Amendment 0016 SF 30.doc
DOC document 108 KB Posted
- Attached to
- Maxwell-Gunter AFB BOS FA3002-06-R-0004 Federal contract opportunity
- Solicitation number
- FA3002-06-R-0004
About this file
Amendment 0016 - SF 30
View the file
Other files for this federal contract opportunity
Show all 50
Maxwell-Gunter AFB BOS FA3002-06-R-0004 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT NO. FA3002-06-R-0004-0016 14 AUG 08
Base Operating Services at Maxwell-Gunter, AL
AMENDMENT NO. FA3002-06-R-0004-0016 14 AUG 2008
Base Operating Services at Maxwell-Gunter, AL
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
PAGE OF PAGES
1 5
2. AMENDMENT/MODIFICATION NO.
FA3002-06-R-0004-0016
4. REQUISITION/PURCHASE REQ. NO.
3. EFFECTIVE DATE
14 AUG 2008
1. CONTRACT ID CODE
(x)
7. ADMINISTERED BY (If other than Item 6) CODE
6. ISSUED BY CODE
AETC CONTRACTING SQUADRON /LGCI
2021 First Street West, Bldg 853
RANDOLPH AFB TX 78150-4302
CONTRACTING OFFICER: Myles Rellstab (210) 652-7756
FA3002
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State, and ZIP Code)
CODE FACILITY CODE
9A. AMENDMENT OF SOLICITATION NO.
FA3002-06-R-0004
9B. DATED (SEE ITEM 11)
20 APR 07
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
X
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the
Following methods: (a) By completing Items 8 and 15, and returning (SEE SECTION L) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF
YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND
DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment. and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority
E. IMPORTANT: Contractor copies to the issuing office. required to sign this document and return is not is
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organize by UCF section headings, including solicitation/contract subject matter where feasible.)
SEE ATTACHED PAGES
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, remain unchanged and in full force and effect 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type of Print)
15A. NAME AND TITLE OF SIGNER (Type or Print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16A. UNITED STATES OF AMERICA
BY ________________________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
15C. DATE SIGNED
5. PROJECT NO. (IF APPLICABLE)
Block 14, Continued
Purpose:
To amend the Period of Performance by revising the following:
1. To replace, in its entirety, Amendment 0015 Schedule B with Amendment 0016 Schedule B.
2. To replace, in its entirety, the Manpower Matrix, dated 20 Jun 08, at Attachment 6 and the Cost Model, dated 20 Jun 08, at Attachment 7 with the revised Manpower Matrix, dated 6 Aug 08, at Attachment 6 and the revised Cost Model, dated 6 Aug 08, at Attachment 7.
3. To make the following revisions to Section B, in addition to replacing the Schedule B, as stated in paragraph 1 above:
Change Clause B-004 From:
B-004. MOBILIZATION/TRANSITION
For the basic contract period only, mobilization/changeover costs are defined as all costs expended pursuant to responsibility for each function under this contract within the mobilization/changeover period. A firm, fixed price will be entered on contract line item (CLIN) 6001.
Change Clause B-004 To:
B-004. MOBILIZATION/TRANSITION
For the basic contract period only, mobilization/changeover costs are defined as all costs expended pursuant to responsibility for each function under this contract within the mobilization/changeover period. A firm, fixed price will be entered on contract line item (CLIN) 0047.
4. To make the following revisions to the Period of Performance in Section F:
Change Period of Performance From:
PERIOD OF PERFORMANCE
Performance under this contract shall be:
| Base Period: Mob/Trans |
| 01 Oct 2008 – 14 Nov 2008 |
| First Option Year |
| 15 Nov 2008 – 14 Nov 2009 |
| Second Option Year |
| 15 Nov 2009 – 14 Nov 2010 |
| Third Option Year |
| 15 Nov 2010 – 14 Nov 2011 |
| Fourth Option Year |
| 15 Nov 2011 – 14 Nov 2012 |
| Fifth Option Year |
| 15 Nov 2012 – 14 Nov 2013 |
| Sixth Option Year |
| 15 Nov 2013 – 14 Nov 2014 |
Change Period of Performance To:
PERIOD OF PERFORMANCE
Performance under this contract shall be:
| Base Period |
| 15 Nov 2008 – 14 Nov 2009 |
| First Option Year |
| 15 Nov 2009 – 14 Nov 2010 |
| Second Option Year |
| 15 Nov 2010 – 14 Nov 2011 |
| Third Option Year |
| 15 Nov 2011 – 14 Nov 2012 |
| Fourth Option Year |
