SOW ATCH 7

View the file

Other files for this federal contract opportunity

Other files attached to SABER IDIQ - Joint Base Charleston, SC, newest first.
File Type Posted
Amendment_0003 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
_4_Qs_ _As _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7__1_Sample_Project_-_SOW_Atch_14_-_Bldg_84 _Roof__Summary_Rpt_2.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_12_-_Bldg_84 _Roof_Survey.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_11-_Bldg_84 _Addendum__1 _7_Dec_15.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_13_-_Bldg_84 _Roof_Summary_Rpt_1.pdf PDF
Amendment_0002 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_8 __2_Sample_Project__-_SOW_Atch_6_-_Bldg_1 _Addendum__1 _7_Dec_15.pdf PDF
SOW__Attachment_12_-_Addendum__1 _7_Dec_15.pdf PDF
_2_Qs_ __As_FA4418-16-R-0001_SABER_IDIQ.pdf PDF
Arch_E-36x48-Border.dwg DWG drawing
_3_Qs_ _As_FA4418-16-R-0001_SABER_IDIQ.pdf PDF
Ansi_E-34x44-Border.dwg DWG drawing
Atch_7 __1_Sample_Project_-_SOW_Atch_7_Bldg_84_-_As-builts_Pt_5.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_4_-_Bldg_84_-_As-builts_Pt_2.pdf PDF
Atch_7 ___1_Sample_Project_-_SOW_Atch_9_-_Bldg_84_-_As-builts_Pt_7.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_4_-_Bldg_1_-_As-builts-Current.pdf PDF
Atch_8 __2_SampleProject_-_SOW_Atch_5_-_Bldg_1_-_As-builts-Original.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_5_-_Bldg_84_-_As-builts_Pt_3.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_8_Bldg_84_-_As-builts_Pt_6.pdf PDF
_1_Qs_ _As _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_3_-_Bldg_84_-_As-builts_Pt_1.pdf PDF
Amendment_0001 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_6_-_Bldg_84_-_As-builts_Pt_4.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_10_Bldg_84_-_As-builts_Pt_8.pdf PDF
Site_Visit_Min _Attendees-SABER.pdf PDF
Atch_9 _Past_Performance_Projects_List.docx DOCX document
Atch_3 _WD_SC29_Berkeley_5-22-15.pdf PDF
SOW_Attachment_2_-_JBCGS_28_31_76_Interior_Fire_Alarm_System_ _Mass_Noti....pdf PDF
SOW_Attachment_3_-_JBC_Cable_Management_Policy.pdf PDF
FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_4 _WD_SC30_Charleston_5-22-15.pdf PDF
SOW_Attachment_6_-_JBCGS_01572_-_Waste_Management.pdf PDF
SOW_Attachment_1_-_JBC_ACP.PDF PDF
Atch_7 __1_Sample_Project_-_SOW_-_Bldg_84 _1_Aug_15.pdf PDF
SOW_Attachment_4_-_JBCGS_01501_-_Environmental.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_-_Bldg_1 _17_Aug_15.pdf PDF
SOW_Attachment_5_-_JBCGS_01540_-_Green_Procurement.pdf PDF
Atch_6 _Green_Procument_Form.pdf PDF
Atch_5 _WD_SC31_Dorchester_5-22-15.pdf PDF
SOW_Attachment_10_-_UFGS_01_45_00_-_Quality_Control.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_1_-_Bldg_1_Existing_Floor_Plan.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_3_-_Bldg_1_Asbestos_Survey.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_2_-_Bldg_1_Conceptual_Floor_Plan.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_1_-_Bldg_84_Floorplan.pdf PDF
SOW_Attachment_11_-_UFGS_Contractor_Special_Conditions_Safety_Requirements.pdf PDF
Atch_2 _WD_SC23_Orangeburg_1-02-15.pdf PDF
SOW_Attachment_9_-_NPTU_Contractor_Special_Conditions.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_2_-_Bldg_84_Asbestos_Survey.pdf PDF
SOW_Attachment_8_-_Brig_Security_Requirements.pdf PDF
Show all 50

