77 - RFI Response Log SABER Seed Related _ 13_Jan 2026.xlsx

XLSX spreadsheet 49 KB Posted

Attached to
SABER IDIQ
Solicitation number
FA486125R0003
Issued by

About this file

This file is an RFI (Request for Information) Response Log for the SABER Seed Project (RKMF240010) involving renovation of Building 10250 at Nellis Air Force Base. The document contains a comprehensive log of 147 questions and official responses related to various technical, design, and construction aspects of the project, covering topics such as demolition, utilities, HVAC, electrical systems, communications infrastructure, fire protection, landscaping, and facility modifications.

Key details include the project involving renovation of an Honor Guard facility, with specific requirements for design submission (ultimately determined to be a Level 1 design), building occupation during construction, and extensive technical specifications. The RFI log addresses critical contractor inquiries about existing building conditions, required demolition and construction work, utility connections, communication and electrical systems, fire protection requirements, and specific room and area modifications. Responses indicate the government will provide additional attachments and clarifications through future amendments, with the overall goal of preparing a comprehensive renovation of Building 10250 that meets Air Force infrastructure standards.

View the file

Other files

File Type Posted
Solicitation Amendment FA486125R00030017 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030017.pdf PDF
Atch 80_ RFI Response Log_General Solicitation 9 March 2026.xlsx XLSX spreadsheet
Solicitation Amendment FA486125R00030016 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030016.pdf PDF
Solicitation Amendment - FA486125R00030015.pdf PDF
Solicitation Amendment FA486125R00030015 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030014.pdf PDF
3 - Self Scoring Matrix 17 Feb 26.xlsx XLSX spreadsheet
Solicitation Amendment FA486125R00030014 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030013.pdf PDF
Solicitation Amendment FA486125R00030013 SF 30.pdf PDF
Attach 79 RFI Log SABER Seed 29 Jan 2026_.xlsx XLSX spreadsheet
Att 78 RFI Log Additional Responses General Solicitation 27 Jan 2026_.xlsx XLSX spreadsheet
Att 3 -Self Scoring Matrix 3_Feb_2026.xlsx XLSX spreadsheet
44- SABER SOO RKMF240010 Renovate Honor Guard 99 FSS B10250_28January2026 (003).pdf PDF
Solicitation Amendment FA486125R00030012 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030012.pdf PDF
Solicitation Amendment FA486125R00030011 SF 30 .pdf PDF
1 - SABER SOW 7 Jan 2026.pdf PDF
Solicitation Amendment - FA486125R00030011.pdf PDF
2 - Price Schedule _13 Jan 2026.xlsx XLSX spreadsheet
3 - Self Scoring Matrix 7_Jan 26.xlsx XLSX spreadsheet
Solicitation Amendment - FA486125R00030010.pdf PDF
44 -Statement of Objectives (SOO) for RKMF 240010 20 Nov 25.pdf PDF
Attach 75 SABER Seed Attachment 19 - B10250 comm room.pdf PDF
Attach 74 SABER Seed Attachment 18 - Knox Box Location.pdf PDF
73 - Task Order Pricing Letter _ Gordian System Licens Fees 5 percent and 1.95 percent.pdf PDF
1- SABER SOW 7 Jan 2025 .pdf PDF
76 - RFI Response Log General Solicitation 13_Jan 26.xlsx XLSX spreadsheet
Solicitation Amendment FA486125R00030010 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030009.pdf PDF
Solicitation Amendment FA486125R00030009_SF 30.pdf PDF
Solicitation Amendment FA486125R00030007 SF 30.pdf PDF
Solicitation Amendment FA486125R00030006 SF 30.pdf PDF
(Attachment 65) SABER Seed SOO Honor Guard Building 10250 Attachment 12 - Mech. Room Report.pdf PDF
(Attachment 66) SABER Seed SOO Honor Guard Building 10250 Attachment 13 - Asbestos and Lead testing building history.xlsx XLSX spreadsheet
Solicitation Amendment - FA486125R00030006.pdf PDF
Attachment 72 SABER IDIQ Preproposal Sign In Sheet 29 October 2025 FA486125R0003.pdf PDF
(Attachment 63) SABER Seed SOO Honor Guard Building 10250 Attachment 10 - Asbestos and Lead testing dated 24 February 2014.pdf PDF
(Attachment 68) SABER Seed SOO Honor Guard Building 10250 Attachment 15 - B10250 room numbers.pdf PDF
(Attachment 55) SABER Seed SOO Honor Guard Building 10250 Attachment 1 - HAZMAT Results 10250 Restrooms Part 1.pdf PDF
(Attachment 58) SABER Seed SOO Honor Guard Building 10250 Attachment 5 - Attachment 5 AFGIMS Utilities Snapshot.pdf PDF
(Attachment 69) SABER Seed SOO Honor Guard Building 10250 Attachment 16 - 10250 BFP Device replacement.png PNG image
(Attachment 57) SABER Seed SOO Honor Guard Building 10250 Attachment 3 - As-Builts 65 LOCATION and GRADING.pdf PDF
(Attachment 70) SABER Seed SOO Honor Guard Building 10250 Attachment 17 - Double Check Valve Assembly.pdf PDF
(Attachment 60) SABER Seed SOO Honor Guard Building 10250 Attachment 7 - Sewer Line with Measurements and Pictures.pdf PDF
Attachment 71 SABER IDIQ Preproposal Conference Slides 29 October 2025 FA486125R0003.pptx PPTX presentation
(Attachment 61) SABER Seed SOO Honor Guard Building 10250 Attachment 8 - Asbestos and Lead testing of entire building dated 7 July 2007.pdf PDF
(Attachment 59) SABER Seed SOO Honor Guard Building 10250 Attachment 6 - Floorplan Conceptual.pdf PDF
Show 40 more

