SOW_Attachment_10_-_UFGS_01_45_00_-_Quality_Control.pdf

PDF 34 KB Posted

Attached to
SABER IDIQ - Joint Base Charleston, SC Federal contract opportunity
Solicitation number
FA4418-16-R-0001
Issued by
Department of the Air Force Air Mobility Command

About this file

SOW ATCH 10

View the file

Other files for this federal contract opportunity

Other files attached to SABER IDIQ - Joint Base Charleston, SC, newest first.
File Type Posted
Amendment_0003 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
_4_Qs_ _As _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_12_-_Bldg_84 _Roof_Survey.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_11-_Bldg_84 _Addendum__1 _7_Dec_15.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_13_-_Bldg_84 _Roof_Summary_Rpt_1.pdf PDF
Amendment_0002 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_8 __2_Sample_Project__-_SOW_Atch_6_-_Bldg_1 _Addendum__1 _7_Dec_15.pdf PDF
SOW__Attachment_12_-_Addendum__1 _7_Dec_15.pdf PDF
Atch_7__1_Sample_Project_-_SOW_Atch_14_-_Bldg_84 _Roof__Summary_Rpt_2.pdf PDF
Arch_E-36x48-Border.dwg DWG drawing
_3_Qs_ _As_FA4418-16-R-0001_SABER_IDIQ.pdf PDF
Ansi_E-34x44-Border.dwg DWG drawing
_2_Qs_ __As_FA4418-16-R-0001_SABER_IDIQ.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_4_-_Bldg_1_-_As-builts-Current.pdf PDF
Atch_8 __2_SampleProject_-_SOW_Atch_5_-_Bldg_1_-_As-builts-Original.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_5_-_Bldg_84_-_As-builts_Pt_3.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_8_Bldg_84_-_As-builts_Pt_6.pdf PDF
_1_Qs_ _As _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_3_-_Bldg_84_-_As-builts_Pt_1.pdf PDF
Amendment_0001 _FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_6_-_Bldg_84_-_As-builts_Pt_4.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_10_Bldg_84_-_As-builts_Pt_8.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_7_Bldg_84_-_As-builts_Pt_5.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_4_-_Bldg_84_-_As-builts_Pt_2.pdf PDF
Site_Visit_Min _Attendees-SABER.pdf PDF
FA4418-16-R-0001 _SABER_IDIQ.pdf PDF
Atch_4 _WD_SC30_Charleston_5-22-15.pdf PDF
SOW_Attachment_6_-_JBCGS_01572_-_Waste_Management.pdf PDF
SOW_Attachment_1_-_JBC_ACP.PDF PDF
Atch_7 __1_Sample_Project_-_SOW_-_Bldg_84 _1_Aug_15.pdf PDF
SOW_Attachment_4_-_JBCGS_01501_-_Environmental.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_-_Bldg_1 _17_Aug_15.pdf PDF
SOW_Attachment_5_-_JBCGS_01540_-_Green_Procurement.pdf PDF
Atch_6 _Green_Procument_Form.pdf PDF
Atch_5 _WD_SC31_Dorchester_5-22-15.pdf PDF
SOW_Attachment_7_-_JBCGS_01575_-_Temporary_Environmental_Controls.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_1_-_Bldg_1_Existing_Floor_Plan.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_3_-_Bldg_1_Asbestos_Survey.pdf PDF
Atch_8 __2_Sample_Project_-_SOW_Atch_2_-_Bldg_1_Conceptual_Floor_Plan.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_1_-_Bldg_84_Floorplan.pdf PDF
SOW_Attachment_11_-_UFGS_Contractor_Special_Conditions_Safety_Requirements.pdf PDF
Atch_2 _WD_SC23_Orangeburg_1-02-15.pdf PDF
SOW_Attachment_9_-_NPTU_Contractor_Special_Conditions.pdf PDF
Atch_7 __1_Sample_Project_-_SOW_Atch_2_-_Bldg_84_Asbestos_Survey.pdf PDF
SOW_Attachment_8_-_Brig_Security_Requirements.pdf PDF
Atch_1 _SOW__Tech_Specs _16_Jul_15 _FA4418-16-R-0001 _SABER.pdf PDF
Atch_9 _Past_Performance_Projects_List.docx DOCX document
Atch_3 _WD_SC29_Berkeley_5-22-15.pdf PDF
SOW_Attachment_2_-_JBCGS_28_31_76_Interior_Fire_Alarm_System_ _Mass_Noti....pdf PDF
SOW_Attachment_3_-_JBC_Cable_Management_Policy.pdf PDF
Show all 50

SABER IDIQ - Joint Base Charleston, SC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01 45 00.00 10 Page 1

JOINT BASE CHARLESTON

SECTION 01 45 00.00 10

QUALITY CONTROL (SABER)

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 3740 (2008) Minimum Requirements for Agencies

Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction

ASTM E 329 (2009) Standard Specification for Agencies

Engaged in the Testing and/or Inspection of Materials Used in Construction

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2012) International Building Code

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1110-1-12 (2006; Change 1) Engineering and Design -- Quality Management

1.2 PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control program, and all associated costs will be included in the offered coefficients.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system in compliance with the Contract Clause titled "Inspection of Construction." QC consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The Contract Manager (CM) will be held

Section 01 45 00.00 10 Page 2 responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence on the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

3.2 QUALITY CONTROL PLAN

Submit no later than 20 calendar days after receipt of notice to proceed, the Quality Control (QC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction." Construction will be permitted to begin only after acceptance of the QC Plan or acceptance of an interim plan applicable to the particular feature of work to be started.