SABER IDIQ - Joint Base Charleston, SC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01575 Page 1

SECTION 01575 CAFB

TEMPORARY ENVIRONMENTAL CONTROLS

1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910 Occupational Safety and Health Standards

40 CFR 122.26 EPA National Pollutant Discharge Elimination

System Permit Regulations

40 CFR 241 Guidelines for Disposal of Solid Waste

40 CFR 243 Guidelines for the Storage and Collection of

Residential, Commercial, and Institutional Solid Waste

40 CFR 258 Subtitle D Landfill Requirements

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Generators of Hazardous Waste

40 CFR 263 Transporters of Hazardous Waste

40 CFR 264 Owners and Operators of Hazardous Waste

Treatment, Storage, and Disposal Facilities

40 CFR 265 Interim Status Standard for Owners and

Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 266 Management of Specific Hazardous Waste and

Specific Types of Hazardous Waste Management Facilities

40 CFR 268 Land Disposal Restrictions

40 CFR 279 Used Oil Regulations

40 CFR 300 National Oil and Hazardous Substances

Pollution Contingency Plan

40 CFR 372-SUBPART D EPA Toxic Chemical Release Reporting

Regulations

49 CFR 173 Shipments and Packagings

SECTION 01575 Page 2

ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 832-R-92-005 Storm Water Management for Construction

Activities

1.2 DEFINITIONS

1.2.1 Sediment

Soil and other debris that have eroded and have been transported by runoff water or wind.

1.2.2 Solid Waste

Garbage, refuse, debris, sludge, or other discharged material (except hazardous waste as defined in paragraph entitled "Hazardous Waste" or hazardous debris as defined in paragraph entitled "Hazardous Debris"), including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.

Material not regulated as solid waste are: nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended;

suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges; regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.

a. Green waste: The vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.

b. Surplus soil: Existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included.

c. Inert construction and demolition debris: Broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials may not be re-inforced with or contain ferrous wire, rods, accessories and weldments.

d. Wood: Dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated and/or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included.

e. Scrap metal: Scrap and excess ferrous and non-ferrous metals such as re-inforcing steel, structural shapes, pipe and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.

f. Paint cans: Metal cans that are empty of paints, solvents, thinners and adhesives. If permitted by the paint can label, a thin dry film may remain in the can.

SECTION 01575 Page 3

1.2.3 Debris

Non-hazardous solid material generated during the construction, demolition, or renovation of a structure which exceeds 2.5 inch particle size that is: a manufactured object; plant or animal matter; or natural geologic material (e.g. cobbles and boulders). A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.

1.2.4 Hazardous Debris

As defined in paragraph entitled "Debris" of this section, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) per 40 CFR 261; or debris that exhibits a characteristic of hazardous waste per 40 CFR 261.

1.2.5 Chemical Wastes

This includes salts, acids, alkalies, herbicides, pesticides, and organic chemicals.

1.2.6 Garbage

Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1.2.7 Hazardous Waste

Hazardous waste as defined in 40 CFR 261 or as defined by applicable State and local regulations.

1.2.8 Oily Waste

Petroleum products and bituminous materials.

1.2.9 Class I Ozone Depleting Substance (ODS)

Class I ODS is defined in Section 602(a) of The Clean Air Act and includes the following chemicals:

chlorofluorocarbon-11 (CFC-11) chlorofluorocarbon-213 (CFC-213) chlorofluorocarbon-12 (CFC-12) chlorofluorocarbon-214 (CFC-214) chlorofluorocarbon-13 (CFC-13) chlorofluorocarbon-215 (CFC-215) chlorofluorocarbon-111 (CFC-111) chlorofluorocarbon-216 (CFC-216) chlorofluorocarbon-112 (CFC-112) chlorofluorocarbon-217 (CFC-217) chlorofluorocarbon-113 (CFC-113) halon-1211 chlorofluorocarbon-114 (CFC-114) halon-1301 chlorofluorocarbon-115 (CFC-115) halon-2402 chlorofluorocarbon-211 (CFC-211) carbon tetrachloride chlorofluorocarbon-212 (CFC-212) methyl chloroform

