates of each order (in the series of orders), the total quantity produced on each order (in the series of orders) and the type and complexity of data deliverables for each order (in the series of orders) shall be submitted. The total dollar value of each order (in the series of orders) shall be added up to calculate the Total Dollar Value to be used in the evaluation, for the submitted effort. The total period of performance of each order (in the series of orders) shall be added up to calculate the Total Period of Performance to be used in the evaluation, for the submitted effort. The total quantity produced on each order (in the series of orders) shall be added up to calculate the Total Quantity Produced to be used in the evaluation, for the submitted effort. The type and complexity of data deliverables provided on each order (in the series of orders) shall be evaluated as a whole for the series of orders.
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 7
Caution: All orders within the series of orders, being submitted, should be for the same continuous technical scope demonstrating relevancy to the instant acquisition. The Government reserves the right to request additional information from the offeror or points of contact provided to verify that the series of orders is for the same continuous technical scope.
4. Key Personnel: The evaluation of the offeror’s/joint venture member’s present/past performance WILL NOT include the present/past performance of any key personnel, even though they may perform major or critical aspects of this requirement. Leave this entry on the PPI Tool blank.
5. Subcontractor/Teaming Member Consent Form (See RFP Attachment 3): In addition to the information provided in the Past Performance Information Sheet (RFP Attachment 2) for each entity as required above, the offeror must submit a consent letter executed by each of its proposed teaming member(s) and/or critical subcontractors authorizing release of adverse past performance information to the prime offeror to allow the prime offeror an opportunity to respond. A sample subcontractor/teaming partner consent form is attached to this RFP (see RFP Attachment 3). The consent form shall be completed by the team member(s) and/or critical subcontractors identified in your proposal. The completed consent forms shall be submitted as part of your Past Performance (Volume III).
6. Small Business Compliance in Past Performance Efforts: On the three (3) contracts submitted in Volume III, Past Performance, include relevant information in the Past Performance Information Sheet concerning the offeror’s/joint venture member’s and critical subcontractor’s compliance with FAR 52.219-8, Utilization of Small Business Concerns or FAR 52.219-9, Small Business Subcontracting Plan, if these clauses are or were contained in the contract. (Please note that FAR 52.219-8 does apply to ALL businesses, whereas FAR 52.219-9 only applies to large businesses.) When subcontracting possibilities existed on the contracts submitted by the offeror/joint venture member and critical subcontractor, address whether or not the offeror/joint venture member and critical subcontractor awarded subcontracts to small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns to the fullest extent consistent with efficient contract performance. If none of the submitted contracts included these clauses, whenever subcontracting possibilities existed in the performance of these contracts, address whether or not it was the offeror/joint venture member and critical subcontractor’s policy to utilize small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns to the fullest extent consistent with efficient contract performance.
7. Past Performance Information Sheet (See RFP Attachment 2): The offeror/joint venture member or critical subcontractor, if applicable, shall focus its Past Performance Information Sheet responses so that they clearly correlate present and past performance with the requirements of this RFP. The Past Performance Information Sheet responses must clearly describe the relevance of the effort to the work proposed. Within the Past Performance Information Sheet, offerors/joint venture members or critical subcontractors may mention efforts by subcontractors as long as it is made clear what the subcontractor accomplished independently, what the contractor accomplished independently, what the contractor and subcontractor accomplished together, and whether the subcontractor will be used in the proposed effort. This is in addition to qualifying critical subcontractors for the current effort (as specified in Section L) being able to provide three Past Performance Information Sheet providing past performance data for tasks they will execute under the proposed T-38 PCIII Phase III and TRIM contract. The answering space on the Past Performance Information Sheet may be expanded so that the filled-in Past Performance Information Sheet for each relevant contract covers no more than both sides of three (3) 8 ½ x 11 inch pages (i.e., no more than six (6) pages). Provide the most current information for the Points of Contact (POCs) identified on the Past Performance Information Sheets.
At least two of the following (in descending order of availability) should be identified as current POCs on the Past Performance Information Sheets:
(a) Procuring Contracting Officer/Contract Negotiator or equivalent
(b) Program/Project Manager, or equivalent
(c) Administrative Contracting Officer/Contract Administrator or equivalent
(d) Other (As specified in your Past Performance Information Sheet)
If problems were encountered during the performance of the identified contracts, provide evidence of the ability to isolate the root causes of problems and include in the Past Performance Information Sheet a description of programs
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 8 or actions taken to resolve those causes. Problems not addressed in the Past Performance Information Sheet, but found by the Government during the evaluation of the information in this volume, will be assumed to still exist.
NOTE: In the case of Contractor Performance Assessment Report System (CPARS), if your input has already been provided and the rationale/circumstances have not changed, DO NOT repeat them here.
