CLOIS DRAFT Attachment L-03 Work Classification Worksheet

View the file

Other files for this federal contract opportunity

Other files attached to Cape Launch Operations and Infrastructure Support (CLOIS), newest first.
File Type Posted
CLOIS_QA_Working_Master_-_Posted_06_Feb_15.xlsx XLSX spreadsheet
L-04_TEP_Task_Ordering_Wrksht_-26_Jan.xlsx XLSX spreadsheet
CLOIS_QA_Working_Master_-_Posted_30_Jan_15.xlsx XLSX spreadsheet
CLOIS_QA_posted_16_Jan_15.xlsx XLSX spreadsheet
L-02_Sample_Mission_-_13_Jan_update_V2.xlsx XLSX spreadsheet
L-04_TEP_Task_Ordering_Wrksht_-Updated_13_Jan_14.xlsx XLSX spreadsheet
Section_L_-_29_Dec_with_Missing_Page.pdf PDF
L-06a_Fac_60650_Act-Deact_Sample_Work_Plan.docx DOCX document
L-06b_Facility_60650_Floor_Plans.pdf PDF
Sect_L_Update_22_Dec.docx DOCX document
L-04_TEP_Task_Ordering_Wrksht_-18_Dec.xlsx XLSX spreadsheet
Sect_B_update_22_Dec.doc DOC document
CLOIS_Q A_18_DEC_FBO_post.xlsx XLSX spreadsheet
CLOIS_DRAFT_CDRL_PORTFOLIO.pdf PDF
CLOIS_TEP_and_Task_Ordering_Worksheet_-Revised_21_Nov_14.xlsx XLSX spreadsheet
CLOIS_Q A_as_of_25_Nov_14.xlsx XLSX spreadsheet
FA2521-13-R-0019_CLOIS_DRAFT_RFP_(25_Nov).doc DOC document
Section_M_Changes_Highlighted_25_Nov_14.docx DOCX document
Section_L_Changes_Highlighted_25_Nov_14.docx DOCX document
CLOIS_Industry_Day_Briefing_Attendee_List.pdf PDF
CLOIS_Industry_Day_17_Nov_14_SLIDES_FINAL.pdf PDF
CLOIS_Industry_Day_-_Opening_Remarks.pdf PDF
Attachment_L-01_CLOIS_Q A_Form.xlsx XLSX spreadsheet
Draft_Section_L_-_28_Oct_14.docx DOCX document
Attachment__L-04_TEP_Worksheet_28_Oct_14.xlsx XLSX spreadsheet
Atch_11_CBA_Yang _TWA.pdf PDF
Atch_02_-_SCA_WD_2005-2118_Rev_17.pdf PDF
Atch_09_CBA_SLCS __TWA.pdf PDF
Atch_06_WD_CBA_Indyne _TWA.pdf PDF
Atch_12_WD_CBA_Yang _TWA.pdf PDF
Atch_10_WD_CBA_SCLS _TWA.pdf PDF
Atch_04 _WD_CBA_Indyne_and_IAM.pdf PDF
Atch_08_WD_CBA_Yang _SPFPA.pdf PDF
Atch_07_CBA_Yang _SPFPA.pdf PDF
Atch_05__CBA__Indyne _TWA.pdf PDF
Atch_03_-_CBA_-_Indyne_and_IAM.pdf PDF
CLOIS_DRAFT_Attachment_L-01_Question_and_Answer_Template.docx DOCX document
CLOIS_DRAFT_Attachment_L-05_Labor_Rates_Listing.xlsx XLSX spreadsheet
CLOIS_DRAFT_Section_L.pdf PDF
CLOIS_DRAFT_Attachment_L-04_TEP_Worksheet.xlsx XLSX spreadsheet
CLOIS_DRAFT_Attachment_L-02_Sample_Mission.xlsx XLSX spreadsheet
CLOIS_DRAFT_Section_M.pdf PDF
1-CLOIS_RFI_Questions_-_25_April_2014.pdf PDF
7-Appendix_D_-_COLS_Definitions_-_25_April_2014.pdf PDF
6-Appendix_C_-_Facility_Tier_Definitions_-_25_April_2014.pdf PDF
3-RFI_Notional_CLIN_Structure_25_April_2015.pdf PDF
2-DRAFT_CLOIS_PWS_-_25_April_2014.pdf PDF
8-Appendix_E_-_Work_Classifications_-_25_April_2014.pdf PDF
5-Appendix_B_--__Communications_Systems_-_DRAFT_-_25_Apr_2014.pdf PDF
OMEU 1 .pdf PDF
Show all 50

Cape Launch Operations and Infrastructure Support (CLOIS) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

1.4.2 Provide classification of the work task identified below as either
corrective maintenance (fixed-price under O&M CLIN), repair (fixed-price under O&M CLIN),
planned worked (cost reimbursement under the planned work CLIN), or projects (fixed-price under the project CLIN):
Part "X" in appropriate box
Corrective maintenance (fixed-price under O&M CLIN)Repair (fixed-price under O&M CLIN)Planned worked (cost reimbursement under the planned work CLIN)Projects (fixed-price under the project CLIN)Work Task
a. Unclog toilet
b. Replace 20-ton chiller
c. Install permanent 100KW generator
d. Paint office 10 sf x 10 sf
e. Replace 30 amp breaker
f. Install 600 amp distribution panel
g. Repair 8-inch diameter pothole in road
h. Repair 18-inch roof flashing from water leak
i. Replace 12-inch backflow preventer
j. Repair 6-foot section of chain link fence (not including posts)
k. Replace 3 each guy wires on 60-foot communication tower
l. Install 5 interior, office door locks and rekey
m. Replace office space thermostat
n. Repair surface rust on 80 foot roof ladder with fall cage
o. Replace lamps in traffic sign light
p. Replace belt on air handling unit

Work Classification Worksheet DRAFT Attachment L-03