1.3 SUBMITTALS

1.3.1 Preconstruction Submittals

SECTION 01575 Page 4

1.3.1.1 ENVIRONMENTAL PROTECTION PLAN

Five days after the award of contract, the Contractor shall meet with the Contracting Officer to discuss the proposed Environmental Protection Plan and develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural resources, required reports, and other measures to be taken. The Environmental Protection Plan shall be submitted in the following format and shall, at a minimum, address the following elements (also refer to paragraph entitled "Protection of Natural Resources" in this section):

a. Description of the Environmental Protection Plan

(1) General overview and purpose

(2) General site information

b. Protection of Natural Resources

(1) Land resources

(2) Tree protection

(3) Replacement of damaged landscape features

(4) Temporary construction

(5) Stream crossings

(6) Fish and wildlife resources

(7) Wetland areas

c. Protection of Historical and Archaeological Resources

(1) Objectives

(2) Methods

d. Storm Water Management and Control

(1) Ground cover

(2) Erodible soils

(3) Temporary measures

(a) Mechanical retardation and control of runoff

(b) Vegetation and mulch

(4) Storm Water Pollution Prevention Measures and Notice of Intent 40 CFR 122.26, EPA 832-R-92-005. Provide a "Storm Water Pollution Prevention Plan" (SWPPP) for the project. The SWPPP shall meet the requirements of the EPA general permit for storm water discharges from construction sites. Submit the SWPPP along with any required Notice of Intents, Notice of Termination, and appropriate permit

SECTION 01575 Page 5 fees, via the Contracting Officer, to the appropriate agency for approval, a minimum of 14 calendar days prior to the start of construction. A copy of the approved SWPPP shall be kept at the construction on-site office, and continually updated as regulations require to reflect current site conditions.

(a) Identify potential sources of pollution which may be reasonably expected to affect the quality of storm water discharge from the site.

(b) Describe and ensure implementation of practices which will be used to reduce the pollutants in storm water discharge associated with industrial activity at the construction site.

(c) Ensure compliance with terms of EPA general permit for storm water discharge.

(d) Select applicable management practices from EPA 832-R-92-005.

(e) Provide completed copy of "Notice of Intent" and "Notice of Termination" except for effective date.]

e. Prevention of Releases to the Environment

(1) Procedures to prevent releases to the environment

(2) Notifications in the event of a release to the environment

f. Protection of the Environment from Waste Derived from Contractor Operations

(1) Control and disposal of solid and sanitary waste

(2) Control and disposal of hazardous waste (Hazardous Waste Management Section)

This item shall consist of the management procedures for all hazardous waste to be generated. The elements of those procedures shall coincide with the Activity Hazardous Waste Management Plan.

A copy of the Activity Hazardous Waste Management Plan will be provided by the Contracting Officer. As a minimum, include the following:

(a) Procedures to be employed to ensure a written waste determination is made for appropriate wastes which are to be generated;

(b) Sampling/analysis plan;

(c) Methods of hazardous waste accumulation/storage (i.e., in tanks and/or containers);

(d) Management procedures for storage, labeling, transportation, and disposal of waste (treatment of waste is not allowed unless specifically noted);

SECTION 01575 Page 6

(e) Management procedures and regulatory documentation ensuring disposal of hazardous waste complies with Land Disposal Restrictions (40 CFR 268);

(f) Management procedures for recyclable hazardous materials such as lead-acid batteries, used oil, and the like;

(g) Used oil management procedures in accordance with 40 CFR 279;

(h) Pollution prevention\hazardous waste minimization procedures;

(i) Plans for the disposal of hazardous waste by permitted facilities;

(j) Procedures to be employed to ensure all required employee training records are maintained.

