1 Qs As
View the file
Other files for this federal contract opportunity
Show all 50
SABER IDIQ - Joint Base Charleston, SC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
#1 Questions and Answers
FA4418-16-R-0001, SABER IDIQ - JB CHS, SC
1. Question: Are there asbuilt drawings available for DKGV 15-2056 Repair Naval
Headquarters Facility B-84 and DKGV 11-2196 Renovate Bldg 1?
Answer: Yes. The asbuilts for the two sample projects will be posted on fbo.gov via Amendment.
2. Question: Section L, Page 49 of 66, Paragraph 3 requires that the Past Performance
Projects List spreadsheet (Attachment #9) and supplemental information in paragraphs 3(a), 3(b), and 3(c) be submitted. Paragraph 3 limits the number to no more than ten
(10) contracts. As a 8(a) JV firm, can 10 contracts be submitted for each member of the
JV?
Answer: No. See Section L, 3. PART III, for details. Ten (10) contracts total for the Prime and major subcontractors. Performance information submitted for individual task orders issued under a single IDIQ contract will not be counted individually. Instead, task orders issued under a single IDIQ contract will be counted with their parent IDIQ as one
(1) of the ten (10) contracts.
3. Question: Section L, Page 50 of 66, Paragraph 3.(a), mentions contracts for major subcontractors. Is there a bona fide requirement to submit contract information for a major subcontractor?
Answer: Yes, if you want major subcontractor’s past performance to be considered.
4. Question: Section L, Page 50 of 66, Paragraph 3.(a) provides a list of information that must be submitted for each contract. The information listed does not indicate the scope of work for each contract to be included. Can detailed scope of work of project also be included?
Answer: Yes.
5. Question: Section L, page 51 of 66, Paragraph 3.(b) states that supplemental information be submitted which demonstrates customer satisfaction with job performance. Can completed performance evaluations and/or CCASS reports be submitted as/with this information.
Answer: Yes.
6. Question: Section L, L-001 Proposal Format, Paragraph C (page 45 of 66), indicates that an electronic copy of the proposal (compatible with Microsoft Office 2010) should be submitted. Paragraph D. references Adobe Acrobat 10.0 format for “Submitting Electronic Proposals.” Can you clarify the electronic format in which you wish the proposal submitted?
#1 Questions and Answers
FA4418-16-R-0001, SABER IDIQ - JB CHS, SC
Answer: If documents and spreadsheets are submitted they shall be compatible with Microsoft Office 2010. If PDF documents are submitted they shall be compatible with Adobe Acrobat 10.0.
7. Question: What is the deadline for final questions on this solicitation?
Answer: 2 Dec 2015
8. Question: Attachment 1 - SOW Technical Specs, Paragraph 3.2.2 (page 6) indicates that “QCMs shall be someone other than the CM or the PS.” In the same document, Paragraph 3.2.5 (also on page 6) states that “SMs cannot be the PS.” Where required personnel qualifications apply and the scope and utilization of resources is appropriate, can the SMs be assigned the QCM responsibilities?
Answer: Yes