Area 59 Mission Support Tasks Area 59 Mission Support Task for a Typical SV Nominal Duration
| SV Pre-Arrival Task/SV Processing @ NPF/DPF - General Support Effort | 60 days before Arrival |
| Clean DPF East Bay to 100K to support (NVR Plate Install) | 7 days |
| Install NVR Plates in DPF East Bay (28 days data EB) | 1 day |
| Pre-Cleaning NPF Processing Bays | 30 days before Arrival |
| Main Bay Cleaning 100K | 7 days |
| High Bay Cleaning 100K | 4 days |
| Air Lock Cleaning 100K | 5 days |
| SV ICE #1 & 2 | 2 days |
| Pre-Inspection of NPF for SV Arrival- 5 days before Arrival (Internal) | 1 day |
| Pre-Arrival Walkdown NPF Arrival- 3 days before Arrival (Customer) | 1 day |
| Cleaning DPF (WB, MB, & A/L) install NVR Plates | 1 day |
| Sample GN2 ports NPF-2 weeks before SV Arrival | 1 day |
| Pre-Ship IRR | 1 day |
| Attend SV Offload Briefing with all Stakeholders | 1 day |
| Move Air Pallets over to NPF | 1 day |
| Order NVR Plates (10) for MB, HB & A/L | 1 day |
| Contamination Control/Flow Manager inspect process bays | 1 day |
| Secure Deluge System (OS&Y Valve) @ NPF for SV Offload | 1 day |
| SV Arrival at NPF - General Support Effort | 35 day in NPF |
| Landoll Trailer with SV backed into Air Lock | 1 day |
| Offload SV in Air lock | 1 day |
| Install new NVR plates in High Bay & Air Lock | 1 day |
| Clean High bay and Air Lock back to 100K | Daily |
| Support crane Ops in High Bay | 1 day |
| SV moved from High Bay to Main Bay | 2 days |
| SV Testing @ NPF in Main Bay (SV only effort) | N/A |
| Offload (ULA) PLF Fairing in East Bay DPF | 4 days |
| Offload (ULA) AGE equipment into Air Lock | 2 days |
| Satellite techs open Air Lock & East Bay blast door | 1 day |
| Contamination Control tech support with Offloading PLFs | 1 day |
| Contamination Control support PLFs cleaning in EB | 1 day |
| Transport Torqus Ring and LV GSE Equipment to DPF Air Lock (45 days before launch) | 5 days |
| Satellite tech open Air Lock blast door | 1 day |
| Contamination Control tech cleaning | 1 day |
| Fuel Arrival Preps in (WB, WCR, WPA, Pressurization) | 8 days |
| Support Fuel Arrival in DPF WB | 2 days |
| GPSIIF Countdown Launch Procedure (CLP#1) @ NPF | 1 day |
| Sample Fuel in WB (DPF Bldg clear) | 1 day |
| Comm perform comm checks for DPF (Fuel Ops) | 1 day |
| Move SV from NPF to DPF (WB) | 1 day |
| Fuel SV in West Bay (Bldg Clear) | 1 day |
| Move SV from WB to A/L for Combined Ops | 1 day |
| Satellite tech open blast door between WB & A/L | 1 day |
| Mate PLA to SV | 4 days |
| Crane Ops -SV weigh, ordnace install, clamp band | 2 days |
| SV mate to PLA (crane Ops) | 1 day |
| Clamp Band Finaling (Crane Ops) | 1 day |
| Mate SV/PLA to (ULA) PAF (Combined Ops) | 3 days |
| Install PLF Fairing to SV in DPF A/L | 4 days |
| Install PLF Fairing (Half #1)- Crane Ops | 1 day |
| Install PLF Fairing (Half#2)- Crane ops | 1 day |
| Contamination Control Cleaning | 2 days |
| Fairing to PAF connector Install | 2 days |
| Preps for Transport to pad | 5 days |
| Transport to Pad | 1 day |
| Satellite techs Open Air Lock door | 1 day |