Latest 50 of 126 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI LOG

FA486125R0003
RENOVATE HONOR GUARD 99 FSS B10250
RKMF240010(SABER Seed Project)
Please use RFI log for questions pertaining to SABER Seed project and related attachments.
INSTRUCTIONS: All columns A through F must be filled out in order to be considered responsive.
Must state SOW, document section, drawing sheet, etc. in column E, and Division in column F.
Please read the SOW and all solicitation docs thoroughly before submitting an RFI.
example:3-Jul-25EXAMPLE. Type your question here after reviewing all docs.SOW 1.2.3.45ELECTRICALOffical Reponse
ITEMDATE SUBMITTEDQUESTIONSOW or DOCUMENT (INCL SECTION #, or PAGE, DWG SHEET, ETC.)DIVISION (ELEC, MECH, COMM, STRUCT, ETC.)Offical Reponse
19-Oct-25Will the government provide CAD based .dwg files of the as built drawings pertaining to Bldg. 10250 (Seed Proj)?44 - SABER SOO RKMF240010GENERALCAD drawings are not available.
29-Oct-25Will the government provide underground utility drawings for ALL identified utilities surrounding B10250 (Seed Proj)?44 - SABER SOO RKMF240010UTILITIESYes. Attachments were attached in Amendment 006
39-Oct-25Item 3 on Pg 2 states "The followings are attachments as a part of the package" but are not included. Will the government please provide these documents?

3.1.1.

HAZMAT Results 10250 Restrooms part 1 Location: Restrooms at South Corner.

3.1.2.

HAZMAT Results 10250 Restrooms part 2 Location: New Office at East Corner.

3.1.3.

As-Builts page 65 LOCATION & GRADING Overview of the Location, Showing B10250 that used to be a CHAPEL.

3.1.4.

As-Builts Combination As-Built of buildings 17001, 10272, 10240, 10245 and 10250.

3.1.5.

AFGIMS Utilities Snapshot Overview and locations of the Communication lines, Electrical, Natural Gas, Sewer, and water lines.

3.1.6.

Floorplan Conceptual Conceptual preferred layout of the Women 109, Men 110, and the new office.

3.1.7.

Sewer Line with Measurements & Pictures Overview and measurements of the existing and the expected new sewer lines with pictures.

3.1.8.

Asbestos and Lead testing of entire building dated 7 July 2007 3.1.9.

Asbestos and Lead testing for installing air compressor dated 29 September 2011 3.1.10.

Asbestos and Lead testing dated 24 February 2014 3.1.11.

Testing on exterior paint walls dated 6 November 2014 3.1.12.

Mech. Room Report3.1.13.

Asbestos and Lead testing building history 3.1.14.

B10250 refurbish space conceptual visuals 3.1.15.

B10250 room numbers 3.1.16.

10250 BFP Device replacement 3.1.17.

Double Check Valve Assembly44 - SABER SOO RKMF240010GENERALAttachments were attached in Amendment 006
49-Oct-25Will the government provide Fire Suppression (Sprinkler) Shop Drawings and Calc's for review and incorporation into the Concept Design?44 - SABER SOO RKMF240010FIRE PROTECTIONFound in as-builts folder for B10250 under RKMF08-0080
59-Oct-25Will the government provide Fire Protction (Fire Alarm/MNS) Shop Drawings and Calc's for review and incorporation into the Concept Design?44 - SABER SOO RKMF240010FIRE PROTECTIONLocated in attachment 3.1.4.
69-Oct-25Will the government provide the Energy Management Control System (EMCS) using Direct Digital Control (DDC) that are manufactured by Johnson Controls as built layout, any Shop Drawings and Calc's for review and incorporation into the Concept Design?44 - SABER SOO RKMF240010MECHANICALAny current drawings have been provided in attachment 3.1.4 for HVAC equipment that is existing.
79-Oct-25Will the government provide the Inside Plant and Outside Plant Tele-Communications As Built Layout/Shop Drawing Pland pertaining to B1025?44 - SABER SOO RKMF240010COMMUNICATIONSPlease refer to attachments and pictures provided for comm related questions
89-Oct-25On page 13, Item 5 under PERFORMANCE PERIOD states the proposed performance period for this task order is 180 days for construction. Will the government confirm this duration does not include design development and reviews?44 - SABER SOO RKMF240010CONTRACTINGYes
921-Oct-25Can the current AFGIMS utility data be provided?SOO Att. 3.1.5, 3.1.7; § 4.3.18Civil / UtilitiesWill be addressed in Amendment; Correct SABER Seed SOO/attachments need to be updated
1021-Oct-25Please provide slab thickness, reinforcement (WWF/rebar), dowel size/spacing, jointing pattern, and compressive strength for exterior concrete used to replace gravel and fill areas adjacent to the courtyard.SOO §§ 4.4.8–4.4.9Civil / Site / ConcreteAs builts were provided as Attachment 49. But Sewer Line with measurements will be included in future amendment.
1121-Oct-25Please clarify the scope of ‘seal asphalt parking lot’ in 4.16.2: Does this mean crack sealing, seal coat application, or an asphalt overlay (and if overlay, specify thickness and mix type)? Also confirm if striping is included after sealing.SOO 4.16.2Civil / Site / ConcreteCrack sealing and seal coat application. Striping is included after sealing is finished per SOW section 4.16.3.
1221-Oct-25Please clarify what “landscaping refresh” entails as listed in 4.16.4:

Does this include removal and replacement of existing rock/gravel, or only weed removal and installation of weed barrier?

Are we required to add new decorative rock, replace existing vegetation, or install new plants/irrigation?

Should the refresh include grading adjustments, edging, or replacement of any damaged hardscape?

Are there any base standards or approved plant lists that must be followed?SOO 4.16.4Civil / Site / ConcreteLandscaping refresh includes removing weeds and dead plants. Any rock/gravel area will be filled so area appears fully covered. Contractor is authorized to use the rock that is asked to be demoed in certain areas to be reused if gravel matches for other areas to fill.
1321-Oct-25Is the double sanitary cleanout at the lateral-to-main connection acceptable to Nellis AFB standards for a 6" lateral, or is a manhole required at this point?SOO 4.17.1 - 4.17.2Civil / Site / ConcreteThis is not a Nellis base standard. Since there is already a manhole located on the lateral, we are asking for a 6" double sanitary cleanout at the intersection of lateral and main to ensure the lateral to B10250 will not fail as it has in the past.
1423-Oct-25In the "SABER STATEMENT OF OBJECTIVES FOR RKMF240010 RENOVATE HONOR GUARD 99 FSS B10250 NELLIS AIR FORCE BASE, NEVADA 14 February 2025", Several key documents listed in item 3 have not been provided to the bidders, which prevents us from developing the Level 2 design. Will the government provide these attachments and additional time to develop the design accordingly?SOO Item 3ContractingAttachments were attached in Amendment 006
1523-Oct-25Item 3 on Pg 2 states "The followings are attachments as a part of the package" but are not included. Will the government please provide these documents?

