00_72_00_dtd_07_11.pdf

PDF 1 MB Posted

Attached to
Protective Coating/Paint Federal contract opportunity
Solicitation number
FA8101-12-R-0009
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

About this file

Section 00 72 00 Environmental Requirements

View the file

Other files for this federal contract opportunity

Other files attached to Protective Coating/Paint, newest first.
File Type Posted
Question-Answers__5_to_FBOcomplete21_Mar_13_84-88_thru.doc.docx DOCX document
fa8101-12-r-0009-0004_amend.pdf PDF
PROTECTIVE_COATING_BID_SCHEDULE_REVISED_13_Mar_13.xls XLS spreadsheet
FA8101-12-R-0009-0003.pdf PDF
FA8101-12-R-0009_solicitation_final.pdf PDF
3rd_amendment_paint_IDIQ.doc DOC document
Amendment_1.doc DOC document
B-1086_Paint_Exterior_SOW_26_Feb_13_(2).pdf PDF
PROTECTIVE_COATING_BID_SCHEDULE_REVISED_26_FEB_13.xls XLS spreadsheet
Prot_Coat_SOW_Rev_26_Feb_13.pdf PDF
Bid_Schedule_to_Paint_Ext_B1086_Seed_Project.pdf PDF
Question-Answers_Complete__3_to_FBO_15_Feb_13_69_-_81_CE_Res.doc DOC document
Ques-Ans_complete__2_to_FBO_30_Jan_13_6Feb_thru_68_CE_Res_complete_.doc DOC document
Question-Answers__4_Complete_to_FBO_14Feb__13_-19_feb_13_82__-_83_thru_____.doc DOC document
Question-Answers__1_to_FBO_29_Jan_13_final.doc DOC document
ITO_ATTACHMENT_1.4_SAMPLE_CONSENT_LETTER.doc DOC document
00_71_00_dtd_07_11.pdf PDF
ITO_ATTACHMENT_1.2_PAST_PERFORMANCE_QUESTIONNAIRE.doc DOC document
Wage_Determination_OK120080.mht MHT file
Section_M.doc DOC document
Section_L_27_jun_2012.doc DOC document
00_70_00_dated_07_11.pdf PDF
Protective_Coating_SOW_14_Aug_12_(2).doc DOC document
EXHIBITS_A-E._BID_SCHEDULE.xls XLS spreadsheet
ITO_ATTACHMENT_2.0_PROPOSED_TEAM_LIST.doc DOC document
ITO_ATTACHMENT_1.1_PAST_AND_PRESENT_PERFORMANCE_INFORMATION_SHEET.doc DOC document
Solicitation.doc DOC document
B-1086_Paint_Exterior_SOW.doc DOC document
01_33_00_Submittal_Procedures_16_Feb_12.pdf PDF
DD_254.pdf PDF
AF_66_Submittals_for_Protective_Coating__26_Jul_12.pdf PDF
ITO_ATTACHMENT_1.5_SAMPLE_CLIENT_AUTHORIZATION_LETTER.doc DOC document
ITO_ATTACHMENT_1.3_SAMPLE_QUESTIONNAIRE_COVER_LETTER.doc DOC document
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 72 00

ENVIRONMENTAL REQUIREMENTS FOR CONSTRUCTION ON TINKER AIR FORCE BASE

15 July 11

TABLE OF CONTENTS PAGE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 ENVIRONMENTAL PROTECTION

1.3.1 Applicable Regulations

1.3.2 Protection of Land Resources

1.3.3 Protection of Water Resources

1.3.3.1 Erosion Control

1.3.3.2 Storm Water Quality Control

1.3.3.3 Spillage

1.3.3.4 Disposal

1.3.3.5 Flushing & Sampling Req. for Potable Water System

1.3.3.6 Water System Construction Permits

1.3.4 Protection of Fish and Wildlife

1.3.5 Disposal of Removed Material

1.3.6 Dust Control

1.3.7 Maintenance of Pollution Control Facilities During

Construction

1.3.8 Pesticides (Insecticides, Fungicides, Herbicides, Etc)

1.3.9 Affirmative Procurement

1.4 HAZARDOUS MATERIAL REPORTING

1.5 ASBESTOS ABATEMENT

1.6 LEAD-BASED PAINT ABATEMENT

1.7 PCB FILLED BALLAST TRANSFORMER & UNIVERSAL WASTE LAMP ABATEMENT

1.8 SPRAY FINISHING

1.9 ENVIRONMENTAL MANAGEMENT SYSTEM AWARENESS TRAINING

1.10 UNEXPECTED DISCOVERIES OF ARCHEOLOGICAL RESOURCES

1.10 UNEXPECTED DISCOVERIES OF ARCHEOLOGICAL RESOURCES

1.11 USING RADIOACTIVE MATERIALS

1.12 LIST OF ATTACHMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

ATTACHMENTS

Attachment 1 - Bacteriological Sampling Requirements Attachment 2 - Tinker AFB Asbestos Abatement Specification Attachment 3 - Tinker AFB Lead-Based Paint Abatement Specification Attachment 3a - Tinker AFB Lead-Based Paint Abatement Specification for

Industrial Facilities Attachment 4 - Tinker AFB PCB Filled Ballast & Universal Waste Lamp

Abatement Specification Attachment 5 - Tinker AFB Construction & Demolition Debris Management

Procedure Attachment 6 - Tinker AFB Hazardous Waste Management Procedures Attachment 7 – Monthly Hazardous Material Usage Report Attachment 8 - Recovered Material Determination Form Attachment 9 – Environmental Management System Awareness Training

Attachment 10 - Integrated Cultural Resource Management Plan (2005), Section E.13 – Unexpected Discoveries of Archeological Materials During Construction Projects

