Atch_3 _WD_SC29_Berkeley_5-22-15.pdf

PDF 16 KB Posted

Attached to
SABER IDIQ - Joint Base Charleston, SC Federal contract opportunity
Solicitation number
FA4418-16-R-0001
Issued by
Department of the Air Force Air Mobility Command

About this file

WD SC 29

View the file

Other files for this federal contract opportunity

Other files attached to SABER IDIQ - Joint Base Charleston, SC, newest first.
File Type Posted
_4_Qs_ _As _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Amendment_0003 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_11-_Bldg_84 _Addendum__1 _7_Dec_15.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_13_-_Bldg_84 _Roof_Summary_Rpt_1.pdf PDF
Amendment_0002 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_8 __2_Sample_Project__-_SOW_Atch_6_-_Bldg_1 _Addendum__1 _7_Dec_15.pdf PDF
SOW__Attachment_12_-_Addendum__1 _7_Dec_15.pdf PDF
Atch_7__1_Sample_Project_-_SOW_Atch_14_-_Bldg_84 _Roof__Summary_Rpt_2.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_12_-_Bldg_84 _Roof_Survey.pdf PDF
Arch_E-36x48-Border.dwg DWG drawing
_3_Qs_ _As_FA4418-16-R-0001_SABER_IDIQ.pdf PDF
Ansi_E-34x44-Border.dwg DWG drawing
_2_Qs_ __As_FA4418-16-R-0001_SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_3_-_Bldg_84_-_As-builts_Pt_1.pdf PDF
Amendment_0001 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_6_-_Bldg_84_-_As-builts_Pt_4.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_10_Bldg_84_-_As-builts_Pt_8.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_7_Bldg_84_-_As-builts_Pt_5.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_4_-_Bldg_84_-_As-builts_Pt_2.pdf PDF
Atch_7 ___1_Sample_Project_-_SOW_Atch_9_-_Bldg_84_-_As-builts_Pt_7.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_4_-_Bldg_1_-_As-builts-Current.pdf PDF
Atch_8 __2_SampleProject_-_SOW_Atch_5_-_Bldg_1_-_As-builts-Original.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_5_-_Bldg_84_-_As-builts_Pt_3.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_8_Bldg_84_-_As-builts_Pt_6.pdf PDF
_1_Qs_ _As _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_-_Bldg_1 _17_Aug_15.pdf PDF
SOW_Attachment_5_-_JBCGS_01540_-_Green_Procurement.pdf PDF
Atch_6 _Green_Procument_Form.pdf PDF
Atch_5 _WD_SC31_Dorchester_5-22-15.pdf PDF
SOW_Attachment_10_-_UFGS_01_45_00_-_Quality_Control.pdf PDF
SOW_Attachment_7_-_JBCGS_01575_-_Temporary_Environmental_Controls.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_1_-_Bldg_1_Existing_Floor_Plan.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_3_-_Bldg_1_Asbestos_Survey.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_2_-_Bldg_1_Conceptual_Floor_Plan.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_1_-_Bldg_84_Floorplan.pdf PDF
SOW_Attachment_11_-_UFGS_Contractor_Special_Conditions_Safety_Requirements.pdf PDF
Atch_2 _WD_SC23_Orangeburg_1-02-15.pdf PDF
SOW_Attachment_9_-_NPTU_Contractor_Special_Conditions.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_2_-_Bldg_84_Asbestos_Survey.pdf PDF
SOW_Attachment_8_-_Brig_Security_Requirements.pdf PDF
Atch_1 _SOW__Tech_Specs _16_Jul_15 _FA4418-16-R-0001 _SABER.pdf PDF
Atch_9 _Past_Performance_Projects_List.docx DOCX document
SOW_Attachment_2_-_JBCGS_28_31_76_Interior_Fire_Alarm_System_ _Mass_Noti....pdf PDF
SOW_Attachment_3_-_JBC_Cable_Management_Policy.pdf PDF
FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_4 _WD_SC30_Charleston_5-22-15.pdf PDF
SOW_Attachment_6_-_JBCGS_01572_-_Waste_Management.pdf PDF
SOW_Attachment_1_-_JBC_ACP.PDF PDF
Atch_7 __1_Sample_Project_-_SOW_-_Bldg_84 _1_Aug_15.pdf PDF
SOW_Attachment_4_-_JBCGS_01501_-_Environmental.pdf PDF
Show all 50

SABER IDIQ - Joint Base Charleston, SC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Atch 3, WD SC29 Berkeley 5-22-15.txt[11/3/2015 1:49:22 PM]

General Decision Number: SC150029 05/22/2015 SC29 FA4418-16-R-0001/ATCH 3

Superseded General Decision Number: SC20140029

State: South Carolina

Construction Type: Building

County: Berkeley County in South Carolina.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Executive Order (EO) 13658 establishes an hourly minimum wage of $10.10 for 2015 that applies to all contracts subject to the Davis-Bacon Act for which the solicitation is issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.10 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/02/2015 1 02/27/2015 2 05/22/2015

ELEC0776-002 01/01/2015

Rates Fringes

ELECTRICIAN......................$ 24.69 6.40+15%

Work more than 40 ft. above the ground on or from swinging scaffolds, boson chairs, or raw structural steel: $1.00 per hour additional.

* IRON0848-006 12/01/2014

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 23.00 12.00

PLUM0421-005 07/01/2013

Rates Fringes

PIPEFITTER.......................$ 24.85 9.65

SUSC2011-018 08/31/2011

Rates Fringes

BRICKLAYER.......................$ 18.00 0.00

CARPENTER (Drywall Hanging Only)............................$ 16.32 1.50

CARPENTER (Form Work Only).......$ 14.09 2.22

CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 16.25 1.36

CEMENT MASON/CONCRETE FINISHER...$ 14.77 0.00

HVAC MECHANIC (HVAC Duct Installation Only)...............$ 19.24 2.69

LABORER: Common or General......$ 11.10 1.72

LABORER: Landscape..............$ 9.45 0.49

LABORER: Mason Tender-Brick/Concrete/Cement/S tone.............................$ 11.00 0.00

LABORER: Pipelayer..............$ 14.69 2.08

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 19.62 3.54

OPERATOR: Bulldozer.............$ 17.07 2.65

OPERATOR: Crane.................$ 19.39 2.02

OPERATOR: Grader/Blade..........$ 17.59 1.56

OPERATOR: Loader................$ 14.18 1.99

PAINTER: Brush, Roller and Spray............................$ 12.74 0.00

PLUMBER..........................$ 18.95 5.35

ROOFER...........................$ 12.11 0.00

TRUCK DRIVER.....................$ 14.21 3.24

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION