Question-Answers_Complete__3_to_FBO_15_Feb_13_69_-_81_CE_Res.doc

DOC document 49 KB Posted

Attached to
Protective Coating/Paint
Solicitation number
FA8101-12-R-0009
Issued by

About this file

Government Responses

View the file

Other files

File Type Posted
Question-Answers__5_to_FBOcomplete21_Mar_13_84-88_thru.doc.docx DOCX document
fa8101-12-r-0009-0004_amend.pdf PDF
PROTECTIVE_COATING_BID_SCHEDULE_REVISED_13_Mar_13.xls XLS spreadsheet
FA8101-12-R-0009-0003.pdf PDF
FA8101-12-R-0009_solicitation_final.pdf PDF
3rd_amendment_paint_IDIQ.doc DOC document
Amendment_1.doc DOC document
B-1086_Paint_Exterior_SOW_26_Feb_13_(2).pdf PDF
PROTECTIVE_COATING_BID_SCHEDULE_REVISED_26_FEB_13.xls XLS spreadsheet
Prot_Coat_SOW_Rev_26_Feb_13.pdf PDF
Bid_Schedule_to_Paint_Ext_B1086_Seed_Project.pdf PDF
Question-Answers__4_Complete_to_FBO_14Feb__13_-19_feb_13_82__-_83_thru_____.doc DOC document
Ques-Ans_complete__2_to_FBO_30_Jan_13_6Feb_thru_68_CE_Res_complete_.doc DOC document
Question-Answers__1_to_FBO_29_Jan_13_final.doc DOC document
B-1086_Paint_Exterior_SOW.doc DOC document
00_70_00_dated_07_11.pdf PDF
ITO_ATTACHMENT_1.4_SAMPLE_CONSENT_LETTER.doc DOC document
00_71_00_dtd_07_11.pdf PDF
ITO_ATTACHMENT_1.2_PAST_PERFORMANCE_QUESTIONNAIRE.doc DOC document
Wage_Determination_OK120080.mht MHT file
Section_M.doc DOC document
ITO_ATTACHMENT_2.0_PROPOSED_TEAM_LIST.doc DOC document
ITO_ATTACHMENT_1.1_PAST_AND_PRESENT_PERFORMANCE_INFORMATION_SHEET.doc DOC document
Protective_Coating_SOW_14_Aug_12_(2).doc DOC document
Solicitation.doc DOC document
00_72_00_dtd_07_11.pdf PDF
Section_L_27_jun_2012.doc DOC document
EXHIBITS_A-E._BID_SCHEDULE.xls XLS spreadsheet
DD_254.pdf PDF
ITO_ATTACHMENT_1.3_SAMPLE_QUESTIONNAIRE_COVER_LETTER.doc DOC document
01_33_00_Submittal_Procedures_16_Feb_12.pdf PDF
ITO_ATTACHMENT_1.5_SAMPLE_CLIENT_AUTHORIZATION_LETTER.doc DOC document
AF_66_Submittals_for_Protective_Coating__26_Jul_12.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question/Answers #3 (69-81) 20 Feb 2013 The questions and answers below comprise all questions submitted by contractors from 6 Feb 13 through 15 Feb 13. If there is a question that isn’t included in this document and was submitted, please contact both Sharla Brandon at sharla.flowers-brandon@tinker.af.mil and lori.fixico@tinker.af.mil

RFI #

Subject Question/Answer

69
Proposal
On the schedule of material submittals it states the following should be awarded by contract award date:

Storm Water Pollution Prevention Plan

Spray Painting Plan

Material Safety Data Sheet

Affirmative Procurement Documentation

Material Specification Sheets and Material Safety Data Sheets.

What section do these need to go in? Are they considered in the page limitations? It does not specify them in Section L.

Do we need to turn in all possible MSDS sheets on materials that would be used throughout the life of the contract?

Yes, please see SOW, Section 01000, paragraph 1.9.2

70
Technical
In the specifications state that a schedule shall be submitted? Is this for after award on a DO or before award for the seed project?

For each DO, (See SOW, Section 01000, paragraph 1.4.1)

71
Technical
In the SOW says the contractor shall submit work plans, samples, brochures, manufacturer’s data, shop drawings and/ or certificates of materials. Is this required for a DO or before the award?