Attachment 11 – Tree Protection Requirements

SECTION 00 72 00

GENERAL ENVIRONMENTAL REQUIREMENTS FOR CONSTRUCTION ON TINKER AIR FORCE BASE

15 July 11

PART 1 GENERAL

1.1 REFERENCES

The current editions of the publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

CODE OF FEDERAL REGULATIONS (CFR)

CFR 29 1910.94 Ventilation

CFR 29 1910.1000 Air Contaminants

CFR 29 1910.107 Spray Finishing Using Flammable and

Combustible Materials

CFR 40 82 Protection of Stratospheric Ozone

CFR 40 112 Oil Pollution Prevention

CFR 40 247 Comprehensive Procurement Guideline for

Products Containing Recovered Material

CFR 40 280 Regulations Pertaining to Underground Storage

Tanks

OKLAHOMA ADMINISTRATIVE CODE

OAC 252 626 Public Water Supply Construction Standards

OAC 165 25 General Requirements for Underground Storage

Tanks

OAC 165 26 Requirements for Aboveground Storage Tank

Systems

DEPARTMENT OF THE AIR FORCE INSTRUCTION (AFI)

AFI 32 7086 Hazardous Material Management Program

AFI 91 301 Air Force Occupational & Environmental

Safety, Fire Protection, and Health (AFOSH) Program

AFI 32-7064 Integrated Natural Resources Management

AFI 40-201 Managing Radioactive Materials in the US Air Force

OKLAHOMA CITY AIR LOGISTICS CENTER – TINKER AFB (OC-ALC-TAFB)

OC-ALC-TAFBI 32-7001 Hazardous Material Management Program

OC-ALC-TAFBI 32-7004 Hazardous Waste Management Instruction

OC-ALC-TAFBI 32-7006 Secondary Containment Requirements

OC-ALC-TAFBI 48-104 Hazard Communication Program

OC-ALC-TAFBI 13-201 Flight and Ground Operations

EXECUTIVE ORDERS

EO 13101 Greening of the Government Through Waste

Prevention, Recycling, and Federal Acquisition

EO 13148 Greening the Government through Leadership in Environmental Management EO 13514 Federal Leadership in Environmental, Energy, and Economic Performance EO 11514 Protection and Enhancement of Environmental Quality

U. S. ARMY CORPS OF ENGINEERS (COE)

FAR 52.223-9 Estimate of Percentage of Recovered Material

For EPA Guideline Items to be used in the Performance of the Contract

FAR 52.223-4 “Recovered Material Certification” Provision

U. S. Environmental Protection Agency

US EPA’S CPG & RMANS EPA’s Comprehensive Procurement Guideline and

Federal Register Recovered Materials Advisory Notices (located at www.epa.gov/cpg)

1.2 SUBMITTALS

Government approval is required for all submittals. The following, as applicable, shall be submitted in accordance with Section 01330, SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Storm Water Pollution Prevention Water System Construction Permits Chemical/Hazardous Material Request/Authorization (AF Form 3952) Spray Painting Plan Construction Debris Analysis Plan Tree Protection Plan Tree Planting/Removal Permit

SD-07 Certificates http://www.epa.gov/cpg�

Monthly Hazardous Material Usage Report

If no hazardous materials were used during the preceding month, the contractor will indicate as such by entering “NONE” in the appropriate space on the report(s).

Refrigerant Technical Certifications

Prior to installation or recovery of refrigerants to or from contracted equipment, the Contractor shall submit: 1) a copy of the refrigerant technician’s certification as required by 40 CFR (Code of Federal Regulations) part 82, subpart F; and 2) a copy of the certification to the EPA that the Contractor acquired recovery equipment per 40 CFR 82.162.

Refrigerant Installations

Contractor shall submit a record of the amount of refrigerant installed with the contracted equipment or recovered from equipment contracted for demolition into government furnished containers. In the case of commissioning new or retrofitted equipment, the Contractor shall provide the refrigerant amount determined to be the “Full Charge” as defined in 40 CFR 82.152. Provide information concerning refrigerant losses to the atmosphere, including that associated with warranty work.

SD-08 Manufacturer’s Instructions

Material Safety Data

SD-11 Closeout Submittals

Notice of Termination for Storm Water Discharges, DEQ Form 640-572

1.3 ENVIRONMENTAL PROTECTION

For the purpose of this specification, Environmental Pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to man; or degrade the utility of the environment for aesthetic and recreational purposes. The control of environmental pollution requires consideration of air, water, and land, and involves noise, solid waste management and management of radiant energy and radioactive materials, as well as other pollutants.

1.3.1 Applicable Regulations

In order to prevent, and to provide for abatement and control of, any environmental pollution arising from the construction activities of the Contractor and his Subcontractors in the performance of this contract, they shall comply with all applicable Federal, State and Local laws and regulations concerning environmental pollution control and abatement.

1.3.2 Protection of Land Resources

It is intended that the land resources within the project boundaries and outside the limits of permanent work performed under this contract be preserved in their present condition, or be restored to a condition, after completion of construction, that shall appear to be natural and not detract from the appearance of the project. Insofar as possible, the Contractor shall confine his construction activities to areas defined by the plans or specifications, to areas to be cleared for other operations, or to quarry, borrow or waste areas indicated on the plans. This shall be accomplished by installing construction barrier fencing at the limits of construction for the duration of the contract. At the onset of borrow excavation, topsoil shall be saved for use in restoring the borrow area. Waste and borrow areas shall be leveled or trimmed to regular lines and shaped to provide a neat appearance. In all instances, the restored shall be well drained, to prevent the accumulation of stagnant water. All activities potentially impacting tree resources including root zones shall be accomplished in accordance with Attachment 8 (Tree Protection Requirements). Except in areas marked on the plans to be cleared, the Contractor shall not deface, injure, or destroy trees or shrubs, nor remove or cut them without approval of the Contracting Officer. Any trees, shrubs, grass areas, flower gardens, etc, scarred or damaged by the Contractor’s equipment or operations shall be restored to the original condition at the Contractor’s expense. The Contracting Officer will determine whether damaged trees/shrubs will be removed and replaced or treated and healed. The Contractor will submit to the Contracting Officer for approval, a restoration plan showing how the damaged area(s) will be returned to their original condition. The Contractor will be responsible for all erosion control required until the area is accepted by the Contracting Officer as being returned to its original condition. In fall, winter, and early spring months, approved cool-season annual grasses may be established as a temporary ground cover for erosion control. However, permanent native warm-season grasses shall be established prior to contract completion. All grasses must be native and comply with the base Natural Resources Management Plan, unless waived by the Contracting Officer.