3.1.1.

HAZMAT Results 10250 Restrooms part 1 Location: Restrooms at South Corner.

3.1.2.

HAZMAT Results 10250 Restrooms part 2 Location: New Office at East Corner.

3.1.3.

As-Builts page 65 LOCATION & GRADING Overview of the Location, Showing B10250 that used to be a CHAPEL.

3.1.4.

As-Builts Combination As-Built of buildings 17001, 10272, 10240, 10245 and 10250.

3.1.5.

AFGIMS Utilities Snapshot Overview and locations of the Communication lines, Electrical, Natural Gas, Sewer, and water lines.

3.1.6.

Floorplan Conceptual Conceptual preferred layout of the Women 109, Men 110, and the new office.

3.1.7.

Sewer Line with Measurements & Pictures Overview and measurements of the existing and the expected new sewer lines with pictures.

3.1.8.

Asbestos and Lead testing of entire building dated 7 July 2007 3.1.9.

Asbestos and Lead testing for installing air compressor dated 29 September 2011 3.1.10.

Asbestos and Lead testing dated 24 February 2014 3.1.11.

Testing on exterior paint walls dated 6 November 2014 3.1.12.

Mech. Room Report3.1.13.

Asbestos and Lead testing building history 3.1.14.

B10250 refurbish space conceptual visuals 3.1.15.

B10250 room numbers 3.1.16.

10250 BFP Device replacement 3.1.17.

Double Check Valve AssemblySolicitation+Amendment+-+FA486125R00030001, L-4.3.1. Seed Project (Technical Proposal and Qualifications Subfactor 1), (a) Pg 47ContractingAttachments were attached in Amendment 006
1623-Oct-25If a Level 2 design remains the submittal standard for this proposal, we request a 6-week time extension from when the remaining bid documents are received. This provides the time to develop the detailed design and to solicit bids from key contractors based on the design documents.Solicitation+Amendment+-+FA486125R00030001, L-4.3.1. Seed Project (Technical Proposal and Qualifications Subfactor 1), (a) Pg 47ContractingLevel 1 will suffice. If not already completed, an amendment Changing the Seed Project for Honor Guard Building to be a Level 1 Proposal will be released.
1710/28/251. Background

Section L-4.3.1 of the solicitation requires the Offeror to submit a “complete Level 2 Design” for the Seed Project RKMF240010 – Renovate Honor Guard, Building 10250, in accordance with Attachment 01 (SABER Specifications SOW, Section 1.4.11.3) and Attachment 45 (Statement of Objectives).

While the contractor fully understands and supports the intent of this requirement — to evaluate each offeror’s technical understanding and design-build capability — it has been determined that submission of a complete Level 2 design at the proposal stage is not feasible without extensive site investigations, Government coordination, input, and access to project data that are not yet available to offerors.

2. Request for Clarification – Level 2 Design Feasibility A Level 2 design, as defined in Attachment 01, Section 1.4.11.3, includes PE-stamped drawings, detailed calculations, and full system coordination (architectural, structural, mechanical, electrical, plumbing, fire protection, and communications).

Producing this level of design requires:

•Field verification of existing utilities and systems.
•Coordination and approval by Government design and safety officials.
•Input from the Base Civil Engineer, Fire Protection Engineer, and Communications personnel; and
•Access to Government-furnished technical data not available pre-award.

Because these coordination steps cannot occur prior to contract award, developing a complete Level 2 design is impossible within the constraints of the proposal period.

Additionally, as noted by our licensed design firm and teaming partner:

“It would be impossible to develop a compliant Level 2 design without direct communication with the customer, and additional time would be required to complete such a design.”

Accordingly, the contractor respectfully recommends that the Government authorize and accept a Level 1 design submission in lieu of a full Level 2 design for proposal evaluation.

A Level 1 design will:

•Provide complete conceptual drawings and narratives addressing all required disciplines.
•Demonstrate a clear understanding of the project intent per the Statement of Objectives; and
•Include sufficient technical detail and assumptions to support a compliant cost proposal in eGordian.

This approach ensures technical adequacy and cost realism while remaining within the feasible and allowable scope of pre-award design work.

3. Request for CAD Files – Level 1 Design Development To accurately prepare the Level 1 design submission, the contractor requests that the Government provide AutoCAD (.dwg) files for the existing as-built drawings and site utilities for Building 10250.

The currently provided PDF as-builts and conceptual layouts cannot be used for scaled CAD integration or layering of proposed system modifications. Access to the native CAD files will enable:

•Accurate depiction of existing conditions,
•Proper alignment of proposed improvements, and
•Multidisciplinary coordination to ensure that the design submission fully aligns with the Government’s objectives and technical expectations.

4. Summary of Requests

1.Confirm that a Level 1 design submission will satisfy the technical evaluation requirement under Section L-4.3.1 in lieu of a complete Level 2 design, due to the coordination and Government input required to produce a compliant Level 2 package.
2.Provide the available AutoCAD (.dwg) base files for Building 10250 and surrounding utilities to support accurate Level 1 design development.Attachment 01 (SABER Specifications SOW, Section 1.4.11.3) and Attachment 45 (Statement of Objectives).Level 1 will suffice. If not already completed, an amendment Changing the Seed Project for Honor Guard Building to be a Level 1 Proposal will be released.
183-Nov-25Can the seed project estimate be generated in the Gordian program instead of submitting the 3052 form?General (no SOW or DIV reference)Project estimate to be generated in eGordian per the SABER SOW
193-Nov-25Are project-related vehicles (i.e., pickup trucks and flatbed trucks) considered large vehicular equipment, resulting in their exclusion from the contractor's coefficient?General (no SOW or DIV reference)Contractor to follow SABER contract and eGordian Construction Task Catalog.
203-Nov-25What elements of division 01 (General Requirements) are available for contractor's use outside of the contractor's coefficient?General Requirements Division 01Contractor to follow SABER contract and eGordian Construction Task Catalog.
213-Nov-25If as built drawings can be provided, can the government show the locations of the west lateral sewer lines that are part of the scope?No SOW or DIV referenceAs builts were provided as Attachment 49. But Sewer Line with measurements will be included in future amendment.
223-Nov-25Can the QC, SSHO, and Superintendent be the same person?The ktr is responsible for providing the level of manning that ensures all contract terms are met without exception. The specific manning structure is at the ktrs descretion.
233-Nov-25Will commissioning be required?4.12.7Yes
243-Nov-25Will a third-party commissioning agent be required?4.12.7Yes
253-Nov-25Please confirm if the contractor is permitted to reuse existing ductwork where feasible.4.12.1No
263-Nov-25Please confirm whether all existing lighting in the building, including Rooms 101, 102, 103, 106, 111, and 112, is to be replaced with LED fixtures, or if some is to remain.4.13.3The reception area and locker room will have a dropped ceiling that will match the other ceiling heights in the building. Whatever ceiling height is for dropped ceiling height located in the building will be the standard.
273-Nov-25Please confirm it is the intent of the government to install the ceiling in Room 108/100 to match the other ceiling heights in the building.4.7.7The reception area and locker room will have a dropped ceiling that will match the other ceiling heights in the building. Whatever ceiling height is for dropped ceiling height located in the building will be the standard.
283-Nov-25If yes to the ceiling height question, please confirm ceiling type.Ceiling type is outlined in the SOO.
293-Nov-25The contractor requests CAD files for the building.CAD are not available
303-Nov-25Will a Fire Protection Engineer (FPE) be required?4.10.6Yes
313-Nov-25Please provide photos of the communication room to include communication equipment and the fire alarm panel.Photos provided
323-Nov-25Will the building be occupied during construction?Yes
333-Nov-25If the building will be occupied during construction, please confirm phasing requirements.SOW Section 3Phasing plan will occur after contract award with the new tenants. The primary goal of the project should be the plumbing, then the rooms located on the sides of room 108 and room 100. The space for room 100 and room 108 should be final phasing.
343-Nov-25Is asbestos present in the building?SOW Section 3Test history to be provided.
353-Nov-25Is lead paint present in the building?SOW Section 3Test history to be provided.
363-Nov-25Are any hazardous materials present in the building?Test history to be provided.
373-Nov-25Please provide a hazardous materials report for the building.3.1.1 to 3.1.13Test history to be provided.
383-Nov-25Is there a geotechnical report available?No geotechnical report is available.
393-Nov-25Is the lighting in areas 101, 102, 103, 106, 111, and 112 to remain existing?4.13.3Yes
403-Nov-25Please confirm the casework in the center of Room 108 is to be demolished and not replaced.Section 4.3.23Contractor shall demo per SOO.
413-Nov-25“Contractor shall provide and install new interior walls and R13 insulation” — please confirm which specific new wall assemblies this applies to (e.g., closed office, changing rooms).4.7.32Any area where a new wall is provided per the task order.
423-Nov-25Please confirm the rooms where new flooring is to be provided.4.7.18 4.7.20Extent of carpet and fix and level flooring areas are specfied in appendices that will provided, specifically 3.1.14.
433-Nov-25please identify the exterior walls that are to be demolished.4.3.26DemoShown in appendices 3.1.14.
443-Nov-25Please provide a proposed seed project layout.SOWContractor shall develop new layout per the government SOO and appendices.
453-Nov-25Are asbestos tests for the seed project site available? If not, are potential contractors expected and/or able to obtain asbestos tests for the site?SOWTest history to be provided.
463-Nov-25Please provide the following missing solicitation attachments: 3.1.1.HAZMAT Results 10250 Restrooms part 1

Location: Restrooms at South Corner.

3.1.2.

HAZMAT Results 10250 Restrooms part 2 Location: New Office at East Corner.

3.1.3.

As-Builts page 65 LOCATION & GRADING Overview of the Location, Showing B10250 that used to be a CHAPEL.

3.1.5.

AFGIMS Utilities Snapshot Overview and locations of the Communication lines, Electrical, Natural Gas, Sewer, and water lines.

3.1.6.

Floorplan Conceptual Conceptual preferred layout of the Women 109, Men 110, and the new office.

3.1.7.

Sewer Line with Measurements & Pictures Overview and measurements of the existing and the expected new sewer lines with pictures.

3.1.8.

Asbestos and Lead testing of entire building dated 7 July 2007 3.1.9.

Asbestos and Lead testing for installing air compressor dated 29 September 2011 3.1.10.

Asbestos and Lead testing dated 24 February 2014 3.1.11.

Testing on exterior paint walls dated 6 November 2014 3.1.12.

Mech. Room Report RKMF240010 Solicitation FA4861-16-R-A200 Nellis Air Force Base, Nevada

SOO-3

3.1.13.

Asbestos and Lead testing building history 3.1.14.

B10250 refurbish space conceptual visuals 3.1.15.

B10250 room numbers 3.1.16.