| Contamination Control tech for Cleaning | 1 day |
| SV transported from DPF to Complex-37 | 1 day |
| Countdown Launch Procedure (CLP#2) @ NPF | N/A |
| On Pad Processing (Complex-37 SV Processing) -10 Day SV effort | N/A |
| Monitoring SV from NPF Control Room | N/A |
| Intergrated Verification Test (IVT), battery charging, IST | N/A |
| LV Propellant loading, SV Battery Top off | N/A |
| Ordnance Install & Stray Voltage check, Battery Top off | N/A |
| Launch Day Activties - General Suport Effort | - |
| Generator Support (Mech and Elect techs) | 1 day |
| Life Safety on site secure Fire Alarm & O2 Sys (2 shifts) | 1 day |
| HVAC on site in Area 59 monitor work station | 1 day |
Sample Mission Support Task DRAFT Attachment L-02
PS - 7 Mission Support Tasks Pump Station 7 Mission Support Tasks Nominal Task Timeline
| Support LV with 1 Engine/Pump at 175 PSI for approx. 2 hours for the LV - Water Deluge ROV Timing Test | L-15 Day |
| Perform System Pre-Launch Validation - Test Deluge Pump/Engines/Safety Equipment for Operational Readiness Requirements | L-10 thru L-1 Day |
Support LV-ASWS Manifold Fill and Water Deluge System Prime, 1 Engine/Pump with 150 PSIG for approx. 4 hours. LV will use ~100,000 gallons of water L-2 Day
Support LV-ACCMR Charge for approx. 3 hours, 1 Engine/Pump Online with 150 PSIG for approx 3 hours. LV will use ~20,000 gallons of water L-1 Day
Launch Support - Pump Station #7: (~T-3:40), 4 pumps minimum with 1 back up pump on the 30" line at 175 +10 -0 psig for ~6 hours. LV washdown crew will call pump station post launch to reduce to 1 pump and will call again to secure all pumps when complete. L-0 Day
Post Launch Wash-down Support - 1 pump online at 150 PSIG from 0800 - 2300, or until released by LV Contractor L+1 Day
Post Launch Wash-down Support - 1 pump online at 150 PSIG from 0600 - 1400, or until released by LV Contractor L+2 Day
DRAFT Attachment L-02
SV-LV Ordnance Mission Support
| Ordnance Mission Support Tasks | Quantity and/or Effort |
| SV Ordnance Mission Support Tasks | |
| Test SV ordnance (using MOTC) | 4 Bolt Cutters |
| Deliver SV ordnance to Area 59 | 4 Bolt Cutters |
| LV Ordnance Mission Support Tasks | |
| Pull from storage booster ordnance for next flight | 300 LV Ordance Items (such as: Bolt Cutters, igniters, S&A devices, thrusters) |
| Test & prep booster ordnance, assign flight kits | 240 items |
| Deliver and Support Installation of 1st stage ordnance | 5 days |
| Deliver and Support Installation of final booster ordnance | 3 days - 8 hr shifts performed on second shift |
| Test booster FTS Safe & Arm on MOTC (T-4 day) | 4 items |
| Deliver and Support Installation of booster FTS Safe & Arm | 4 hours |
Launch of Booster/SV
DRAFT Attachment L-02
Comm Mission Support Tasks
| SV Comm Mission Support | | | | | | | |
| Equipment | Facilities | | | | | | |
| NPF Ctrl Rm 1 | NPF Cntrl Rm 2 | DPF West Cntrl Rm | DPF East Cntrl Rm | SOSF | NPF & DPF Facilities (non-specific locations) | General Mission Support Effort Description |