1.3.3 Protection of Water Resources

The Contractor shall not pollute streams, lakes, or reservoirs with fuels, oils, bitumen’s, calcium chloride, chlorinated potable water, acids or harmful materials. It is the responsibility of the Contractor to investigate and comply with all applicable Federal, State, County, and Municipal laws concerning pollution of rivers and streams. All work under this contract shall be performed in such a manner that objectionable conditions shall not be created in streams through or adjacent to the project areas.

1.3.3.1 Erosion Control

Surface drainage from cuts and fills within the construction limits, whether or not completed, and from borrow and waste disposal areas, shall, if turbidity producing materials are present, be held in suitable sedimentation ponds; otherwise the surface shall be graded to control erosion within the construction site. Temporary erosion and sediment control measures such as berms, dikes, drains, or sedimentation basins, if required to meet the above standards, shall be provided and maintained until permanent drainage and erosion control facilities are completed and operative. The area of bare soil exposed at any one time by construction operations shall be held to a minimum. Stream crossings by fording with equipment shall be limited to control turbidity, and in areas of frequent crossings, temporary culverts or bridge structures shall be installed before the need arises, and then removed upon completion of the project. Fills and waste areas shall be constructed by selective placement to eliminate silts or clays on the surface that will erode and contaminate adjacent streams. The Contractor shall be required to contain all eroded soil, silt, sand, or other debris on the construction site. When necessary a containment area shall be constructed on the project site to prevent eroded soils or debris from entering storm sewer systems, drainage channels, or streams. The Contractor shall prevent eroded soils or debris from entering, crossing, or standing on existing street and roadways.

1.3.3.2 Storm Water Quality Control

The Contractor is required to comply with the requirements outlined in the Oklahoma Department of Environmental Quality (ODEQ) General Permit for Storm Water Discharges from Construction Activities (OKR10). In brief, the Contractor is required to submit Tinker AFB’s Notice of Intent (NOI) form to Tinker’s Storm Water Program Management office requesting for the authorization to discharge pollutants for the construction activity. The development and implementation of a Storm Water Pollution Prevention Plan (SWPPP) is required and must be submitted with the NOI. This plan shall provide for the control of storm water runoff from construction activities to reduce storm water contamination. The NOI and SWPPP must be submitted and authorized prior to discharging any pollutants. The Environmental Office can be contacted at (405)734-1228 to obtain further information.

For projects disturbing over an acre of land, the Contractor is required to submit to the ODEQ DEQ Form 605-002A, Notice of Intent for Storm Water Discharges Associated with Construction Activity on Sites of One Acre or More Acres. The Contractor must provide a copy of the certification authorizing the discharge from the ODEQ to Tinker’s Storm Water Program Management office before any consideration will be given for authorization for Tinker AFB’s NOI.

Adequate Best Management Practices (BMP’s) and appropriate control measures shall be included in the SWPPP to prevent construction dirt, chemicals, and/or debris from becoming a pollutant source to storm water discharges and to retain sediment on site. Such measures include but are not limited to silt fences, hay bales, earth dikes, sediment traps, storm drain inlet protection, and temporary/permanent sediment basins. Stabilization practices shall be included in the SWPPP and implemented to preserve existing vegetation and stabilize those portions of the construction site that are disturbed. The Contractor shall be required to amend the SWPPP when there is a change in the project design, operation, or maintenance and when BMP’s/control measures are ineffective in minimizing pollution.

The Contractor shall ensure that inspections of the construction site are performed at least every 14 calendar days and within 24 hours after a storm event of 0.5 inches or greater. The Contractor shall inspect the area to ensure that structural control measures and BMP’s are effective in preventing the discharge of dirt and construction debris. Any instances of non-compliance shall be corrected within 7 days of the inspection. The Contractor shall annotate these inspections in a report to be kept on site or at an easily accessible location. The report shall summarize the scope of the inspection, person performing the inspection, the date and time, and the major observances relating to the effectiveness of the SWPPP. The inspection report is subject to inspection by the Contracting Officer at any time during construction performance period.

The Contractor’s self inspections will be submitted to the Contracting Officer in batches every 30 days. These submittals, coordinated by the Construction Inspector and approved by the Contracting Officer, should satisfy permit compliance requirements.

The Contractor shall include in the submittals, the maximum height of each piece of construction equipment expected to be used during construction, which is to be submitted to the Contracting Officer prior to the start of construction. For all construction sites with a trailer or office, the Contractor shall post with a brief description of the project, point of contact and the location of the SWPPP. For those without an on-site trailer, the Contractor shall maintain the information at an easily accessible location.

The Contractor shall submit a completed form to terminate coverage under base permit for storm water discharges from construction activities to Tinker’s Storm Water Program Management office. Tinker AFB’s Notice of Termination (NOT) can be obtained by contacting Tinker’s Storm Water Program Management office at (405)734-1228. If NOI was also submitted to the ODEQ for the construction activity, DEQ Form 605-003 must be submitted to the ODEQ. Completed form shall be submitted when final stabilization of construction site has been achieved. Final stabilization means all soil disturbing activities have been completed and a uniform vegetative state with a density of 70% of native background cover has been established.