10250 BFP Device replacement 3.1.17.

Double Check Valve AssemblySOWAddressed in Amendment 06
4728-Oct-25Will Seed Project Bldg 10250 be occupied during renovation activities?N/AGeneralYes
4828-Oct-25Will all utilities and electrical power be available to Seed Project Bldg 10250 during renovation activities?N/AGeneralThe sewer is not operational and is part of the project to fix. Any utility outages will have to be coordinated with customer service in 99 CES.
4931-Oct-25Please provide missing attachments listed in the SOO, specifically 3.1.1, 3.1.2, 3.1.5, 3.1.6, 3.1.7, 3.1.8, 3.1.9, 3.1.10, 3.1.11, 3.1.12, 3.1.13, 3.1.14, 3.1.15, 3.1.16, 3.1.17SOO Att missingGeneralAppendices will be provided.
5031-Oct-25RM 111 Cooms closet was unavaible during site visit- please provide detailed photos of current IT equipment, Rack/cabinet size, room dimensions, current IT equipment to include make & model. Include rack/cabinet make & model.SOO 4.14CommunicationsWill be provided.
5131-Oct-254.12.1 states: Demolish all HVAC equipment, exhaust fans, duct work throughout the facility. However, will RM 111 Comms Closet split unit remain as distinct and separate from rest of facility as current?SOO 4.12.1CommunicationsSplit unit will remain distinct. A comm space requires a separate hvac unit per ufc standards.
5231-Oct-25RM 111 Comms Closet door and current cipher lock were not called out for replacement. Is current door and cipher lock acceptable or should matching cipher lock similar to new installation on door 101B- Northside main entrance?N/ACommunicationsCurrent cipher lock acceptable. Combination was uncovered and lock operates.
5331-Oct-25As part of "assist government in relocating the storage equipment"- does the contractor have a storage requirement or will the government provide a storage/relocation location? If contractor has a storage requirement, please state for how long.SOO 4.2.10GeneralPlease include storage, demoltion, and transportation fees for the duration of the project not to exceed period of performance. If an extension of the period of performance occurs, it will be the responsibility of the contractor to provide notification of what items will need to be relocated for storage by the government and at that time, the government will accept the storage, demolition, and transportation responsibility
5431-Oct-25Please define "soundproof" with an STC rating desired to achieve. "The closed office area will be soundproof…"SOO 4.7.22GeneralSTC-50.
5531-Oct-25Reception area- mentioned in 4.4.1, 4.13.9, 4.14.1.3, 4.14.4, 4.14.7 where is it?SOOGeneralRefer to appendix 3.1.14.
5631-Oct-25Please provide current location of Knox Box. Unable to locate while conducting site visit. Is new Knox Box intended to remain in the same location? If not provide new location.SOO 4.10.9FireNo Knox Box is currently present in the facility. The SOO will be updated in a future amendment (if not already completed) to specify placement of a Knox Box near the northside main entrance, positioned 6 feet above the finished floor. The box will be installed either on the wall at the latch side of the door or on the wall nearest to the entry door. Reference pictures have been provided for both wall options
5731-Oct-25Hall 107 exit- does the overhang, railing, and sidewalk leading to the east remain or should it be removed? 4.3.22 states demolish door, but makes no refernce to overhang, railing, or sidewalk. 4.3.26 provides guidance for Block wall immediately outside door 107.Civil / Site / ConcreteOnly demolish door. Contractor has specified incorrect wall. The wall immediately outside of door 107 shall remain. The portion of the wall that will be demolished is the east facing wall that is attached to the iron gate. Only the North side.
582-Nov-25East wall and Gates to be Removed, Does the Chain link fence on the east side of the building remain?SOO 4.3.26FencingFencing to remain.
592-Nov-25If it is the intention to Concrete from the Courtyard Slab up to the building, Will a Storm water drain need to be installed to move water away from the building?SOO 4.3.28Concrete / Storm waterThe courtyard slab will not go up to the building. Please see appendix 3.1.14 for area. The concrete slab may have to be redone to allow for storm water to properly drain into the street, per Nellis IFS standards.
603-Nov-25Does this ceiling grid reference pertain to the Restroom 104 & 105 conversion to officeSOO 4.7.5FinishesYes
613-Nov-25Is the new office in Room 108 to have an STC rating. What will the STC rating be?SOO 4.7.7FinishesSTC-50.
623-Nov-25Does the floor drain the the Mechanical room remain and tie into new Sewer line?N/AFinishesSee updated SOO. Floor drain to remain and tied into new sewer line. Contractor shall fix the drain, if necessary.
633-Nov-25Is it the intention to go back to Epoxy floors in Rooms 100 and 108 after repairs are made?SOO 4.7.20FinishesYes, except for new office area and changing area. Those spaces will be carpeted.
643-Nov-25The ceiling in room 100 is higher than 7' AFF. The SOO calls for 4' X 7' Mirrors running full height. Should the Mirrors be centered between the floor and ceiling?SOO 4.7.33 & 34FinishesNo, contractor to provide mirrors beginning 1 foot above cove base.
653-Nov-25Section 3.1.6 of the SOO references a conceptual floorplan. Can this floorplan be provided?Section 3.1.6 of the SOOFloorplan ConceptualProvided in Amendment 06
663-Nov-25Section 3.1.14 of the SOO references “refurbished space conceptual visuals”. This is also referenced in Section 4.7.28 of the SOO. Can this document be provided?Section 3.1.14 of the SOOB10250 refurbish space conceptual visualsProvided in Amendment 06
673-Nov-25Section 3.1.15 of the SOO references “10250 room numbers”. Can this document be provided?Section 3.1.15 of the SOOB10250 Room NumbersProvided in Amendment 06
683-Nov-25There are many brick walls and windows in the rooms requiring additional receptacles and communication drops. Will surface mount conduit be acceptable?SOO GeneralContractingSurface mount is acceptable in room 102. Recessed shall be used in new furred out walls. Surface mount is acceptable on existing CMU walls.
6929-Oct-25The SOO references the closed office as being “soundproofed,” but does not specify required STC rating or wall/ceiling assembly type. Please confirm the required STC rating and whether ceiling/floor assemblies must also meet this rating.SOO Section 4.7.22FinishesSTC-50.
7029-Oct-25The SOO specifies Monaco MAAP-X or equivalent for fire alarm/mass notification system, and tie-in with the D-21 system and base dispatch. During the site visit, we were unable to confirm the make, model, or physical location of the existing fire alarm control panel (FACP) and its associated infrastructure. Please confirm the make and model of the existing FACP and MNS systems currently in Bldg. 10250 (if any).SOO Sections 4.10.5–4.10.8Fire Alarm/ MNS RequirementsPictures will be provided.
7129-Oct-25The SOO calls for leveling floors in Rooms 100 and 108 and a finish suitable for quick cleaning, but does not specify if sealed concrete or tile/carpet is preferred in these spaces. Please confirm required final flooring finish type in Rooms 100 and 108.SOO Sections 4.7.18–4.7.20Finishes/FlooringNew office area and changing area will be carpeted. The rest of the flooring in room 100 and room 108 will match but be scuff resistant.
7229-Oct-25The SOO states ADA compliance is required "where possible." Is the KTR responsible for full ADA compliance in restrooms, ramps, and entrances under design-build, or are there any site exceptions already approved by Base Civil Engineering?SOO Section 4.3.33Specialties4.4.7 may be the only exception that is required per this task order. All other areas will need to comply with ADA standards.
7329-Oct-25The SOO states the contractor shall “paint exterior per IFS” and “submit color samples,” but no color schedule or base-wide finish standard is included. Please confirm if a standardized base color schedule exists, and if not, whether proposed paint colors must match adjacent buildings.SOO Section 4.7.30Finishes/PaintColor samples are to be provided and then approved. Please refer to Nellis IFS subsection D. Facility exteiors.
7431-Oct-25During the site visit and record drawing review, we were unable to verify the intended new exit point of the lateral from the building or the exact routing of the new line to the manhole. As such, we request the following clarification: What is the exact exit point and direction of the new sewer lateral from Bldg. 10250?SOO 4.17UtilitiesRefer to appendix 3.1.7 for extent that will be provided.
7531-Oct-25There is no current information on the sewer Iateral as far as pipe depth, pipe diameter, and pipe type and length. In the SOO Attachment 3.1.7 ("Sewer Line with Measurements & Pictures") is referenced multiple times but was not included in the bid package documents. If available, please provide ATT 3.1.7 Sewer Line with Measurements & Pictures; otherwise please provide details on the pipe depth, diameter, type and length.SOO AttachmentsUtilitiesIt will be provided.
7631-Oct-25The SOO notes the contractor is to perform a landscaping refresh around the entire building. For bidding purposes please clarify the size of the area to be updated and type of material required.SOO 4.16.4Exterior ImprovementsAny area inside the square area around the facility that is bounded by a block wall on the west side, the end of the ramp of the North end, the chein link fence on the east side, and the block wall located south of the existing concrete pad.
773-Nov-25The SOO references the following attachments: 3.1.1 - 3.1.17. Please provide the following documents to assist with accurate bidding of the Seed Project: 3.1.1, 3.1.2, 3.1.5, 3.1.8-3.1.14, 3.1.16, 3.1.17SOO 3.1.1 - 3.1.17Seed Project AttachmentsThey will be provided.
783-Nov-25The SOW requires AF 103 approval before construction starts but doesn’t specify whether that waiting period counts against the contractor’s schedule.Please clarify whether the AF Form 103 approval timeline (work clearance permit) is included in the performance period.SABER SOW 3.4.4SchedulingClarification, an AF 103 is for any digging to occur outside of a facility. The AF 103 approval is within perormance period. Contractor's are encouraged to coordinate an AF 103 to allow for proper staging in the project.
793-Nov-25For the seed project technical proposal, please confirm whether the design must be submitted to Level 1, Level 2, or both (as illustrated in the sample drawing sets), and whether a 35% design narrative or concept-level design is acceptable.SABER SOW & ATT 46-48The example drawings show both Level 1 and Level 2, but Section L only says “submit design in accordance with SOW and attachments,” which could mean concept or more complete design.Level 1 will suffice. If not already completed, an amendment Changing the Seed Project for Honor Guard Building to be a Level 1 Proposal will be released.
8011/3/25the SOO states to ABATE hazardous material found after award. Please clarify is this would be a differing site condition.SOO 4.3.2Demo DIV 2 existing conditionsNo, all materials that are to be disturbed during construction must be tested prior to disturbing. Previous tests of building materials are provided to contractors so the contractor may estimate the amount of hazardous materials present and factor in the cost to abate in their estimate.
8111/3/25should the floor be cut and opened so sewer lines feeding rooms 104 and 105 can demolished all the way back to the main sewer and capped to insure no sewer gasses can escape through the floor.Demo DIV 2 existing conditionsYes.
8211/3/25please define what the antifreeze system is? Is this part of the buildings fire suppression?SOO 4.3.15Demo DIV 2 existing conditionsAfter site visit, it appears that the anti-freeze is related to the fire sprinkler system. It is unclear if it is still needed for current fire sprinkler system or is an obsolete portion of an older system. Regardless, Contractor shall relocate the system.
8311/3/25what is the concrete slurry covering over the type II fill? Will there be any material placed above the slurry to finish the area? is this inside the facility or outside?SOO 4.4.3ConcreteThis is specifiying the trench for plumbing work. Also, see SOO section 4.4.6.
8411/3/25what room numbers are the changing roomsSOO 4.6.5openingsThe changing rooms will be located in a new space to in room 100.
8511/3/25in what's rooms or are all windows in the building to be replaced?SOO 4.6.6openingsRoom 108, room 103, room 102, room 109, and room 112.
8611/3/25will the logo be just a decal adhered to the frosted glass?SOO 4.6.8openingsPer SABER SOO 4.5.8 "The emblem shall be etched into glass".
8711/3/25Please confirm the changing room is a combo office changing room that will be converted from the current restrooms 104 and 105?SOO 4.7.7Finishes
8811/3/25can an approximate SF be given for bid purposes? Who will define what is damaged enough to replace?SOO 4.7.8FinishesPer SABER SOO 4.7.9 "4.7.9.Contractor shall replace 80% of the existing ceiling tiles and existing SLT ceiling grid in the facility. "