Fourteen days after the environmental protection meeting, submit the proposed Environmental Protection Plan for further discussion, review, and approval. Commencement of work shall not begin until the environmental protection plan has been approved.

1.3.1.2 Dirt and Dust Control Plan

Submit truck and material haul routes along with a plan for controlling dirt, debris, and dust on base roadways. As a minimum, identify in the plan the subcontractor and equipment for cleaning along the haul route and measures to reduce dirt, dust, and debris from roadway.

1.3.2 Test Reports

1.3.2.1 Laboratory Analysis

Submit a copy of a laboratory analysis of solid waste and debris with the potential of becoming classified as a hazardous waste (i.e., abrasive/sand blasting debris, etc.). Waste stream determinations are required at the point of generation and must sufficiently document whether the waste will be a solid waste, hazardous waste, or Resource Conservation and Recovery Act (RCRA) exempt waste. Determinations must use EPA approved methods and provide written rational for whether the waste is classified as hazardous or non-hazardous. The Contractor shall bear the cost of the waste stream determinations, and the Contracting Officer reserves the right to request waste stream determinations on questionable waste streams.

1.3.3 Closeout Submittals

Some of the records listed below are also required as part of other submittals. For the "Records" submittal, maintain on-site a separate three-ring Environmental Records binder and submit at the completion of the project. Make separate parts to the binder corresponding to each of the applicable sub items listed below.

Preconstruction survey

Solid waste disposal permit

Waste determination documentation

SECTION 01575 Page 7

Disposal documentation for hazardous and regulated waste

Contractor 40 CFR employee training records

Regulatory notification

Erosion and sediment control inspection reports

Solid waste disposal report

1.3.3.1 Preconstruction Survey

Perform a preconstruction survey of the project site with the Contracting Officer, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record.

1.3.3.2 Solid Waste Disposal Permit

Submit one copy of a local permit or license showing such agency's approval of the disposal plan before transporting wastes off Government property.

1.3.3.3 Waste Determination Documentation

The Contractor shall complete a Waste Determination form (provided at the pre-construction conference) for all contractor derived wastes to be generated. The waste determination must be based upon either a constituent listing from the manufacturer used in conjunction with consideration of the process by which the waste was generated, EPA approved analytical data, or laboratory analysis (Material Safety Data Sheets (MSDS) by themselves are not adequate). All support documentation must be attached to the Waste Determination form. As a minimum, a Waste Determination form must be provided for the following wastes (this listing is not all inclusive): oil and latex based painting and caulking products, solvents, adhesives, aerosols, petroleum products, and all containers of the original materials.

1.3.3.4 Disposal Documentation for Hazardous and Regulated Waste

Submit a copy of the applicable EPA permit(s), manifest(s), or license(s) for transportation, treatment, storage, and disposal of hazardous and regulated waste by permitted facilities.

1.3.3.5 Contractor 40 CFR Employee Training Records

Prepare and maintain employee-training records throughout the term of the contract meeting applicable 40 CFR requirements. Submit these training records to the Contracting Officer at the conclusion of the project, unless otherwise directed.

1.3.3.6 Regulatory Notification

The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. The Contractor shall forward copies to the Contracting Officer prior to commencement of work activities. Typically, regulatory notifications must be provided for the following (this listing is not all inclusive): demolition, renovation, SECTION 01575 Page 8

NPDES defined site work, remediation of controlled substances (asbestos, hazardous waste, lead paint).

1.3.3.7 Erosion and Sediment Control Inspection Reports

Submit "Erosion and Sediment Control Inspection Reports" required for permitted Construction projects to SC DHEC per the NPDES General permit SCR100000 Part 3.10.