1.3.3.3 Spillage

At all times, special measures shall be taken to prevent chemicals, fuels, oils, greases, bituminous materials, waste washings, herbicides and insecticides, cement and surface drainage from entering surface or ground waters. If a spill occurs, the Contractor is responsible for reporting the spill to the Base Fire Department. The Contractor shall dial 911 from a base phone or 737-1117 to report the spill. The Contractor shall also advise the Contracting Officer immediately. The Contractor is liable for all clean-up, damages and repairs that resulted from the spill.

Spill Classification Guidelines: Standard spill classifications will enable response personnel to communicate the extent of a spill to other personnel within a common framework. The Contractor will determine if the spill creates a fire hazard to aircraft or equipment and will post a fireguard.

The following classifications are provided:

- Class I or Minor Spill – This spill involves an area less than two

(2) feet in any dimension and is not of a continuing nature.

- Class II or Medium Spill – This spill involves an area of less than ten (10) feet in any dimension, or not over fifty (50) square feet in area and is not of a continuing nature.

- Class III or Major Spill – This classification includes spills that are over ten (10) feet in any one dimension or over fifty (50) square feet in total area, or spills that have a continuing source.

1.3.3.4 Disposal

Disposal of any materials, wastes, effluents, trash, garbage, oil, grease, chemicals, etc.; in areas adjacent to streams or other bodies of water shall be subject to the written approval of the Contracting Officer. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the condition of the adjacent undisturbed area. If necessary, contaminated ground shall be excavated, disposed of as directed by the Contracting Officer, and replaced with suitable fill material, compacted and finished with topsoil all at the expense of the contractor.

1.3.3.5 Flushing & Sampling Requirements for Potable Water System

All newly constructed water mains and/or service lines shall be cleaned and sterilized according to Oklahoma Administrative Code (OAC) 252.626; which requires that all new piping be flushed and cleaned, isolated, and filled with a 50-100 mg/l chlorine solution for a continuous time period not less than 24 hours. A residual of not less than 10 mg/l chlorine must remain after the 24 hour retention period. If retention residual is met, the line will be flushed and sampled for coliform bacteria. Two consecutive safe bacteriological samples separated by a time period of not less than 24 hours must be obtained before the new line may be placed in service. If the 10 mg/l chlorine residual cannot be maintained, or if water samples test positive for coliform bacteria, the sterilization and flushing process shall be repeated until such time as required chlorine residual and bacteriological requirements met. In accordance with National Pollutant Discharge Elimination System (NPDES) requirements and storm water quality regulations, water flushed from the system shall be de-chlorinated and tested for chlorine prior to discharge. Water shall contain less than 0.1 mg/l total residual chlorine when discharged into any conveyance of the storm water system. See letter from 72 ADS/SGGB at Attachment 1 on Bacteriological Sampling Requirements for Water Line Maintenance for more detailed information. In addition, anytime that a Contractor taps into the bases water supply, they are required to utilize a backflow prevention device to prevent any possible contamination to the bases water supply.

1.3.3.6 Water System Construction Permits

Any project proposing to extend the Tinker AFB potable water system with connections to two or more buildings shall meet the construction permit requirements of “Oklahoma Water Systems Act”, 27A O.S. Supp. 1993, 2-6-301 et seq. as directed by Oklahoma Administrative Code Section 252, Chapter 626, Subchapters 3 and 5 (OAC 252:626-3-5). All required documents by the Act should be submitted to the Contracting. The Contractor shall plan accordingly in the scheduling of water permits to allow for ample lead time to accommodate the government (i.e., holidays, down days, etc).

1.3.4 Protection of Fish and Wildlife

The Contractor shall at all times perform all work and take such steps required to prevent any interference of disturbance to fish and wildlife.

The Contractor shall not be permitted to alter water flow or otherwise disturb native habitat adjacent to the project area that are critical to fish and wildlife. Fouling or polluting of water shall not be permitted.

Wash waters and wastes, shall be processed, filtered, ponded or treated by the Contractor and disposed of off base at no expense to the government.

Additionally, the use of chlorinated water is strictly prohibited, including discharge to storm drains, creeks or ponds on Tinker Air Force Base. Additional measures and precautions are required for areas draining directly to a pond or water way where long-term exposure of chlorine could be lethal to fish and other aquatic species. If disturbing the native habitat is essential to project completion, the Contractor shall request permission, in writing, from the Contracting Officer. The Contracting Officer shall notify the Natural Resources Program to determine if construction impacts to native habitat require any special requirements, mitigation or permits prior to construction disturbance. The Contractor shall also note any requirements for avoidance, minimization or mitigation required by any Environmental Assessment (EA)conducted for the project under the National Environmental Policy Act (NEPA).

1.3.5 Disposal of Removed Material

Unless otherwise specified in other sections of these specifications or unless reusable under the terms of this contract, all removed material shall be disposed of off base. This disposal shall be in accordance with all applicable Federal, State, County, and Municipal laws. Contractor is required to follow Tinker Air Force Base Construction and Demolition Debris Procedures (Attachment 5) to properly track and document all material removed, whether reused, recycled or sent for disposal. If hazardous waste is generated as a result of the project, the Contractor is required to comply with TAFBI 32-7004 and TAFBI 32-7006.

1.3.6 Dust Control

The Contractor shall be required to maintain all excavations, embankments, stockpiles, haul roads, permanent access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which would cause a hazard or nuisance to others.