| 15 Nov 2012 – 14 Nov 2013 |
| Fifth Option Year |
| 15 Nov 2013 – 14 Nov 2014 |
5. To make the following revisions to Section J:
Change Section J From:
Section J – Attachments
| Title |
| Number of Pages |
| Date |
| 1. Performance Work Statement |
| Table of Contents, plus 26 Sections |
| 5 May 08 |
2. Wage Determinations AL080005, AL080007, AL080058, AL080143, AL080112, AL080008, 05-2011 (Rev.-7), 85-0983 (Rev.-31), 04-255 (Rev.-5), 04-2520 (Rev.-5)
| 31 |
| 08 Feb 08, 08 Feb 08, |
08 Feb 08, 08 Feb 08, 08 Feb 08, 08 Feb 08, 29 May 08, 22 Jan 08, 01 Aug 07, 01 Aug 07
| 3. Conformed Classifications & Wage Rates Memo |
| 2 |
| 10 Sep 07 and 1 Oct 07 |
| 4. Statement of Equivalent Rates for Federal Hires |
| 3 |
| 07 Mar 07 |
| 5. Collective Bargaining Agreements |
| 182 |
| 09 July 02, 16 Jun 06, 06 Sept 06 |
| 6. Manpower Matrix |
| 35 |
| 20 Jun 08 |
| 7. Cost Model |
| 234 |
| 20 Jun 08 |
| 8. Past Performance Relevancy Matrix |
| 1 |
| 29 Mar 07 |
| 9. Past Performance Information Sheet |
| 6 |
| 1 May 07 |
| 10. Past Performance Consent Form |
| 1 |
| 29 Mar 07 |
| 11. Past Performance Questionnaire |
| 8 |
| 29 Mar 07 |
| 12. Past Performance Cover Letter |
| 1 |
| 29 Mar 07 |
13. Past Performance Subcontracting Plan Work
Sheet
| 3 |
| 9 May 07 |
| 14. Subcontracting Worksheet |
| 7 |
| 29 Mar 07 |
| 15. Question / Comment Form |
| 1 |
| 29 Mar 07 |
| 16. Draft Performance Plan and Metrics |
| 191 |
| 25 Mar 08 |
17. DD 254, Contract Security Classification
Specification
| 2 |
| 29 Mar 07 |
Change Section J To:
Section J – Attachments
| Title |
| Number of Pages |
| Date |
| 1. Performance Work Statement |
| Table of Contents, plus 26 Sections |
| 5 May 08 |
2. Wage Determinations AL080005, AL080007, AL080058, AL080143, AL080112, AL080008, 05-2011 (Rev.-7), 85-0983 (Rev.-31), 04-255 (Rev.-5), 04-2520 (Rev.-5)
| 31 |
| 08 Feb 08, 08 Feb 08, |
08 Feb 08, 08 Feb 08, 08 Feb 08, 08 Feb 08, 29 May 08, 22 Jan 08, 01 Aug 07, 01 Aug 07
| 3. Conformed Classifications & Wage Rates Memo |
| 2 |
| 10 Sep 07 and 1 Oct 07 |
| 4. Statement of Equivalent Rates for Federal Hires |
| 3 |
| 07 Mar 07 |
| 5. Collective Bargaining Agreements |
| 182 |
| 09 July 02, 16 Jun 06, 06 Sept 06 |
| 6. Manpower Matrix |
| 35 |
| 6 Aug 08 |
| 7. Cost Model |
| 234 |
| 6 Aug 08 |
| 8. Past Performance Relevancy Matrix |
| 1 |
| 29 Mar 07 |
| 9. Past Performance Information Sheet |
| 6 |
| 1 May 07 |
| 10. Past Performance Consent Form |
| 1 |
| 29 Mar 07 |
| 11. Past Performance Questionnaire |
| 8 |
| 29 Mar 07 |
| 12. Past Performance Cover Letter |
| 1 |
| 29 Mar 07 |
13. Past Performance Subcontracting Plan Work
Sheet
| 3 |
| 9 May 07 |
| 14. Subcontracting Worksheet |
| 7 |
| 29 Mar 07 |
| 15. Question / Comment Form |
| 1 |
| 29 Mar 07 |
| 16. Draft Performance Plan and Metrics |
| 191 |
| 25 Mar 08 |
17. DD 254, Contract Security Classification
Specification
| 2 |
| 29 Mar 07 |
6. To make the following revisions to Section L:
Change Section L paragraph 7.1.2.b.3. From:
3. A completed copy of the Manpower Matrix (provided in Section J, Attachment 6). The Manpower Matrix must be identical to the matrix provided in the technical proposal. The following total number of working man-hours per calendar year must be employed in filling out the Manpower Matrix and the Cost Model:
FY09 264 hours (Mobilization/Transition)
FY09-10 2,080 hours (Basic Contract Period)
FY10-11
2,080 hours (1st Option Year)
FY11-12
2,088 hours (2nd Option Year)
FY12-13
2,096 hours (3rd Option Year)
FY13-14
2,088 hours (4th Option Year)
FY14-15 2,088 hours (5th Option Year)
Change Section L paragraph 7.1.2.b.3. To:
3. A completed copy of the Manpower Matrix (provided in Section J, Attachment 6). The Manpower Matrix must be identical to the matrix provided in the technical proposal. The following total number of working man-hours per calendar year must be employed in filling out the Manpower Matrix and the Cost Model:
FY09-10 2,080 hours (Base Period)
FY10-11 2,080 hours (1st Option Year)
FY11-12
2,088 hours (2nd Option Year)
FY12-13
2,096 hours (3rd Option Year)
FY13-14
2,088 hours (4th Option Year)
FY14-15
2,088 hours (5th Option Year)
NOTE: All changes are marked with a vertical line in the left hand margin and highlighted in yellow in the attached conformed RFP labeled Amendment 0016.
END OF AMENDMENT 0016
PAGE
File details come from the government source that posted it. Updated .