1.3.3.8 Solid Waste Disposal Report

Monthly the Contractor shall submit a solid waste disposal report to the Contracting Officer. For each waste, the report shall state the classification (using the definitions provided in this section), amount, location, and name of the business receiving the solid waste. The Contractor shall include copies of the waste handling facilities' weight tickets, receipts, bills of sale, and other sales documentation. In lieu of sales documentation, the Contractor may submit a statement indicating the disposal location for the solid waste, which is signed by an officer of the Contractor firm authorized to legally obligate or bind the firm. The sales documentation or Contractor certification shall include the receiver's tax identification number and business, EPA or State registration number, along with the receiver's delivery and business addresses and telephone numbers.

For each solid waste retained by the Contractor for his own use, the Contractor shall submit on the solid waste disposal report the information previously described in this paragraph. Prices paid or received shall not be reported to the Contracting Officer unless required by other provisions or specifications of this Contract or public law.

1.4 CLASS I ODS PROHIBITION

Class I ODS as defined and identified herein shall not be used in the performance of this contract, nor be provided as part of the equipment.

This prohibition shall be considered to prevail over any other provision, specification, drawing, or referenced documents.

1.5 ENVIRONMENTAL PROTECTION REQUIREMENTS

Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during normal construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with Federal, State, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.

1.5.1 Facility Hazardous Waste Generator Status

Charleston Air Force Base is designated as a Large Quantity Generator. All work conducted within the boundaries of this activity must meet the regulatory requirements of this generator designation. The Contractor shall comply with all provisions of Federal, State and local regulatory requirements applicable to this generator status regarding training and storage, handling, and disposal of all construction derived wastes.

SECTION 01575 Page 9

1.5.2 Licenses and Permits

Obtain licenses and permits pursuant to the "Permits and Responsibilities" FAR Clause except for the following permits which will be obtained by the Contracting Officer:

None

For permits obtained by the Contracting Officer, whether or not required by the permit, the Contractor is responsible to perform quality control inspections of the work in progress, and to submit notifications and certifications to the applicable regulatory agency, via the Contracting Officer, that the work conforms to the contract and permit requirements.

The inspections and certifications shall be provided through the services of a Professional Engineer, registered in the State where the work is being performed. As a part of the quality control plan, which is required to be submitted for approval by the quality control section, provide a sub item containing the name, P.E. registration number, address, and telephone number of the professional engineer(s) who will be performing the inspections and certifications for each permit listed above.

1.5.3 Contractor Liabilities for Environmental Protection

The Contractor is advised that this project and the station are subject to Federal, State, and local regulatory agency inspections to review compliance with environmental laws and regulations. The Contractor shall fully cooperate with any representative from any Federal, State or local regulatory agency who may visit the job site and shall provide immediate notification to the Contracting Officer, who shall accompany them on any subsequent site inspections. The Contractor shall complete, maintain, and make available to the Contracting Officer, station, or regulatory agency personnel all documentation relating to environmental compliance under applicable Federal, State and local laws and regulations. The Contractor shall immediately notify the Contracting Officer if a Notice of Violation (NOV) is issued to the Contractor.

The Contractor shall be responsible for all damages to persons or property resulting from Contractor fault or negligence as well as for the payment of any civil fines or penalties which may be assessed by any Federal, State or local regulatory agency as a result of the Contractor's or any subcontractor's violation of any applicable Federal, State or local environmental law or regulation. Should a Notice of Violation (NOV), Notice of Noncompliance (NON), Notice of Deficiency (NOD), or similar regulatory agency notice be issued to the Government as facility owner/operator on account of the actions or inactions of the Contractor or one of its subcontractors in the performance of work under this contract, the Contractor shall fully cooperate with the Government in defending against regulatory assessment of any civil fines or penalties arising out of such actions or inactions.

1.6 UNFORESEEN HAZARDOUS OR REGULATED MATERIAL

If material that is not indicated in the contract documents is encountered that may be dangerous to human health upon disturbance during construction operations, stop that portion of work and notify the Contracting Officer immediately. Intent is to identify materials such as PCB, lead paint, mercury, petroleum products, and friable and nonfriable asbestos. Within 14 calendar days the Government will determine if the material is hazardous.