Approved temporary methods of stabilization consisting of sprinkling chemical treatment, light bituminous treatment or similar methods shall be permitted to control dust. Sprinkling, to be approved, shall be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times; the Contractor shall have sufficient competent equipment on the job to accomplish this task. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs. A dust nuisance shall be defined as a concentration of nuisance insoluble particulates of less than 10 milligrams per cubic meter (mg/m3). A dust hazard shall be defined as a concentration of any dust that exceeds its Permissible Exposure Limit (PEL) as listed in 29 CFR 1910.1000 or its Threshold Limit Value – Time Weighted Average (TLF-TWA), Short Term Exposure Limit (TLV-STEL), or Ceiling Value (TLV-C) as listed in “Threshold Limit Values for Chemical Substances and Physical Agents & Biological Exposure Indices” published by the American Conference of Governmental Industrial Hygienists, Cincinnati, OH.

1.3.7 Maintenance of Pollution Control Facilities During Construction

During the life of this contract the Contractor shall maintain all facilities constructed for pollution control under this contract as long as the operations creating the particular pollutant are being carried out or until the material concerned has become stabilized to the extent that pollution is no longer being created. During the construction period the

Contractor shall conduct and document frequent training courses for his maintenance personnel and provide copies of this training to the Government.

The curricula shall include methods of detection of pollution, familiarity with pollution standards, and installation and care of vegetation covers, plants and other facilities to prevent and correct environmental pollution.

1.3.8 Pesticides (Insecticides, Fungicides, Herbicides, Etc.)

Application of all pesticides shall be accomplished by a certified pest control operator. Delivery and storage of pesticides shall be monitored by certified personnel to insure the adequacy of containers and the safe storage of toxic materials. Disposal of containers and chemicals off base shall not pollute natural drainage systems. If hazardous waste is generated as a result of the project, the Contractor is required to comply with AFI 32-7086. The Contractor shall submit any/all pesticides through the Hazardous Material Reporting process in specified in paragraph 1.3 of this section; to include application procedures, quantities, application rates, and storm water protection measures shall be included in the submittal. The Contractor shall notify the Contracting Officer at least 14 days prior to use of any pesticide.

1.3.9 Affirmative Procurement

Tinker Air Force Base has a requirement for the cost effective affirmative procurement of environmentally preferable products and services.

Affirmative Procurement is defined as the process of purchasing environmentally preferable products; especially products manufactured from recycled and reclaimed materials. The purpose of TAFB’s Affirmative Procurement Program is to increase the purchase and use of products with the highest percentage of recovered materials practicable. The United States Environmental Protection Agency (USEPA) has designated guideline items in the Comprehensive Procurement Guideline (CPG) III for mandatory procurement.

These CPG products are products that are or can be made containing recycled materials. In the CPG, the USEPA organizes these items into 8 product categories as follows:

1. Construction Products

2. Landscaping Products

3. Non-paper Office Products

4. Paper and Paper Products

5. Park and Recreation Products

6. Transportation Products

7. Vehicular Products

8. Miscellaneous Products

A current detailed listing of these products and recycled content requirements can be found at http://epa.gov/cpg/products.htm. Once in the website, to view the products, click on a specific product. The following information will be provided: Recommend Recovered Materials Content levels, Product Specifications, and Product Information, which includes the list of suppliers will be provided. In accordance with 40 CFR 247.2, the Contractor is required to research, propose and utilize these designated products, and any other recycled-content products available in the market place. CPG products with the highest percentage of recovered materials practicable shall be utilized, unless otherwise specified, or if one more of the following exemptions apply:

- Does not meet appropriate performance specifications.

- Is not available competitively (from two or more sources).

- Is not available within a reasonable time frame.

- Is only available at an unreasonable price.

The Contractor shall certify that the percentage of recovered materials to be used in the performance of the contract will be at least the amount required by applicable specifications or other contractual requirements, and shall also estimate the percentage of total material utilized, the Contractor shall provide written explanation and documentation as to why the products were not used. A Recovered Material Determination Form, (Attachment 8), shall be used to document any exemption.

1.4 HAZARDOUS MATERIAL REPORTING

In accordance with the requirements in AFI 32-7086, Hazardous Materials Management, the following management practices are. The Contractor shall submit these forms/reports as indicated to the Contracting Officer.

Material Safety Data Sheet: To assist in the evaluation of health hazards and to provide information pertinent to the Emergency Planning Comprehensive and Response Act (EPCRA), the Contractor shall submit copies of the Material Safety Data Sheets (MSDS) for all hazardous materials used, to the

AF Form 3952: The Contractor shall submit an electronic AF Form 3952, Chemical/Hazardous Material Request/Authorization, for all hazardous material that is Contractor furnished or provide information as contract specifies.

Monthly Hazardous Material Usage Report (Attachment 7): The Contractor is required to furnish to the Contracting Officer a monthly report stating the type, amounts, and locations of Hazardous Materials the Contractor used in the construction of this project. This report shall be provided by the fourth workday of each month for information on the preceding month.

1.5 ASBESTOS ABATEMENT

Contracts that include asbestos abatement requirements will adhere to the requirements contained in Attachment 2, Tinker Air Force Base Asbestos Abatement Specification.

1.6 LEAD-BASED PAINT ABATEMENT

Contracts that include lead-based paint abatement requirements will adhere to the requirements in Attachment 3 and Attachment 3A, Tinker Air Force Base Lead-Based Paint Abatement Specifications.

1.7 PCB FILLED BALLAST TRANSFORMER & UNIVERSAL WASTE LAMP ABATEMENT

Contracts that include PCB-filled ballast, PCB-filled transformer and universal waste lamp abatement requirements will adhere to the requirements contained in Attachment 4, Tinker Air Force Base PCB Filled Ballast and Universal Waste Lamp Abatement Specifications.

1.8 SPRAY FINISHING

Spray finishing operations (painting) shall be used only after the written approval of the Contracting Officer. The Contractor shall submit a plan, a list of resultant cost savings, and a list of procedures, which indicates methods of isolating the contract area from other areas of the building.