| Orion COEI | 2 | 6 | 4 | 4 | 1 | - | Circuits remain connected, daily verification checks, process and work approx. 50 comm type changes/issues per SV flow (110 days) |
Provide network programming of all nets on Peas and Orion switches for all NEMO supported operations using Console Level Voice Matrix (CLVM)
| Orion Touch Screen | 4 | 1 | 0 | 0 | - | - |
| Orion SDEI | 0 | 2 | 0 | 0 | 4 | - |
| Orion OEEI | 0 | 2 | 0 | 0 | - | - |
| Pesa P32D Video Selector | 1 | 2 | 0 | 0 | 6 | - |
| Pelco Camera Controller | 0 | 1 | 1 | 1 | - | - |
| Video Monitor (48") | 2 | 2 | 0 | 0 | - | - |
| Video Monitor (9"") | 0 | 4 | 8 | 8 | - | - |
| Video Monitor (55") | 0 | 0 | 0 | 0 | 4 | - |
| Video Monitor (32") | 0 | 0 | 0 | 0 | 4 | - |
| Phones (Desktop/Single Line) | 3 | 4 | 0 | 0 | - | - |
| Phones (Desktop STE) | 1 | 0 | 0 | 0 | - | - |
| Phones (Wall mount/Single Line) | 2 | 4 | 2 | 2 | - | - |
| Phones (Horiz Comm Panel/SL) | 0 | 0 | 4 | 4 | - | - |
| Phones (Spkr Phones) | - | - | - | - | 45 | - |
| Phones (P-Sets) | - | - | - | - | 3 | - |
| Projectors | 0 | 0 | 0 | 0 | 2 | - |
| XTRON Controller | - | - | - | - | 1 | - |
| LAN Drops | - | - | - | - | 55 | 30 |
| PA/AW System | - | - | - | - | 1 | 1 |
| Timing Displays | - | - | - | - | 3 | 13 |
DRAFT Attachment L-02
NEMO Mission Support NEMO Mission Support
| OPERATION | DELIVERABLE / SUPPORT | Quantity | Effort Details |
| SV COMPATABILITY TEST | F-1 NETWORK VALIDATION CHECKS | | Facilities where console support occurs for a typical operation are the TSF, DOC, ASOC, MOC, DPF, NPF. Provide network connectivity, support and comm checks on approx. 106 consoles, totaling 2,704 nets, during all operations. |
CLP= Countdown Launch Procedure
| SV COMPATABILITY TEST | F-0 TECH SUPPORT |
| SV COMPATABILITY TEST | F-0 TECH SUPPORT |
| SV COMPATABILITY TEST | F-0 TECH SUPPORT |
| INTEGRATED CREW EXERCISE #1 | F-1 NETWORK VALIDATION CHECKS |
| INTEGRATED CREW EXERCISE #1 | F-0 NETWORK VALIDATION CHECKS & CONSOLE SUPPORT |
| INTEGRATED CREW EXERCISE #2 | F-1 NETWORK VALIDATION CHECKS |
| INTEGRATED CREW EXERCISE #2 | F-0 NETWORK VALIDATION CHECKS & CONSOLE SUPPORT |
| CLP REHEARSAL #1 | F-0 NETWORK VALIDATION CHECKS |
| CLP REHEARSAL #1 | F-0 TECH SUPPORT |
| FUEL SAMPLING | F-0 TECH SUPPORT |
| CLP REHEARSAL #1 | F-0 TECH SUPPORT |
| FUELING OPERATION | F-1 NETWORK VALIDATION CHECKS |
| FUELING OPERATION | F-0 TECH SUPPORT |
| CLP REHEARSAL #2 | F-0 NETWORK VALIDATION CHECKS |
| CLP REHEARSAL #2 | F-0 TECH SUPPORT |
| MISSION DRESS REHEARSAL | F-1 NETWORK VALIDATION CHECKS |
| MISSION DRESS REHEARSAL | F-0 NETWORK VALIDATION CHECKS & CONSOLE SUPPORT |
| LAUNCH | F-1 NETWORK VALIDATION CHECKS |
| LAUNCH ROLL TO PAD | F-0 NETWORK VALIDATION CHECKS & CONSOLE SUPPORT |
| LAUNCH | F-0 NETWORK VALIDATION CHECKS & CONSOLE SUPPORT |
| NEMO Mission Script Support | | | |
| OPERATION | DELIVERABLE | | |
| INTEGRATED CREW EXERCISE #1 | DRAFT MISSION SCRIPT | 1 | Effort includes developing the Integration Mission Script (IMS) and integrating inputs/changes with the LV, SV and Government. IMS includes L-minus time/T-minus time tag sequence of major milestones and activities in the countdown procedures. The purpose is to highlight those activities that cross organizational boundaries -SV/LV/Range/Contractor/Government. It also integrates the Government polling activity with the basic LV and SV countdown activities. |
| INTEGRATED CREW EXERCISE #1 | FINAL MISSION SCRIPT | 1 | |
| INTEGRATED CREW EXERCISE #2 | DRAFT MISSION SCRIPT | 1 | |
| INTEGRATED CREW EXERCISE #2 | FINAL MISSION SCRIPT | 1 | |
| MISSION DRESS REHEARSAL/LAUNCH | DRAFT MISSION SCRIPT | 1 | |
| MISSION DRESS REHEARSAL/LAUNCH | FINAL MISSION SCRIPT | 1 | |
NEMO Seating Plan Support
INTEGRATED CREW EXERCISE #1 DRAFT CLVM & SEATING PLAN 1 each Develop a Console Level Voice Matrix (CLVM) and provide to 45 LCSS, 5 SLS, CSR, LV and SV customers.
Develop seating plans for consoles located in the following typical launch/SV supported facilities: NPF, DPF, MOC, DOC, and TSF.
| INTEGRATED CREW EXERCISE #1 | FINAL CLVM & SEATING PLAN | 1 each |
| INTEGRATED CREW EXERCISE #2 | DRAFT CLVM & SEATING PLAN | 1 each |
| INTEGRATED CREW EXERCISE #2 | FINAL CLVM & SEATING PLAN | 1 each |
| MISSION DRESS REHEARSAL/LAUNCH | DRAFT CLVM & SEATING PLAN | 1 each |
| MISSION DRESS REHEARSAL/LAUNCH | FINAL CLVM & SEATING PLAN | 1 each |
NEMO Launch Console Handbook Support
INTEGRATED CREW EXERCISE #1 DRAFT LAUNCH CONSOLE HANDBOOK 1 Develop, build and deliver Launch Console Handbooks that include as a minimum the below sections:
1. Countdown
2. Integrated Mission Script
3. Personnel
4. Constraints
5. Mission Overview
6. Supplemental Information
After operation is completed, pickup and breakdown the Launch Console Handbooks.
| INTEGRATED CREW EXERCISE #1 | DRAFT SC LAUNCH CONSOLE HANDBOOK | 1 |
| INTEGRATED CREW EXERCISE #1 | FINAL LAUNCH CONSOLE HANDBOOK | 23 |
| INTEGRATED CREW EXERCISE #1 | FINAL SC LAUNCH CONSOLE HANDBOOK | 33 |
| INTEGRATED CREW EXERCISE #2 | DRAFT LAUNCH CONSOLE HANDBOOK | 1 |
| INTEGRATED CREW EXERCISE #2 | DRAFT SC LAUNCH CONSOLE HANDBOOK | 1 |
| INTEGRATED CREW EXERCISE #2 | FINAL LAUNCH CONSOLE HANDBOOK | 23 |
| INTEGRATED CREW EXERCISE #2 | FINAL SC LAUNCH CONSOLE HANDBOOK | 33 |
| MISSION DRESS REHEARSAL / LAUNCH | DRAFT LAUNCH CONSOLE HANDBOOK | 1 |
| MISSION DRESS REHEARSAL / LAUNCH | DRAFT SC LAUNCH CONSOLE HANDBOOK | 1 |
| MISSION DRESS REHEARSAL / LAUNCH | FINAL LAUNCH CONSOLE HANDBOOK | 42 |
| MISSION DRESS REHEARSAL / LAUNCH | FINAL SC LAUNCH CONSOLE HANDBOOK | 35 |
NEMO Eastern Vehicle Checkout Facility (EVCF) Support Activities
| SV Compatibility Testing | Timing and Comm Support | 1 | Provide timing distribution and two Orion voice unit connectivity and support for each activity. |
| CLP #1 | Timing and Comm Support | 1 | |
| CLP #2 | Timing and Comm Support | 1 | |
| INTEGRATED CREW EXERCISE #1 | Timing and Comm Support | 1 | |
| INTEGRATED CREW EXERCISE #2 | Timing and Comm Support | 1 | |
| F-1 Data Flow | Timing and Comm Support | 1 | |
| Day-of-Launch (DoL) | Timing and Comm Support | 1 | |
DRAFT Attachment L-02
CLVM Example