SECTION 01575 Page 10

If the material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If the material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

2 PRODUCTS

Not used.

3 EXECUTION

3.1 PROTECTION OF NATURAL RESOURCES

Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified.

3.1.1 Land Resources

Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer. Where such use of attached ropes, cables, or guys is authorized, the Contractor shall be responsible for any resultant damage.

3.1.1.1 Protection of Trees

Protect existing trees, which are to remain and which may be injured, bruised, defaced, or otherwise damaged by construction operations. Remove displaced rocks from uncleared areas. By approved excavation, remove trees with 30 percent or more of their root systems destroyed.

3.1.1.2 Replacement

Remove trees and other landscape features scarred or damaged by equipment operations, and replace with equivalent, undamaged trees and landscape features. Obtain Contracting Officer's approval before replacement.

3.1.2 Water Resources

3.1.2.1 Stream Crossings

The Contracting Officer's approval is required before any equipment will be permitted to ford live streams. In areas where frequent crossings are required, install temporary culverts or bridges. Obtain Contracting Officer's approval prior to installation. Remove temporary culverts or bridges upon completion of work, and repair the area to its original condition or as indicated.

3.1.2.2 Oily and Hazardous Substances

Prevent oily or other hazardous substances from entering the ground, drainage areas, or local bodies of water. For oil, fuel oil, or other hazardous substance spills, verbally notify the Contracting Officer

SECTION 01575 Page 11 immediately. The contractor shall comply with all applicable Spill Prevention Control and Countermeasure Plan (SPCC) regulations. Specifically, provide secondary containment for fuel storage tanks, 55-gallon drums of oil, etc.

3.1.3 Fish and Wildlife Resources

Do not disturb fish and wildlife. Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as indicated or specified.

3.2 HISTORICAL AND ARCHAEOLOGICAL RESOURCES

Carefully protect in-place and report immediately to the Contracting Officer historical and archaeological items or human skeletal remains discovered in the course of work. Stop work in the immediate area of the discovery until directed by the Contracting Officer to resume work. The Government retains ownership and control over historical and archaeological resources.

3.3 EROSION AND SEDIMENT CONTROL MEASURES

3.3.1 Burnoff

Burnoff of the ground cover is not permitted.

3.3.2 Protection of Erodible Soils

Immediately finish the earthwork brought to a final grade, as indicated or specified. Immediately protect the side slopes and back slopes upon completion of rough grading. Plan and conduct earthwork to minimize the duration of exposure of unprotected soils.

3.3.3 Temporary Protection of Erodible Soils

Use the following methods to prevent erosion and control sedimentation:

3.3.3.1 Mechanical Retardation and Control of Runoff

Mechanically retard and control the rate of runoff from the construction site. This includes construction of diversion ditches, benches, berms, and use of silt fences and straw bales to retard and divert runoff to protected drainage courses.

3.3.3.2 Sediment Basins

Trap sediment in temporary sediment basins. Pump dry and remove the accumulated sediment, after each storm. Use a paved weir or vertical overflow pipe for overflow. Remove collected sediment from the site.

Institute effluent quality monitoring programs.

3.3.3.3 Vegetation and Mulch

Provide temporary protection on sides and back slopes as soon as rough grading is completed or sufficient soil is exposed to require erosion protection. Protect slopes by accelerated growth of permanent vegetation, SECTION 01575 Page 12 temporary vegetation, mulching, or netting. Stabilize slopes by hydroseeding, anchoring mulch in place, covering with anchored netting, sodding, or such combination of these and other methods necessary for effective erosion control.

a. Seeding: Provide new seeding where ground is disturbed. Include topsoil or nutriment during the seeding operation necessary to establish a suitable stand of grass.