The plan shall provide for air infiltration, isolation of work area and complete work safety methods as outlined in applicable regulations and specifications. The Contracting Officer shall evaluate the plan and decide if spraying will be allowed. Adherence to applicable regulations is mandatory for continued operation of spraying. Applicable regulations include, but are not limited to:

29 Code of Regulations (CFR) 1910.94, Ventilation

29 Code of Federal Regulations (CFR) 1910.107, Spray Finishing Using

Flammable and Combustible Materials.

When spray painting is being performed in occupied areas, all personnel with the exception of painters and their helpers shall be removed. The area shall be physically isolated from the occupied areas by the use of plastic or some other vapor proof barrier. This isolation shall remain in place until the paint has cured and dried and is no longer emitting air contaminants. Local exhaust ventilation shall be utilized in the isolated area to remove air contaminants so they do not build to an explosive level or exceed the capacity of the respirator being worn. This local exhaust ventilation shall not be directly vented to the outdoors unless a permit has already been obtained from the Oklahoma City/County Health Department for air contaminants prior to discharge to the environment. Storage use and handling of all portable cylinder gases shall comply with NFPA 55.

1.9 ENVIRONMENTAL MANAGEMENT SYSTEM AWARENESS TRAINING

An Environmental Management System (EMS) is a system to achieve continual improvement in mission performance by reducing environmental risks and cost.

To help meet these goals, all contractor’s working on TAFB are required to receive EMS awareness training.

The Contractor will be responsible to ensure that all personnel working on TAFB (including sub-contractors) review the one page awareness training sheet (Attachment 9). A copy of this sheet, signed by the contractor and certifying that all personnel have received this training, shall be submitted to the contracting officer.

1.10 UNEXPECTED DISCOVERIES OF ARCHEOLOGICAL RESOURCES

In the event of the discovery of unexpected archeological resources (i.e.

human remains or cultural items) during construction, contractors shall follow the guidelines set in the Integrated Cultural Resource Management Plan (2005) Section E.13 Unexpected Discoveries of Archeological Materials During Construction Projects. A copy of this document is included as Attachment 10.

1.11 USING RADIOACTIVE MATERIALS

When a civilian organization or other Federal agency desires to bring radioactive material onto or conduct operations using radioactive materials, written approval must be obtained from the installation RSO. The request must be at least 30 calendar days before bringing the materials onto the installation. The installation RSO is located in the BEF.

1.12 LIST OF ATTACHMENTS

Attachment 1: Bacteriological Sampling Requirements Attachment 2: TAFB Asbestos Abatement Specifications Attachment 3: TAFB Lead-Based Paint Abatement Specifications for

High Priority Facilities.

Attachment 3A: TAFB Lead-Based Paint Abatement Specifications for

Industrial Facilities.

Attachment 4: TAFB PCB-Filled Ballast, PCB-Filled Transformer and

Universal Waste Lamp Specifications.

Attachment 5: TAFB Construction and Demolition Debris Management

Procedures Attachment 6: TAFB hazardous Waste Management Procedures Attachment 7: Monthly Hazardous Material Usage Report Attachment 8: Recovered Material Determination Form Attachment 9: Environmental Management System Awareness Training

Attachment 10 - Integrated Cultural Resource Management Plan (2005), Section E.13 – Unexpected Discoveries of Archeological Materials During Construction Projects

Attachment 11 – Tree Protection Requirements

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

- End of Section -

ATTACHMENT 1

Bacteriological Sampling Requirements

Tinker Contracting Document 0720, Attachment 2

TINKER AIR FORCE BASE ASBESTOS ABATEMENT SPECIFICATIONS

Revision Date: 12 May 2010

Part A - General

Part B - Definitions

Part C - Pre-Abatement Submittals

Part D - Abatement Material Requirements

Part E - Air Sampling & Monitoring All Classes of Removal

Part F - Respiratory Protection

Part G - Class I Asbestos Removal, Negative Pressure Enclosure (NPE) Area Preparation

Part H - Negative Pressure Enclosure, Removal

Part I - Class I Asbestos Abatement, Glovebag, Negative Pressure Glovebag Removal Pre-Abatement Preparation

Part J - Removal

Part K - Class II Asbestos Work

Part L - Disposal

Part M - Post-Abatement Submittals

Part N - Hazardous Property Disclaimer

PART A

GENERAL

The requirements for asbestos abatement are stated herein. The drawings or statement of work associated with this project outline the work area that contains asbestos and the work to be accomplished. In case of conflict between the drawings and the specifications, the specifications shall govern.

The following regulations, their appendices, memorandums, attachments and other appurtenant documents, which form a part of these regulations, shall apply in their entirety.

A.1 Title 29 Code of Federal Regulations (CFR), Section 1926.1101 including all appendices and memorandums, Occupational Safety and Health Administration (OSHA), U.S. Department of Labor, latest edition.

A.2 Title 40 CFR Part 61, Subparts A and M, National Emission Standards for

Hazardous Air Pollutants, U. S. Environmental Protection Agency (EPA), latest edition.

A.3 Title 29 CFR, Section 1910.134, Respiratory Protection (OSHA), latest edition.

A.4 Title 40 CFR, Part 355.40, Emergency Planning and Notification, latest edition.

A.5 Title 49 CFR, Part 172, Hazardous Material Tables and Hazardous

Materials Communications Regulations, latest edition.

A.6 The Asbestos Contractor shall have in his possession, at the job site and in view, one copy of each of the following: OSHA Reg 1926.1101, EPA 40 CFR, Part 61, subparts A and M, and Tinker AFB Asbestos Specification.

A.7 Where a conflict exists between the requirements of this specification and any of the above-mentioned regulations, the most stringent shall be applicable.

A.8 All Asbestos Contractors are encouraged to make a pre-bid site visit, to ensure familiarization with site conditions and the extent of the work requirements.