8. Past Performance Questionnaire: The Present/Past Performance Questionnaire (see RFP Attachment 4) will be one means used by the Government to obtain present/past performance information. The Government reserves the right to change, alter, and/or supplement the questionnaire without further notice to the offeror(s). The offeror shall send out and track the completion of the Present/Past Performance Questionnaires (See RFP Attachment 4) to each of the offeror’s, joint venture members and/or critical subcontractors’ (i.e., each entity’s) Points of Contact (POCs) identified in each Past Performance Information Sheet. The responsibility to send out and track the completion of the Present/Past Performance Questionnaires rests solely with the offeror - i.e., it shall not be delegated to any other entity. Exert your best effort to ensure that at least two POCs per relevant contract submit a completed Present/Past Performance Questionnaire directly to the Government not later than the date established in the RFP for receipt of proposals. POCs may submit their completed Present/Past Performance Questionnaire either electronically, or by mail. If sending electronically, follow the procedures outlined in paragraph I.B. Communications above, and email to: russell.walter.1@us.af.mil, and casey.hodson@us.af.mil. If mailing, the POCs may return the completed questionnaires via mail directly to:
AFLCMC/WLDKA
ATTN: Russell Walter and Casey Hodson 6072 Fir Ave. Building 1233 Hill AFB, UT 84056
If mailing, the outside envelope must be marked as follows:
NOTE: TO BE OPENED BY ADDRESSEE ONLY
The completed questionnaires should be contained in a second envelope marked with the mailing address and the following legend:
SOURCE SELECTION INFORMATION - See FAR 2.101 and 3.104
FOR OFFICIAL USE ONLY
Once the Present/Past Performance Questionnaires are completed by your POCs, the information contained therein shall be considered source selection sensitive and shall not be released to you, the offeror. Therefore, any exchange/contact between the offeror/joint venture member and/or critical subcontractor and its own POCs in regards to comments made on the questionnaire is not permitted.
9. Client Authorization Letter (See RFP Attachment 5): In the event that commercial contracts are presented as present/past performance sources of information, a client authorization letter shall be issued to those commercial POCs requesting/authorizing them to complete a Present/Past Performance Questionnaire. A sample client authorization letter is attached to this RFP (see RFP Attachment 5). The offeror is required to send the client authorization letter(s) with the Present/Past Performance Questionnaire(s) to each POC on commercial contracts. A separate copy of client authorization letter(s) for each commercial contract shall be included in the offeror’s Present/Past Performance submission for the Government’s use in case additional questionnaires need to be sent by the Government after the RFP due date.
10. Follow-up Discussions: The Government may conduct follow-up discussions with any of the people identified in the Past Performance Information Sheets or in the offeror’s Present/Past Performance Volume. Pursuant to FAR 15.305(a)(2)(ii), the Government may obtain other information by sending out additional questionnaires and through other sources, other than those listed within the Past Performance Information Sheets.
11. RFP Attachment Legend: Past Performance Information Sheet and Present/Past Performance Questionnaire must include the following legend at the top and bottom of the page:
SOURCE SELECTION INFORMATION - See FAR 2.101 and 3.104 mailto:russell.walter.1@us.af.mil mailto:casey.hodson@us.af.mil
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 9
FOR OFFICIAL USE ONLY
E. Volume IV, Price Volume Organization: The Price volume shall consist of the following sections:
SECTION 1 - Table of Contents SECTION 2 - Data other than certified cost or pricing data, to include estimating methodology; include a completed copy of the TEP Pricing Matrix (See RFP Attachment 6).
SECTION 3 - List the Price assumptions of the offeror’s proposal, if any. Provide complete rationale for assumptions.
1. General Instructions: The Price Volume shall be submitted using Microsoft Word and/or Excel compatible document/spreadsheets as appropriate. Documents and spreadsheets shall be editable and not password protected.
The offeror shall provide all formulas and calculations used in the respective price documents and spreadsheets.
Data beyond that required by this instruction shall not be submitted, unless you consider it essential to document or support your price position. All data relating to the proposed price, including all required supporting documentation, must be included in the section of the proposal designated as the Price Volume. Under no circumstances shall this data and documentation be included elsewhere in the proposal.
2. Price Criteria: The price evaluation criteria consists of: (1) Price Reasonableness, (2) Balance, and (3) TEP. This section is to assist you in submitting data other than certified cost or pricing data that is required to evaluate the reasonableness, balance, and TEP. Compliance with these requirements is mandatory and failure to comply may result in rejection of your proposal. Offerors shall review Section M criteria to ensure the minimum requirements are met.
2.1 Total Evaluated Price: The TEP will be assessed from the Offeror’s information provided in this volume.
The burden of proof for credibility of proposed prices rests with the Offeror.