8911/3/25Is this line requesting all new ceiling tile throughout the facility 10250? there currently is verry littleSOO 4.7.10FinishesNo. New tgrid and ceiling tiles will be installed in reception area and changing area.
9011/3/25old concrete and will look warn compared to new concrete placed over the new plumbing trenches will this be acceptable or should the entire floor in the restrooms be cut out and poured new for a constant finish and look?SOO 4.7.14FinishesContractor to pour concrete leveler and then seal to match the new areas. See revised SOO.
9111/3/25confirming this is just requesting a clear spray applied finish over raw concrete and not a ground concrete floor with polished clear finish.SOO 4.7.14FinishesClear spray applied finish over raw concrete. See revised SOO.
9211/3/25please define in more detail what is being requested. Is this for the bathroom floors that are being requested to be left sealed concrete? Is this just requesting that the transition from existing concrete to new concrete be smooth with no high or low spots?SOO 4.7.17FinishesCorrect.
9311/3/25is there an STC sound proofing level that is required?SOO 4.7.22FinishesSTC-50.
9411/3/25Will this control be done by JCI and be accomplished by VAV?SOO 4.7.24FinishesYes
9511/3/25paint the entire building exterior? Please confirmSOO 4.7.30FinishesYes
9611/3/25is this requesting R13 in only newly framed walls or requesting R13 be added to new and existing interior walls?SOO 4.7.32FinishesOnly framed walls
9711/3/25is this requesting filters at each return in the ceiling?4.12.15No. On each HVAC unit a filter will be provided.
9811/3/25where new comm drops are being requested in existing room not being renovated will the EMT be surface mounted?4.14EMT not to be surface mounted on dry wall. EMT may be surface mounted if mounted on cmu. All EMT needed to be installed in room 102 shall be installed surface mounted.
9911/3/25where new comm drops are being requested will receptacles for power be required to be added? Will they need to be dedicated and will they be surface mounted in rooms not being renovated?4.14Follow SOO for direction of power that is needed in new office that takes up the previous location of rooms 104 and 105 and the new reception area that takes up the area located in the Southeast corner of room 108. Follw SOO for dedicated circuits to be installed. Please see revised SOO for surface mount direction.
10011/3/25is the SOO requesting all existing comm not touched during this project be retested by the contractor?4.14.8The SOO is requesting that the communication installers be certified to touch comm equipment. To be able to ensure new comm is properly incorporated into exsiting comm infrastructure.
10111/3/25in soo requesting only 2x2 grid in new office space and not in locker rooms or closed office4.7.6/4.7.7Finishes2x2 grid and ceiling tiles in new office space (replacing the bathrooms located on Southeast corner of building), new closed office area, and changing area. Refer to attachment 3.1.14 for areas.
10211/3/25Where will the storage equipment in rooms 100 and 108 be relocated to?4.2.10Gen. RequirementsThe contractor shall include storage, demolition, and transportation cost esimates in their design.
10311/3/25There is no mention of the rolling file storage system that is located in the building, Are these to be included in the items to be relocated?4.2.10Gen. RequirementsThe rolling storage system is one item that will need to be relocated (demolished or transported to another building).
10411/3/25Will the ceiling tiles have a tegular reveal and will they have a NRC requirement?4.7.6/4.7.7FinishesYes.
10511/3/25Regarding the large 11' tall 2'6" wide windows on the south facing exterior wall, when replacing these does the government want the contractor to match the existing number of small windows per each of the 7 locations or one large pane window in each opening?4.6.6FinishesMatch existing number.
10611/3/25There is existing drywall and base trim damage to the lower 1 foot section of the walls in Room 102, does the government want this repairs as part of the scope of work?4.7.FinishesYes, see revised SOO.
10711/3/25The transformer concrete pad located on the east side of the building appears to have settled and is no longer level, Does the government want the transformer pad removal and replacement to be included in the scope of work?4.13.ElectricalNo.
10811/3/25SOO 4.11.16 mentions to snake and jet existing sewer in B101250 up to the main. SOO 4.11.18 mentions to provide a new sewer line to the main. What is the intent of SOO 4.11.16 if new sewer line is being installed per SOO 4.11.18?4.11.16/4.11.18PlumbingRefer to 4.11.20 for reason to jet existing sewer line.
10911/3/25Attachment 3.1.7 mentioned in SOO 4.11.18 was not provided in contract documents.4.11.18PlumbingWill be provided.
11011/3/25Will the building be occupied at all during construction ?Yes
11111/3/25During the site walk there was no access to the Comm Room. Can the gov't provide picture of the Comm Rm or can another site walk be held to investigate this room?Communication RoomPictures will be provided.
11211/3/25Please confirm all CAT6 requested in SOO is unshielded.4.14CommunicationsUnshielded.
11311/3/25Can the gov't provide a visual aid to show exactly what part of this block wall is being demoed in SOO 4.3.26?4.3.26Existing ConditionsAttachment will be provided in 3.1.14.
11411/3/25SOO 4.3.29 mentions to demo all existing signs and replace. Can the gov't clarify what signs contractor is to demo/replace? All interior and exterior signage? Room signs, building signs, exit signs?4.3.29Existing conditionsAll interior and exterior building signs. Any fire evacuation signs shall be removed and replaced.
11511/3/25soo 4.2.4 mention temp wall screens to be used during renovation, will the facility be occupied during renovation4.2.4Gen. RequirementsYes
11611/3/25soo 4.3.24 how much of existing ramp is being demolished4.3.24Gen. RequirementsAttachment 3.1.14 provides extent of demoltion.
11711/3/25s00 4.3.27 what is the lineal ft of curb and gutter will be demolished, there is also a metal pipe swing gate arm at that location does gov. want this demolished as well4.3.27Gen. RequirementsApproximately 12.5 feet.
11811/3/25soo 4.3/28 does gov want the chain link fence demolish in this area also4.3.28Gen. RequirementsChain link fence to remain.
11911/3/25SOO 4.3.29 does gov. want the 59 rescue squad sign returned to them and do we replace that sign with a new sign for the Honor Guard, if so do you have want that sign is to say from the user?4.3.29Gen. RequirementsContractor to dispose of sign. Replace with new sign. Contractor to receive verbiage after contract award.