Work outside of the accepted interim plan will not be permitted to begin until acceptance of a QC Plan or another interim plan containing the additional work.

3.2.1 Content of the CQC Plan

Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of records, consultants, architect/engineers (AE), fabricators, suppliers, and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the QC staff will implement the three phase control system for all aspects of the work specified. Include QC System Managers who report to the contract manager (CM).

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a QC function.

c. A copy of the letter to the QC Managers signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of a QC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the QC Managers. Copies of these letters must be furnished to the Government.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators and suppliers. These procedures must be in accordance with the STATEMENT OF WORK & TECHNICAL SPECIFICATIONS for this contract.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and

Section 01 45 00.00 10 Page 3 person responsible for each test. (Laboratory facilities approved by the Contracting Officer must be used.)

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

3.2.2 Acceptance of Plan

Acceptance of the Contractor's plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in the QC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.3 Notification of Changes

After acceptance of the QC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3.3 COORDINATION MEETING

See Section 7.6 of the STATEMENT OF WORK & TECHNICAL SPECIFICATIONS for this contract.

3.4 QUALITY CONTROL ORGANIZATION

3.4.1 Personnel Requirements

Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the QC organization. The Contractor's QC staff must maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The QC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional QC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the QC organization. The QC organization shall be responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.

3.5 SUBMITTALS AND DELIVERABLES

The QC Managers are responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.

Section 01 45 00.00 10 Page 4

3.6 CONTROL

Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control must be conducted by the QC Managers for each definable feature of the construction work as follows:

3.6.1 Preparatory Phase

This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. A review of task order drawings.

c. A check to assure all materials and/or equipment have been tested, submitted, and approved.

d. A review of provisions which have been made to provide required control inspection and testing.

e. An examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

f. An examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

g. A review of the appropriate activity hazard analysis to assure safety requirements are met.

h. A discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.

i. A check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

j. A discussion of the initial control phase.

k. The Government must be notified at least 48 hours in advance of beginning the preparatory control phase. Include a meeting conducted by a QC Manager and attended by the superintendent, other QC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the QC Manager and attach

Section 01 45 00.00 10 Page 5 to the daily QC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

3.6.2 Initial Phase

This phase is accomplished at the beginning of a definable feature of work.

Accomplish the following:

a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

b. Verify adequacy of controls to ensure full contract compliance.

Verify required control inspection and testing.

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government must be notified at least 48 hours in advance of beginning the initial phase. Prepare separate minutes of this phase by a QC Manager and attach to the daily QC report. Indicate the exact location of initial phase for future reference and comparison with follow-up phases.

g. The initial phase should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.6.3 Follow-up Phase

Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the QC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

3.6.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable QC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

3.7 TESTS

Section 01 45 00.00 10 Page 6

3.7.1 Testing Procedure

Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. Perform the following activities and record and provide the following data:

a. Verify that testing procedures comply with contract requirements.

b. Verify that facilities and testing equipment are available and comply with testing standards.

c. Check test instrument calibration data against certified standards.

d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.

e. Record results of all tests taken, both passing and failing on the

QC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.

3.7.2 Testing Laboratories

3.7.2.1 Capability Check

The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel must meet criteria detailed in ASTM D 3740 and

ASTM E 329.

3.8 COMPLETION INSPECTION

3.8.1 Punch-Out Inspection

Conduct an inspection of the work by a QC Manager near the end of the work, or any increment of the work established by a time stated in the SPECIAL CONTRACT REQUIREMENTS Clause, "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the QC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION.

Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection by a QC Manager or staff to ascertain that all deficiencies have been corrected. Once this is

Section 01 45 00.00 10 Page 7 accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.

3.8.2 Pre-Final Inspection

The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph must be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.

3.8.3 Final Acceptance Inspection

The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative must be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base Civil Engineer Squadron, Wing Safety and user groups may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 5 working days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the contract clause titled "Inspection of Construction".

3.9 DOCUMENTATION

Maintain current records providing factual evidence that required quality control activities and/or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:

a. Contractor/subcontractor and their area of responsibility.

b. Operating plant/equipment with hours worked, idle, or down for repair.

c. Work performed each day, giving location, description, and by whom.

d. Test and/or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.

Section 01 45 00.00 10 Page 8

e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.

g. Offsite surveillance activities, including actions taken.

h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.

i. Instructions given/received and conflicts in plans and/or specifications.

j. Contractor's verification statement.

Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period.

All calendar days must be accounted for throughout the life of the contract.

The first report following a day of no work will be for that day only.

Reports must be signed and dated by a QC Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the QC Manager Report.

3.10 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

-- End of Section --

PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 QUALITY CONTROL PLAN
3.2.1 Content of the CQC Plan
3.2.2 Acceptance of Plan
3.2.3 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.5 SUBMITTALS AND DELIVERABLES
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Testing Procedure
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
3.8.2 Pre-Final Inspection
3.8.3 Final Acceptance Inspection
3.9 DOCUMENTATION
3.10 NOTIFICATION OF NONCOMPLIANCE