A.9 Health Warnings: Asbestos Contractors are warned that unprotected exposure to asbestos fibers has been determined to significantly increase risk of incurring four diseases; lung cancer, gastrointestinal cancer, mesothelioma, and asbestosis. Care must be taken to avoid releasing or causing to be released, asbestos fibers into the atmosphere. The Government assumes no liability for damages, personal injuries, illness, disabilities or death to the Asbestos Contractor, Asbestos Contractor Employees, and other persons subject to the Asbestos Contractor’s control or to any other person including members of the general public, arising from, or incident to the purchase, use, disposition, subsequent operations performed on, contact with or exposure to the asbestos, provided such is caused or contributed to in any manner by the Asbestos Contractor. Heat Stress: The Contractor should also be aware that due to the nature of asbestos work, the wearing of respirators, impermeable clothing, material to be abated

(steam lines, boilers, etc.), and containment could all add to heat stress.

A.10 Property Damage: The Asbestos Contractor shall be responsible for all damages caused by or during the abatement. All damaged areas shall be restored to their original condition subject to approval by the Contracting Officer. Any repair or replacement shall be done at no cost to the Government.

A.11 Quality Assurance: The Asbestos Contractor shall ensure all employees are knowledgeable of and comply with the procedures listed in this specification. Work shall not begin each day until a monitor from CE is on site.

A.12 Glovebag Removal: Glovebags shall not be used on surfaces whose temperatures exceeds 150 Fahrenheit, shall not be larger than 60 inches X 60 inches and shall not be used more than once or moved after use.

Two employees per glovebag and all employees monitored.

A.13 HEPA Filters/Shower Filters: All filters shall be new at the beginning of the project.

A.14 All asbestos removal shall be supervised by a Competent Person and shall have daily air monitoring.

A.15 Air Monitoring: The Asbestos Contractor shall use an independent laboratory for air monitoring and analysis support.

A.16 Site Security: The Contractor shall be required to provide security at all Negative Pressure Enclosures after abatement has begun and until clean air has been established. This employee shall maintain the negative pressure enclosure, prevent unauthorized entry, watch for fires within the negative pressure enclosure, and guard Contractors material/equipment.

A.17 Fire Protection: The work area shall have dry-change ammonium fire extinguishers with a UL rating of at 10A:B:C, with a valid inspection tag for every 1500 square feet of area for Negative Pressure Enclosures and at least one extinguisher for every glovebag removal area.

PART B

DEFINITIONS

The following is a listing of terms and definitions for this specification.

B.1 Class I Asbestos Work: Work activities involving removal of TSI, surfacing ACM, and PACM.

B.2 Class II Asbestos Work: Work activities involving the removal of ACM, which is not thermal system insulation or surfacing material. Removal of non-friable building materials such as asbestos wallboard, floor tile, roofing, siding, shingles, construction mastics, etc. are examples of Class II Asbestos Work.

B.3 Class III Asbestos Work: Means repair and maintenance operations, where “ACM”, including thermal systems insulation and surfacing material is likely disturbed.

B.4 Abatement: Procedures to control fiber release from asbestos containing materials. This includes removal, encapsulation and enclosure.

B.5 Air Monitoring: The process of measuring the fiber concentration of a specific volume of air over a specified period time.

B.6 Airlock: An enclosure consisting of two polyethylene curtained doorways (3 sheets of plastic per doorway) at least 3 feet apart.

B.7 Amended Water: A mixture of at least one ounce of 50 percent polyoxyethylene ester and 50 percent polyoxyethylene ether in five gallons of water.

B.8 Asbestos: A group of naturally occurring minerals that separate into fibers. There are six asbestos minerals used commercially:

chrysotile, amosite, crocidolite, anthophyllite, tremolite and actnolite and any of these minerals that has been chemically treated and/or altered.

B.9 Asbestos Containing Material (ACM): Any material containing more than

1 percent asbestos.

B.10 Asbestos Contractor: A private entity certified in asbestos abatement.

B.11 Asbestos Fiber: A particulate form of asbestos 5 micrometers or longer with a length to diameter ratio of at least 3:1.

B.12 Authorized Visitor: Any representative of a regulatory or other agency having jurisdiction over the project or anyone authorized by CEA and is required by work duties to be present in the regulated area.

B.13 Clean Room: An uncontaminated area or room which is part of the worker decontamination enclosure with provisions for storage of worker’s street clothes and protective equipment.

B.14 Competent Person: One who is capable of identifying existing and predictable hazards in the surroundings or working conditions and has authorization to take prompt corrective measures to eliminate the hazards. The Competent person must be an employee of the Asbestos Contractor and shall be named as that person in the project pre-abatement submittals. The Competent person shall meet the criteria of the EPA’s Model Accreditation Plan for Supervisors 40 CFR Part 763 and duties required by Subpart C of 29 CFR 1926.20 through 1926.32.

B.15 Decontamination Enclosure System: A series of connected rooms and airlocks used for the decontamination of workers and of materials and equipment (i.e., airlock, clean room, airlock, shower, airlock, dirty or equipment room, airlock, work area).

B.16 Demolition: The wrecking or taking out of any load supporting structural member and related asbestos containing materials.

B.17 Employee: Any person working for the Asbestos Contractor who physically engages in the abatement of asbestos or performs a task on the job site.

B.18 Encapsulant (Sealant): A material applied to asbestos containing materials to control the release of asbestos fibers by creating a membrane over the surface (bridging encapsulant) or by penetrating into the material and binding its components (penetrating encapsulant).

B.19 Encapsulate: The application of a sealant to asbestos containing materials to control the release of asbestos fibers.

B.20 Enclosure: The complete enclosing of asbestos containing material behind airtight, impermeable, permanent barriers.

B.21 Equipment Room: A contaminated room which is part of the worker decontamination enclosure system used for storage of contaminated clothing and equipment.

B.22 Friable Asbestos: Any material or combination of materials containing more than 1% asbestos than hand pressure can crumble, pulverize or reduce to powder when dry.

B.23 General Contractor: Shall deem to exercise general supervisory authority over the work even though the General Contractor is not qualified to serve as the “competent person” as defined in 29 CFR

1926.1101 paragraph b. The General Contractor shall have the overall responsibility that his Subcontractor(s) are in compliance with this standard and all other regulations covering asbestos abatement.

B.24 Glovebag: An asbestos labeled bag constructed of 6 mil or greater transparent plastic, two inward projecting long-sleeve rubber gloves, one inward projecting water wand sleeve and an internal tool pouch.

B.25 HEPA Filter: A High Efficiency Particulate Air (HEPA) filter capable of trapping and retaining 99.97 percent of particles (asbestos fibers) greater than 0.3 micrometers in diameter.

B.26 HEPA Vacuum Equipment: Vacuuming equipment with a HEPA filter system.

B.27 Load-Out Area: An area designated for controlled transfer of asbestos waste and equipment. This area can be adjacent to the equipment room or work area and must have two airlocks.

B.28 Landfill (approved): An EPA approved site for the disposal of asbestos containing materials and other hazardous waste.

B.29 Mini-Containment: A small enclosure intended for a small scale abatement procedure from the environment through negative air pressure, physical barriers, and/or other means, mini-containments will ordinarily not have an attached decontamination system.

B.30 Negative Pressure Enclosure (NPE): An enclosure of the regulated area with a minimum of -0.02 column inches of water pressure relative to the outside area using HEPA filtered negative air pressure equipment, four

(4) air exchanges per hour. This shall be maintained within the NPE as evidenced by a manometer. The NPE also has a decontamination facility and a load-out area.

B.31 Negative Air Pressure Equipment: A portable local exhaust system equipped with HEPA filtration and capable of maintaining low velocity airflow into a contaminated area from an adjacent uncontaminated area.

B.32 Objects: Fixed items are those which cannot be removed from the work area. Moveable items are those which can be removed from the work area.

B.33 Non-Friable Asbestos: Any material containing more than 1% asbestos by weight that hand pressure cannot crumble, pulverize or reduce to powder when dry.

B.34 Presumed Asbestos Containing Material (PACM): Thermal systems and surfacing material found in buildings constructed no later than 1985, that the Government has not verified the absence of asbestos.

B.35 Plasticize: To cover with plastic sheeting.

B.36 Personal Protective Equipment (PPE): Disposable, impervious coveralls that are equipped with head and foot covers, gloves, and respirators.

B.37 Regulated Area: The area surrounding the work area demarcated by danger warning tape and signs. All personnel entering the regulated area must wear full PPE.

B.38 RACM: Regulated asbestos-containing materials.

B.39 Shower Room: A room between the clean room and the equipment room in the worker decontamination enclosure with hot, cold, or warm-running water suitably arranged for complete showering during decontamination.

Showers shall comply with 29 CFR 1910.141. All wastewater shall be filtered to the one (1) micron level prior to being discharged into the sewer system.

B.40 Warning Labels and Signs: Signs and labels which conform to OSHA CFR

1910.1200 (f), and 29 CFR 1926.1101 (8).

B.41 Wet Cleaning: The process of eliminating asbestos contamination by using cloth’s, mops, or other cleaning tools which have been dampened with amended water.

B.42 Work Area: A regulated area where asbestos is abated. A contained work area is sealed, plasticized and equipped with a decontamination enclosure system. A non-contained work area is not plasticized but is equipped with a decontamination enclosure system and is demarcated by danger warning tape.

B.43 CEA: Asset Management Division

B.44 BEF: Bio-environmental Engineering Flight.

B.45 CE: Civil Engineering Directorate.

PART C

PRE-ABATEMENT SUBMITTALS

The Contractor shall submit all required pre-abatement submittals to the Contracting Officer at least five working days prior to commencement of work for review and/or approval. After completion of the submittal review, additional information may be required for clarification of or in support of documents submitted. The required submittal areas include, but are not limited to the following:

C.1 Documentation of Training/Experience: All training must meet the criteria of 40 CFR 763 and 29 CFR 1926.1101. All abatement employees must be certified in accordance with 40 CFR 763 and 29 CFR 1926.1101, and certifications must be current throughout the contract period.

C.2 Employee Physicals: All physicals shall be in accordance with 29 CFR

1926.1101. Prior to start of work copies of the examinations for each employee utilized on this project must be submitted to the Contracting Officer. All additional employees or those with expiration dates of the physicals before or during the construction project must submit updated physicals or have an immediate medical examination. Submittals must received be prior to start of work on this project. All submittal documents must be present and accessible for review at the project site.

C.3 Regulatory Agency Notification: Verify that NESHAPS report

(attachment) was received by the following agency and a copy of this verified report must be submitted to the Contracting Officer prior to start of work: The NESHAPS coordinator is located in Oklahoma City, the Compliance Section, Air Quality Division, Oklahoma Department of Environmental Quality, 4545 N. Lincoln, Oklahoma City, Oklahoma 73104.

C.4 Security Documentation: Work area and equipment must be secured at all times to ensure no unauthorized persons enter contaminated or asbestos storage areas. The Contracting Officer prior to starting the asbestos abatement must approve storage sites for all contractor equipment.

C.5 Communications: The Contractor shall submit the Contracting Officer a phone and/or pager number where the General Contractor Supervisor and the Competent Person of the Asbestos Contractor may be reached at all times.

C.6 Step-by-Step Abatement Procedures: This applies to friable and non-friable asbestos abatement procedures for each distinct location.

C.7 Glovebag Procedures: The submittal for glovebag procedures shall include but not be limited to the following:

- Sizes and type of bags to be used.

- Glovebag installation insuring leak-proof system.

- Method used for smoke testing bag.

- Type and manufacturer of negative air equipment.

-…