| Console | Position User / Call Sign | Key Name | 41 CH01 / COUNTDOWN 1 | 41 CH02 / COUNTDOWN 2 | 41 CH03 / MANAGEMENT | 41 CH04 / ENGINEERING | 41 CH05 / RANGE | 41 CH06 / ANOMALY 1 | 41 CH07 / ANOMALY 2 | 41 CH08 / WX CONF | 41 CH09 / SPACECRAFT 1 | 41 CH10 / SPACECRAFT 2 | 41 CH11 / AF INT | 41 CH12 / FLIGHT CONTROL | 41 CH13 / ATLAS LOAD | 41 CH14 / CENTAUR LOAD | 41 CH15 / ATLAS MECH | 41 CH16 / CENTAUR MECH | 41 CH17 / COMM | 41 CH18 / QUALITY | 41 CH19 / AIRBOURNE ELEC | 41 CH20 / FLIGHT TERM SYS | 41 CH21 / GC3 | 41 CH22 / FACILITIES | 41 CH23 / INSTRUMENTATION | 41 CH24 / TDRSS | a af anom 1 | a af anom 2 | a af cord | a af engr | a af mgmt | a af rd-180 anom | a lr mgmt | b net | beach cord | cc lcl | em net | er tlm | fco lcl | flt cord | gps intercom 1 | gps intercom 2 | inst 1 | inst 2 | inststat | mco net | md net a | miss aud | net stat |
| | | ASOC 049 | ASOC 025 | ASOC 050 | ASOC 026 | ASOC 051 | ASOC 027 | ASOC 052 | ASOC 028 | ASOC 053 | ASOC 029 | ASOC 054 | ASOC 030 | ASOC 055 | ASOC 031 | ASOC 056 | ASOC 032 | ASOC 057 | ASOC 033 | ASOC 058 | ASOC 034 | ASOC 059 | ASOC 035 | ASOC 060 | ASOC 036 | ASOC 146 | ASOC 147 | ASOC 148 | ASOC 149 | ASOC 150 | ASOC 188 | ASOC 173 | ASOC 061 | | ASOC 048 | | ASOC 076 | | ASOC 068 | | | | | | | ASOC 151 | ASOC 047 | ASOC 077 |
| 60705.0 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| ST-31 | Comm Mgr 105 | | 1 | | | | | 2 | 3 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 4 | | | 5 |
| ST-34 | Comm Mgr 119 | | 1 | | | | | 2 | 3 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 4 | | | 5 |
| ST-41 | Comm Mgr 120 | | 1 | | | | | 2 | 3 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 4 | | | 5 |
| AE/MDC | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| MUOS OBSVR | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 18 | | 19 |
| MUOS OBSVR | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 18 | | 19 |
| MUOS OBSVR | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 18 | | 19 |
| MUOS OBSVR | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 18 | | 19 |
| ASOC/ESA | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 324 | AFA | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | | 16 | | | 17 | 18 | 19 | 20 | 21 | 22 | 23 | | | | | | | | | | | | | | 24 | | |
| 325 | AGO CE | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | | 16 | | | 17 | 18 | 19 | 20 | 21 | 22 | 23 | | | | | | | | | | | | | | | | |
| 326 | AGO PD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 9 | | 10 | 11 | 12 | | | 13 | 14 | 15 | | | | | 16 | 17 | 18 | 19 | 20 | | 21 | | | | | | | | | | | | | | 22 | | |
| ASOC/MDC | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 125 | LV-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | 12 | 13 | 14 | 15 | | | 16 | | | | | | 17 | 18 | 19 | 20 | 21 | | 22 | | | 23 | | | | | | | | | | | 24 | | |
| 126 | MD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | 18 | | | 17 | | | | | | | | | | | 19 | | |
| 127 | | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | 18 | | | 17 | | | | | | | | | | | 19 | | |
| 131 | MUOS OBSVR | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 18 | | 19 |