2.1.1 Offerors shall input fixed unit prices for Production Kits and First Articles and Production Kits for all quantity ranges and ordering periods identified in the TEP Pricing Matrix IAW the instructions contained therein. Submit a copy of the completed TEP Pricing Matrix in the Price Volume (Volume IV) in Microsoft Excel format (non-PDF).
2.1.2 Offerors shall input fully-burdened labor rates that include all applicable Direct Labor, Fringe, Indirect rates (Overhead, General and Administrative, etc.), Facilities Capital Cost of Money (if applicable), and Profit for the performance of the entire requirement for each of the requested labor categories. A fully-burdened labor rate must be proposed for all labor categories and all years of the contract in accordance with the TEP Pricing Matrix, Labor Rate Worksheet instructions. Each fully-burdened labor rate is a single composite rate for a labor category and will be considered contractually-binding and utilized to price future negotiations, orders, and modifications (upward and downward) for both the prime and the prime’s subcontractors’ direct and indirect labor costs including profit during the contract. The Government’s intent is to utilize these rates primarily in relation to CLIN X056, Supplemental Kits and CLIN X057 Supplemental Kits First Article; however, the Government may opt to utilize these rates for other in-scope modifications/orders. Submit a copy of the completed TEP Pricing Matrix, Labor Rate Worksheet in the Price Volume (Volume IV) in Microsoft Excel format (non-PDF).
2.1.3. The cost of producing data is not separately priced in the TEP of the solicitation.
2.2 Approved Accounting and Purchasing Systems: As portions of this contract will be other-than fixed price, the Offeror must provide evidence of an approved accounting and purchasing system for themselves and any subcontractors who will be issued other-than fixed price subcontracts. The offeror shall indicate whether the accounting or purchasing systems are Government approved and if so, provide evidence of such approval.
Also, identify any deviations from the offeror’s standard procedures in preparing this proposal. In the event
Source Selection Information – See FAR 2.101 and 3.104 – FOR OFFICIAL USE ONLY Page | 10 the offeror does not have an approved system, the offeror shall submit a completed Standard Form (SF) 1408 for a potential pre-award survey. The SF 1408 and instructions to complete the SF 1408 can be found at the following two links:
http://www.dcaa.mil/Preaward_Survey_of_Prospective_Contractor_Accounting_System_Checklist.pdf and http://www.gsa.gov/portal/forms/download/115778
3. Pricing Assumptions: Summarize all significant pricing assumptions, scope limitations, and/or qualifications of the cost proposal. List each exception to the ground rules and assumptions provided in the solicitation and each qualification of the Price Volume, if any. Provide complete rationale for any exceptions. This section shall not exceed five pages.
4. Estimating Techniques and Methods: Estimating methods used in the proposal shall be described in a manner that will show clear traceability into the proposed pricing throughout the Price Volume.
(a) Estimating System.
The offeror shall indicate whether it has a Government approved estimating system and if so, provide evidence of such approval. If the offeror does not have an approved estimating system, the offeror shall provide evidence that it has taken action to obtain approval or re-approval of its estimating system. The offeror shall identify any deviations from standard estimating procedures in preparing the Price Volume.
(b) Purchasing System.
The offeror shall indicate whether it has a Government approved purchasing system and if so, provide evidence of such approval. If the offeror does not have an approved purchasing system, the offeror shall provide evidence that it has taken action to obtain approval or re-approval of its purchasing system. The offeror shall identify any deviations from standard purchasing procedures in preparing the Price Volume.
5. Pricing Information Requirements: In the event that adequate competition does not emerge in response to the solicitation, the PCO may require submission of certified cost and pricing data, and a Certificate of Current Cost or Pricing Data (IAW FAR 15.403-4). IAW FAR 15.403-1(b) and 15.403-3(a), information other than certified cost or pricing data may be required to support price reasonableness. If, after receipt of proposals, the PCO determines that there is insufficient information available to determine price reasonableness the Offeror shall be required to submit information other than certified cost or pricing data; if none of the exceptions in FAR 15.403-1 apply, the Offerors may be required to submit certified cost or pricing data. Information shall be provided in format that is IAW FAR 15.403-5.
http://www.dcaa.mil/Preaward_Survey_of_Prospective_Contractor_Accounting_System_Checklist.pdf http://www.gsa.gov/portal/forms/download/115778
| SSP Attachment 3 |
| L-900. INSTRUCTIONS TO OFFERORS |
| 1. General: Volume I, Completed RFP (reference Table 1) shall consist of the completed and signed RFP, to include any amendments issued, with a cover letter delineating any exceptions taken to the RFP terms and conditions with accompanying rationale. ... |
| 2. Cross Reference Matrix: The offeror shall fill out the cross reference matrix at RFP Attachment 7 indicating where in their proposal the information can be found as it relates to the RFP. The cross reference matrix will be utilized as a tool to sh... |