DD1423-2__CDRLs_A027_A028_ITCC_II.pdf

PDF 281 KB Posted

Attached to
Information Technology Capabilities Contract (ITCC) II Federal contract opportunity
Solicitation number
FA4600-14-R-0017
Issued by
Department of the Air Force Air Combat Command

About this file

This Contract Data Requirements List (CDRL) outlines two data items required under the Information Technology Capabilities Contract (ITCC) II awarded by the United States Air Force Air Combat Command. The contractor must submit a monthly Service Delivery Invoice and Payment Report to the United States Strategic Command detailing costs by the structure specified in the contract. A one-time Transition Plan is also required and must be delivered to the United States Strategic Command no later than 60 days prior to the transition start date. Both data items will be delivered electronically and in hard copy, with the invoice requiring two hard copies and the transition plan one hard copy to the designated offices.

CDRL

View the file

Other files for this federal contract opportunity

Other files attached to Information Technology Capabilities Contract (ITCC) II, newest first.
File Type Posted
20141110_Q A.pdf PDF
FA4600-14-R-0017-0005.pdf PDF
20141031_Q A.pdf PDF
ITCC__II_Q A_20141028.pdf PDF
Section_J _Attachment_15 _Contractor_Cost_Price_Model.xls XLS spreadsheet
DID_Contr_Prop_Mgmt_Plan_CCSS_OT-14-37511.docx DOCX document
DD1423-2__CDRLs_A005_A006_ITCC_II.pdf PDF
DD1423-2__CDRLs_A027_A028_ITCC_II.pdf PDF
DD1423-2__CDRLs_A007_A008_ITCC_II.pdf PDF
DD1423-2__CDRL_A021_Appendix_SDO_to_PWS_Mapping_Matrix.xlsx XLSX spreadsheet
DD1423-2__CDRLs_A019_A020_ITCC_II.pdf PDF
DD1423-2__CDRLs_A025_A026_ITCC_II.pdf PDF
DD1423-2__CDRL A021 Appendix SDO to PWS Mapping Matrix.xlsx XLSX spreadsheet
DID CCSS Security and Training OT-14-37504.docx DOCX document
Section_J _Attachment_13 _Subcontracting_Teaming_Partner_Consent_Ltr.docx DOCX document
DID Price Breakdown Report OT-14-37509.docx DOCX document
DD1423-2__CDRLs_A013_A014_ITCC_II.pdf PDF
DD1423-2__CDRL_A023 Appendix Metrics.docx DOCX document
Section_J _Attachment_4 _Integrated_Team_Process_(ITP)_User's_Guide.doc DOC document
DD1423-2__CDRLs_A023_A024_ITCC_II.pdf PDF
DID Config Mangament Plan OT-14-37502.docx DOCX document
DD1423-2__CDRLs_A017_A018_ITCC_II.pdf PDF
DID Config Mangament Drawings OT-14-37505.docx DOCX document
DD1423-2__CDRLs_A015_A016_ITCC_II.pdf PDF
DID Tech Refresh Plan OT-14-37503.docx DOCX document
DD1423-2__CDRLs_A003_A004_ITCC_II.pdf PDF
DID Life-Cycle Mangament Plan OT-14-37501.docx DOCX document
DID_Life-Cycle_Mangament_Plan_OT-14-37501.docx DOCX document
DD1423-2__CDRLs_A009_A010_ITCC_II.pdf PDF
DD1423-2__CDRLs_A009_A010_ITCC_II.pdf PDF
DD1423-2__CDRLs_A017_A018_ITCC_II.pdf PDF
Section_J _Attachment_19_SB_Subcontracting_Plan_Review_Checklist.xls XLS spreadsheet
DD1423-2__CDRLs_A015_A016_ITCC_II.pdf PDF
DD1423-2__CDRLs_A011_A012_ITCC_II.pdf PDF
DID Life-Cycle Mangament Plan OT-14-37501.docx DOCX document
DID SD Invoice and Payment Report OT-14-37512.docx DOCX document
DD1423-2__CDRLs_A021_A022_ITCC_II.pdf PDF
DID_Config_Mangament_Drawings_OT-14-37505.docx DOCX document
DID Cybersecurity Documentation OT-14-37508.docx DOCX document
DD1423-2__CDRLs_A011_A012_ITCC_II.pdf PDF
DID Tech Refresh Plan OT-14-37503.docx DOCX document
DID Contr Prop Mgmt Plan CCSS OT-14-37511.docx DOCX document
Section_J _Attachment_16 _OFCCP_clearance_request_documentation.doc DOC document
DD1423-2__CDRLs_A019_A020_ITCC_II.pdf PDF
Section_J _Attachment_9 _PP_Information_Doc_(tables).docx DOCX document
Section_J _Attachment_1 _Appendix_A _CPIF_Workbook.xlsx XLSX spreadsheet
DID_CCSS__Security_and_Training_OT-14-37504.docx DOCX document
DID SD Invoice and Payment Report OT-14-37512.docx DOCX document
DD1423-2__CDRLs_A007_A008_ITCC_II.pdf PDF
DD1423-2__CDRLs_A015_A016_ITCC_II.pdf PDF
Show all 50

Information Technology Capabilities Contract (ITCC) II has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423-2, AUG 96

CONTRACT DATA REQUIREMENTS LIST

(2 Data Items)

PREVIOUS EDITION MAY BE USED.

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page ____ of ____ Pages

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

DD FORM 1423-2 (BACK), AUG 96

line_item: X999
exhibit: A
xtdp: Off
xtm: Off
othercat: Management
system: ITCC II
ctr_no:
contr:
data_item1: A027
title1: Service Delivery Invoice and Payment Report
sub1:
auth1: OT-14-37512
ref1: PWS Sections 3.1, 3.1.8, 6, 6.2
req_ofc1: USSTRATCOM/J645
dd250_1: LT
appcode1: N/A
dist1: C
freq1: Monthly
asof1: See Item 16
firstsub1: See Item 16
subsub1: See Item 16
addr1_1: USSTRATCOM/J645
draft1_1:
reg1_1: 2
repro1_1:
addr1_2:
draft1_2:
reg1_2:
repro1_2:
addr1_3:
draft1_3:
reg1_3:
repro1_3:
addr1_4:
draft1_4:
reg1_4:
repro1_4:
addr1_5:
draft1_5:
reg1_5:
repro1_5:
addr1_6:
draft1_6:
reg1_6:
repro1_6:
addr1_7:
draft1_7:
reg1_7:
repro1_7:
addr1_8:
draft1_8:
reg1_8:
repro1_8:
addr1_9:
draft1_9:
reg1_9:
repro1_9:
addr1_10:
draft1_10:
reg1_10:
repro1_10:
addr1_11:
draft1_11:
reg1_11:
repro1_11:
addr1_12:
draft1_12:
reg1_12:
repro1_12:
addr1_13:
draft1_13:
reg1_13:
repro1_13:
addr1_14:
draft1_14:
reg1_14:
repro1_14:
totaldraft1: 0
totalreg1: 2
totalrepro1: 0
rmks1: The Service Delivery Invoice Report shall include cost reporting IAW the Cost Reporting Structure specified in Section J Attachment 17.

- Format to be mutually agreed to during phase-in.

Items 11-13:

- Delivery of the first report 90 days after assumption of full responsibility, with subsequent deliveries within 7 workdays of the beginning of the month reporting the month previous.

Item 14:

- One hard copy and one soft copy on CD. Delivery of the hard copy and CD shall be submitted to the ITCC II PMO no later than close of business on the day the CDRL is due.

group1:
totalprice1:
data_item2: A028
title2: Transition Plan
sub2:
auth2: OT-14-37513
ref2: PWS Section 4.1
req_ofc2: USSTRATCOM/J642
dd250_2: LT
appcode2: N/A
dist2: C
freq2: One Time
asof2: See Item 16
firstsub2: See Item 16
subsub2: N/A
addr2_1: USSTRATCOM/J645
draft2_1:
reg2_1: 1
repro2_1:
addr2_2:
draft2_2:
reg2_2:
repro2_2:
addr2_3:
draft2_3:
reg2_3:
repro2_3:
addr2_4:
draft2_4:
reg2_4:
repro2_4:
addr2_5:
draft2_5:
reg2_5:
repro2_5:
addr2_6:
draft2_6:
reg2_6:
repro2_6:
addr2_7:
draft2_7:
reg2_7:
repro2_7:
addr2_8:
draft2_8:
reg2_8:
repro2_8:
addr2_9:
draft2_9:
reg2_9:
repro2_9:
addr2_10:
draft2_10:
reg2_10:
repro2_10:
addr2_11:
draft2_11:
reg2_11:
repro2_11:
addr2_12:
draft2_12:
reg2_12:
repro2_12:
addr2_13:
draft2_13:
reg2_13:
repro2_13:
addr2_14:
draft2_14:
reg2_14:
repro2_14:
totaldraft2: 0
totalreg2: 1
totalrepro2: 0
rmks2: Block 11-12:

- Delivery of the first report due no later than 60 days prior to transition start.

Block 14:

- Electronic posting to a Government owned server constitutes delivery. An e-mail notice of the posting shall be submitted to the ITCC II PMO by close of business on the day the CDRL is posted. E-mails shall be submitted to personnel as directed by the Contracting Officer.

Note: In no government response or comments are provided within 45 days of the delivery of this document, it will be considered final.

group2:
totalprice2:
prep_by:
prep_date:
app_by:
app_date:
Page: 1
of_pages:
app: Adobe Professional 8.0
Reset:

File details come from the government source that posted it. Updated .