For each DO, (See SOW, Section 01000, paragraph 1.9.1) This requirement is delivery order specific and will be determined at that time. Submittal procedures will be used for approval of material, etc.

Technical
In the SOW section 1.5 submittals are these required for a DO or before the award?

Submittals are required at time of award and for DO (IAW project specifications). See SOW, Section 01000, paragraphs 1.9.1- 1.9.3

73
Technical
Section 1.5 qualifications says to submit documentation certifying for equipment operations and handling of chemicals.

IAW SOW, Section 03200, Paragraph 1.5.1, documentation is required on personnel’s experience. Please submit a more detailed question

74
Technical
Will drawings and as builts be added to each delivery order as needed since it is not on the bid schedule. It is listed in section 00 70 00 para 1.3.15

Drawings and as builts are not applicable to the protective coating acquisition. While Sections 00 70 00, 00 71 00 and 00 72 00 of the SOW are required to be included on all construction acquisitions, not all requirements are applicable to the protective coating acquisition.

75
Technical
Will drawings and as builts be added to each delivery order as needed since it is not on the bid schedule. It is listed in section 00 70 00 para 1.3.15

See RFI #74

76
Technical/Contracting
In section 2.5 and2.6 of Section L it states that each volume must be bound separate and a separate electronic copy is to be submitted. I do not see the number of copies we are to submit.

Also, it says that it is to be mailed in section 2.7. Will we be able to hand carry it to the visitor center on the response day?

See Paragraph 2.3.3 (Table 2.3) for number of copies

77
Contracting
Looking at the Protective coating solicitation I was wondering if an 8(a) for Chicago Il can bid? I do not see anywhere in the solicitation or amendments that addresses this.

This requirement is an Oklahoma region 8(a) set aside. An option for out of state and out of region entities that do not meet the requirements could be joint venture, mentorship, or performing as a subcontractor, to name a few

78
Technical/Contracting
When will the sign-in sheet and Q&A answers be published to FBO?

All questions and answers are being posted as received from the technical team.

79
Technical
The bid schedules indicate the prices should include Labor and Material unless noted otherwise. Is it the governments intention, the unit price should also include the Equipment costs such as man lifts, air compressors, air dryers, dehumidification, generators, paint pumps, etc. associated with performing that type of work? For instance, during the job walk, it was discussed that one of the projects would involve abrasive blasting and painting of an elevated water tower. What provisions are there for inclusion of the other costs such as scaffolding, containment, equipment, etc. to perform a task order such as this and others when the hourly rate for abrasive blasting and painting are significantly different that abrasive blasting and painting

The unit price shall include all labor, materials and equipment for normal every day painting. If specialized equipment is needed for an individual delivery order, then the equipment shall be negotiated for the individual delivery order.

80
Technical
On the bid schedule the quantities could influence your unit price. For instance if you are texturing a 5,954 sq ft area your unit price would be lower than texturing a 20 sq ft area. But to take that unit price to texture a patch of 6 sq ft would not be realistic. This could be for numerous items, like texturing exterior, painting fences, walls, etc for the low sq ft price given you would not be charging enough for only a small portion. The set up time, driving time, buying materials (you will not be able to buy $2 worth of paint) etc would be the same for a small patch or painting a short area of fence as painting a large area, where you can lower your unit price. How do we justify small patches of work vs a large portion of work for the same unit price.

"Unit price for texturing $0.XX 5954=XXXX For a patch $0.XXx6 sq ft= $XXX is very unrealistic.

Float walls 10421 sq ft x .XX= $XXXX Float a patch $.XXx 6 sq ft= XXX Paint plaster for 14,847 sq ft x .XX=$XXX Paint patch 6 sq ft x .XX= $XXXX, also unrealistic.

So to tape and bedd and finish and paint a patch you would get $XXXX. Which is not reasonable. "

Maybe a patch should be all inclusive, like remove patch, install new gypsum board, tape, bedd, texture and paint to match. So we could price you for a true patch job.

Please do not post the pricing example to the Internet. Please remove the numbers before posting to FBO.

Bid Schedule will not change

81
Technical
Was the bid schedule used in the past on the last Paint IDIQ? No

In our paint price should caulking, taping off, masking, catching water to meet EPA requirements, cleaning up area from paint chips, should it all be inclusive in the unit price.

There are no line items to prep work and misc items. See CLINs A001 and A0003