FA3002-16-R-0005
Appendix 3A, Sorties Utilization and Total Aircraft Inventory Data
Amendment 05
TAIWAN F-16 AIRCRAFT MAINTENANCE
LUKE AFB
Appendix 3A – Sorties, Utilization and Total Aircraft Inventory Data
3.1. Note: The OP/OY Sortie Projections are the Government’s best estimation of required sorties but can be adjusted by the AFSAT OP/OY 21 FS Approved Sorties before the period of performance (POP) or during the POP. The AFSAT Ordering Period (OP)/Option Year (OY) 21 FS Approved Sorties are the joint TAF/AFSAT issued sorties requirement for the 21 FS Taiwan pilot training during the affected POP. If the AFSAT OP/OY 21 FS Approved Sorties is different than the OP/OY Projected Sorties, the difference will be adjusted using the Section B Sortie Adjustment Clause to conform to the AFSAT OP/OY 21 FS Approved Sortie requirement for the affected POP.
Table 3A-1. OP/OY ANNUAL SORTIE MANAGEMENT/ADJUSTMENT TABLE (See Section B Table B-3):
OP/OY
SORTIE
PROJECTIONS
(Non-Binding for estimates Only)
OP/OY AFSAT
APPROVED
SORTIES
(Government Unilateral Decision)
BINDING
ACTUAL
ANNUAL
OP/OY
21 FS
COMPLETED
SORTIES
AFSAT SORTIE
ADJUSTMENT
PARAMETERS
(+/-7%)
OP/OY
ADJUSTED
SORTIES
(Outside the Adjustment Parameters)
OP/OY SORTIE
ADJUSTMENT
CLIN X005
COST
CONTRACT
TASK ORDER
OR
MODIFICATION
NUMBER
OP 1 of 5
2430 2430 (+164/-164)
OP 2 of 5
OP 3 of 5
OP 4 of 5
OP 5 of 5
OY 1
OY 2
3.2. Flying Program Utilization.
3.2.1. Night flights consist of approximately 7.0 percent of the sorties per year.
Weekend cross-country flights consist of approximately 1.9 percent of the sorties per year.
FCF flights consist of approximately .01 percent of the sorties per year.
Air-to-Air flights consist of approximately 50 percent of the sorties per year.
Air to Ground flights consist of approximately 46.2 percent of the sorties per year.
Air to Ground flights with live munitions consist of approximately 3.8 percent of the sorties per year.
AA standard is used for scheduling front lines and spares.
Average flying window is 6.5 hours per day.
The SP shall have the ability to support both local flying and off station flying simultaneously during 21 FS deployments. Normally, the combination of both the local and deployed flying schedules does not exceed 8 front lines. For example, 6 deployed front lines and 2 local frontlines or 8 deployed front lines and no local sorties scheduled.
FA3002-16-R-0005
Appendix 3A, Sorties Utilization and Total Aircraft Inventory Data
Amendment 05
TAIWAN F-16 AIRCRAFT MAINTENANCE
LUKE AFB
Table 3A-2. Aircraft Assignment Data
MDS Sortie Utilization
(UTE)
RATE
(Note 1)
Average Sortie Duration
(ASD)
Projected Annual Flying Hours
Primary Aircraft Inventory
(PAI)
Total Aircraft Inventory
(TAI)
F-16 Block 20
16.87 1.34 3256.20 12 currently
Remains 12 aircraft for the Rising Phoenix Retrofit Modification
13 currently
Then 14 aircraft for the Rising Phoenix Retrofit Modification
Note 1: The Sortie UTE rate is an hourly UTE rate. This is calculated as follows: annual sorties divided by 12 to get hours in a month divided by sortie length to get number of sorties in a month divided by PAI = UTE rate. The above is an estimate only and is based on the most current information available. Actual execution and unit flying hour adjustments may drive variances to the allocation numbers. The actual Utilization Rate (UTE) and Average Sortie Duration (ASD) will vary as much as plus or minus 5 percent during the year and as much as plus or minus 5 percent, cumulative, at the end of the year.
Table 3A-3. 21 FS Assigned Total Aircraft Inventory (SEE Section J, Attachment 11, Table, B- 3):
OPs 21 FS
TAI
PROJECTIONS
(Non-Binding)
21 FS
ASSIGNED
TAI
(Binding)
TAI
Parameter (-/+ 7.5%)
ADJUSTED
TAI
(Outside the Adjustment Parameters)
OP
TAI
ADJUSTMENT
CLIN X006
COST
CONTRACT
TASK
ORDER
NUMBER
OP 1 of 5 13 13 1 OP 2 of 5 13 1 OP 3 of 5 13 1 OP 4 of 5 13 1 OP 5 of 5 14 1
OY 1 14 1
OY 2 14 1