3.4 CONTROL AND DISPOSAL OF SOLID WASTES

Pick up solid wastes, and place in covered containers, which are regularly emptied. Do not prepare or cook food on the project site. Prevent contamination of the site or other areas when handling and disposing of wastes. At project completion, leave the areas clean. Recycling is encouraged and can be coordinated with the Contracting Officer and the activity recycling coordinator. Remove all solid waste (including non-hazardous debris) from Government property and dispose off-site at an approved landfill. Solid waste disposal off-site must comply with most stringent local, State, and Federal requirements including 40 CFR 241, 40 CFR 243, and 40 CFR 258.

3.4.1 Dumpsters

Equip dumpsters with a secure cover and paint the standard base color. Keep cover closed at all times, except when being loaded with trash and debris.

Locate dumpsters behind the construction fence or out of the public view.

Empty site dumpsters at least once a week, or as needed to keep the site free of debris and trash. If necessary, provide 55-gallon trash containers painted the darker base color to collect debris in the construction site area. Locate the trash containers behind the construction fence or out of the public view. Empty trash containers at least once a day. For large demolitions, large dumpsters without lids are acceptable but should not have debris higher than the sides before emptying.

3.5 CONTROL AND DISPOSAL OF HAZARDOUS WASTES

3.5.1 CAFB Requirements to Coordinate Hazardous Waste Disposal

Disposal of all hazardous waste shall be coordinated through 628 Civil Engineer Squadron Environmental Engineering Flight (CEV). The Contractor shall provide copies, for approval by CEV, of permits for transporters and treatment, storage, disposal facilities the Contractor intends to use, or as an alternative, the Contractor shall utilize only those transporters/facilities listed on the CAFB list of approved transporters/facilities. The Contractor shall provide all testing/analysis data and waste profiles to CEV for review and signature, SC Authorization Request Forms (when applicable) to CE for review and signature, and the Contractor shall coordinate with CE to have authorized CEV personnel sign the hazardous waste manifest for shipment of hazardous wastes.

3.5.2 Hazardous Waste/Debris Management

The Contractor shall identify all construction activities, which will generate hazardous waste/debris. The Contractor must provide a documented waste determination for all resultant waste streams. Hazardous waste/debris shall be identified, labeled, handled, stored, and disposed of in accordance

SECTION 01575 Page 13 with all Federal, State, and local regulations including 40 CFR 261, 40 CFR 262, 40 CFR 263, 40 CFR 264, 40 CFR 265, 40 CFR 266, and 40 CFR 268.

Hazardous waste shall also be managed in accordance with the approved Hazardous Waste Management Section of the Environmental Protection Plan.

Store hazardous wastes in approved containers in accordance with 49 CFR 173.

Hazardous waste generated within the confines of Government facilities shall be identified as being generated by the Government. Prior to removal of any hazardous waste from Government property, all hazardous waste manifests must be signed by activity personnel from the Station Environmental Office. No hazardous waste shall be brought onto Government property. Provide to the Contracting Officer a copy of waste determination documentation for any solid waste streams that have any potential to be hazardous waste or contain any chemical constituents listed in 40 CFR 372-SUBPART D. For hazardous wastes spills, verbally notify the Contracting Officer immediately.

3.5.2.1 Regulated Waste Storage/Satellite Accumulation/90 Day Storage Areas

If the work requires the temporary storage/collection of regulated or hazardous wastes, the Contractor may request the establishment of a Regulated Waste Storage Area, a Satellite Accumulation Area, or a 90 Day Storage Area at the point of generation. The Contractor must submit a request in writing to the Contracting Officer providing the following information:

Contract Number ____________ Contractor ______________

Haz/Waste or Regulated Waste POC ____________ Phone Number ______________

Type of Waste ____________ Source of Waste ______________

Emergency POC ____________ Phone Number ______________

Location of the Site: ____________ (Attach Site Plan to the Request)

Attach a waste determination form. Allow ten working days for processing this request.

3.5.3 Pollution Prevention/Hazardous Waste Minimization

The Contractor shall actively pursue minimizing the use of hazardous materials and the generation of hazardous waste while on base. The Hazardous Waste Management Section of the Environmental Protection Plan shall include the Contractor's procedures for pollution prevention/ hazardous waste minimization. For preparing this part of the plan, the Contractor may consult the activity Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for reference material. If no written plan exists, the Contractor may obtain information by contacting the Contracting Officer.

The Contractor shall describe the types of the hazardous materials expected to be used in the construction when requesting information.

3.5.4 Hazardous Material Control

The contractor must receive authorization from the Contracting Officer prior to transporting or using hazardous material on Charleston AFB. The

SECTION 01575 Page 14 contractor shall submit a CAFB Transient Organization Hazardous Material Form for review and authorization. The Contractor shall include hazardous material control procedures in their Safety Plan. The procedures shall address and ensure the proper handling of hazardous materials, including the appropriate transportation requirements. The Contractor shall submit a MSDS and estimated quantities to be used for each hazardous material to the Contracting Officer prior to bringing the material on base. Any material covered under the OSHA HAZCOM standard is considered a hazardous material for purposes of this contract. Typical materials requiring MSDS and quantity reporting include, but are not limited to oil and latex based painting and caulking products, solvents, adhesives, aerosol, and petroleum products. The contractor shall provide usage reports monthly or as otherwise indicated on the completed CAFB Transient Organization Hazardous Material Form. The Contractor shall also ensure that hazardous materials are utilized in a manner that will minimize the amount of hazardous waste that is generated. The Contractor shall ensure that all containers of hazardous materials have NFPA labels or their equivalent. Copies of the MSDS for hazardous materials shall be kept on site at all times. The Contractor shall certify that all hazardous materials removed from the site are hazardous materials and do not meet the definition of hazardous waste per 40 CFR 261.

3.5.5 Petroleum Products

Conduct the fueling and lubricating of equipment and motor vehicles in a manner that protects against spills and evaporation. All used oil generated on site shall be managed in accordance with 40 CFR 279. The Contractor shall determine if any used oil generated while on-site exhibits a characteristic of hazardous waste. In addition, used oil containing 1000 parts per million of solvents will be considered a hazardous waste and disposed of at Contractor's expense. Used oil mixed with a hazardous waste will also be considered a hazardous waste. All hazardous waste will be managed in accordance with the paragraph entitled Hazardous Waste/Debris Management of this section and shall be managed in accordance with the approved Environmental Protection Plan.

3.5.6 Spills of Oil and Hazardous Materials

Take precautions to prevent spills of oil and hazardous material. In the event of a spill, immediately notify the Contracting Officer. Spill response shall be in accordance with 40 CFR 300 and applicable State regulations.

3.6 DUST CONTROL

Keep dust down at all times, including during nonworking periods. Sprinkle or treat, with dust suppressants, the soil at the site, haul roads, and other areas disturbed by operations. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming. Air blowing will be permitted only for cleaning nonparticulate debris such as steel reinforcing bars. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete. Do not unnecessarily shake bags of cement, concrete mortar, or plaster.

3.7 ABRASIVE BLASTING

SECTION 01575 Page 15

3.7.1 Blasting Operations

The use of silica sand is prohibited in sandblasting.

Provide windscreens to enclose abrasive blasting operations to confine and collect dust, abrasive, agent, paint chips, and other debris. Perform work involving removal of hazardous material in accordance with 29 CFR 1910.

3.7.2 Disposal Requirements

Submit analytical results of the debris generated from abrasive blasting operations per paragraph entitled Laboratory Analysis of this section.

Hazardous waste generated from blasting operations shall be managed in accordance with paragraph entitled "Hazardous Waste\Debris Management" of this section and with the approved HWMP. Disposal of non-hazardous abrasive blasting debris shall be in accordance with paragraph entitled, "Control and Disposal of Solid Wastes".

3.8 NOISE

Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times.

--End of Section--