12011/3/25soo 4.3.33 missing conceptual floor plans4.3.33Gen. RequirementsAttachment addressed in previous amendment.
12111/3/25soo 4.4.8 how far are we removing gravel on south side of bldg. 102504.4.8ConcreteAttachment 3.1.14 provides the area.
12211/3/25soo 4.7.20 does gov want the entire concrete floor fix and level in rooms 100 and 108 or just where the new offices/changing room are located4.7.20FinishesEntire floor. The flooring is not concrete in rooms 100 and rooms 108. Additionally, changing area and new office area located in room 108 and room 100 will be carpeted.
12311/3/25soo 4.12.1 does gov. want screen cmu wall demo around the existing havc equip that is being demolished4.12.1HVACNo
12411/3/25soo 4.13 does gov want existing exterior lights demolished and replaced4.13ElectricalYes
12511/3/25soo 4.13.13 how many dedicated circuits does the gov want in room 112 for appliances4.13.13Electrical3
12611/3/25soo 4.14.13 what is the location of the new reception area4.14.13CommunicationProvided in attachment 3.1.14.
12711/3/25soo 4.16.2 how much asphalt does the gov want sealed on north side of bldg. 102504.16.2Earth WorkSee attachment.
12811/3/25soo 4.16.3 how many parking space are being painted on the eastside of bldg. 10250 and north side of bldg. 102504.16.3Earth WorkArea indicated in attachment 3.1.14. Match adjacent existing space dimensions
12911/3/25soo 4.16.4 does the gov. want all health plant protected on exterior of bldg. 10250 during construction4.16.4Earth WorkNo. Remove all plants.
13011/3/25SOO 4.12.6 states that Bldg. 10250 contains an existing Series Network Engine. During the site walk on 10/29, it was confirmed that Bldg. 10250 does not contain a JCI SNE. Please confirm that JCI will be furnishing and installing a new SNE for Bldg. 10250.4.12.6ControlsThis is an incorrect interpretation. 4.12.6 states that the contractor must ensure the version of the Network Automated Engine matches the version of the existing Metasys ADX server that operates at the EM CS control office at Nellis AFB. Contractor shall include the cost to have JCI supply the SNE for new hvac units.
13111/3/25There are currently no JCI controls in Bldg. 10250; the SOO requires us to connect to the Base wide LAN for integration to the existing EMCS ADX Server. Please confirm that there is an IP drop within Bldg. 10250 that will enable us to connect to the existing Nellis ADX Server.4.12.6ControlsIf not available, contractor shall install.
13211/3/25Section 3.1.6 of the SOO references a conceptual floorplan. Can this floorplan be provided?3.1.6ElectricalAttachments were attached in Amendment 006
13311/3/25Section 3.1.14 of the SOO references “refurbished space conceptual visuals”. This is also referenced in Section 4.7.28 of the SOO. Can this document be provided?3.1.14ElectricalAttachments were attached in Amendment 006
13411/3/25Section 3.1.15 of the SOO references “10250 room numbers”. Can this document be provided?3.1.15ElectricalAttachments were attached in Amendment 006
13511/3/25There are many brick walls and windows in the rooms requiring additional receptacles and communication drops. Will surface mount conduit be acceptable?ElectricalSurface mount is acceptable.
13611/3/25Is the FRP to be a standard white, orange peel texture or smooth finish?4.7.1Finishesstandard white
13711/3/25Will all Level 4 finish be smooth wall?4.7.12Finishesyes
13811/3/25There is an existing stainless steel box located adjacent to the buildings south side entry door that has a conduit attached that runs throughout the wall to the interior. Does the government want this to stay in place for future use, or should it be demolished and the exterior wall repaired?ElectricalSOO will be updated. Stainless steel box and conducting conduit shall be demolished Exterior Wall and interior shall be repaired per SABER SOO 4.3.32.
13911/3/25SOO 4.3.34 states to demolish all components of existing fire alarm system except panel shall remain. Is the current fire alarm system operational? If so, does the system need to remain operational until the new system is ready to be switched over? Since existing panel is to be reused, there will be some small down time while switching to the new system. Are there procedures needed for this downtime such as fire watch?4.3.34Fire Alarm/General RequirementsSystem shall remain operational for as long as possible, afterwards, facility shall be put on fire watch.
14011/3/25SOO 4.3.34 states existing fire alarm control panel to remain. This panel was unavailable to view during the walkthrough. Can pictures, manufacturer, and model of fire alarm panel and fire alarm closet/space be provided? Are the As-builts correct with panel being a Monaco M-2?4.3.34Fire Alarm/General RequirementsPicutres will be provided
14111/3/25SOO 4.3.34 If existing panel is Monaco M-2 as shown in as-builts, this panel contradicts the Nellis IFS for Fire Protection Requirements E.5. Should the fire alarm panel be replaced to meet the Nellis IFS for Fire Protection Requirements E.5 as stated as a requirement in Scope Fire Suppression 4.10.5?4.3.34 / 4.10.5Fire Alarm/General RequirementsYes
14211/3/25SOO 4.10.10 states to install new remote annunciator with control functions same as the main control panel. If manufacturer does not have annunciator with these functions available (Monaco), will an LOC/RDU be acceptable?4.10.10Fire AlarmYes
14311/3/25Will the new communication cabling require a new communications cabinet? During the site visit, we were unable to determine what type of existing communications cabinet is currently in place. Is there adequate space available for the new communication cabling?4.14.CommunicationsAdquate space is available.
14411/3/25Will the dedicated circuit for the communications cabinet be provided as part of the new installation?4.14.CommunicationsNew cabinet should not be needed. Therefore no decidicated circuit needed.
14511/3/25Does the existing communications cabinet include a ground bar suitable for bonding new cabling and equipment?4.14.CommunicationsYes, see pictures provided of comm room.
14611/3/25will an extension to the proposal deadline be granted. the amount of RFI the directly impact seed design and pricing there will not be enough time for a through coefficient buildup. Also the missing attachments that were to be sent with the SOO minimal work to be accomplished pre site visit.Missing Attachments have been uploaded; current Proposal deadline as per Amendment 009 is 5 Feb 2026.
147Does the government want the split unit located inside the comm room to be replaced as well?4.12HVACNo. It appeared to be in working order.