| 132 | MUOS OBSVR | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 18 | | 19 |
| 133 | AGO GM | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 9 | | 10 | 11 | 12 | | | | 13 | 14 | | | | | 15 | 16 | 17 | 18 | 19 | | 20 | | | 21 | | | | 22 | | | | | | | 23 | | |
| 134 | DAFLD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 9 | | | | | | | | | | | | | | 10 | 11 | 12 | 13 | 14 | | | | | 15 | | | | | | | | | | | 16 | | |
| 135 | AFLD / AFLDA | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 9 | | | | | | | | | | | | | | 10 | 11 | 12 | 13 | 14 | | | | | 15 | | | | | | | | | | | 16 | | |
| 136 | SVPD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | | | 12 | | 13 | | | | | 14 | | | | | | | | | | | 16 | | 17 |
| 137 | GP-2 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | | 13 | | 14 | | | | | 15 | | | | | | | | | | | 16 | | |
| 138 | GP-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | | 13 | | 14 | | | | | 15 | | | | | | | | | | | 16 | | |
| 139 | AERO 1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | 13 | | | | | | | | | | | 15 | | 16 |
| ASOC/MSR #3 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 3-1 | SVA | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | | | 12 | | 13 | | | | | 14 | | | | | | | | | | | 16 | | 17 |
| 3-2 | BOEING RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | | | 12 | | 13 | | | | | 14 | | | | | | | | | | | 16 | | 17 |
| 3-3 | GPS RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | | 13 | | 14 | | | | | 15 | | | | | | | | | | | 17 | | |
| 3-4 | AERO 2 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | 13 | | | | | | | | | | | 15 | | 16 |
| 3-5 | AERO RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | 13 | | | | | | | | | | | 15 | | 16 |
| 3-6 | GP-5 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | | 13 | | 14 | | | | | 15 | | | | | | | | | | | 17 | | |
| ASOC/MSR #4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 4-1 | SPO ATLAS | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | | 23 | 24 | | | | | | | | | | | | | | | | |
| 4-2 | AGO ATLAS | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | | 23 | 24 | | | | | | | | | | | | | | | | |
| 4-4 | AP-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | | 23 | | | | | | | | | | | | | | | | | |
| 4-5 | AGO 180 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | | 23 | | | | | | | | | | | | | | | | | |
| 4-6 | SPO 180 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | | 23 | 24 | | | | | | | | | | | | | | | | |
| 4-8 | AFP-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | | 9 | 10 | 11 | 12 | 13 | | | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | | 23 | | | | | | | | | | | | | | | | | |
| ASOC/SOC | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 221 | LVTA | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | | | 12 | | 13 | | | | | | | | | | | | | | | | 15 | 16 | 17 |
| ASOC/EXEC CONF ROOM | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| COMM 2-3 | LR COORD | | 1 | 2 | 3 | | 4 | 5 | 6 | 7 | 8 | 9 | | | | | | | 10 | | | | | | | | 11 | 12 | 13 | 14 | 15 | | 16 | | | 17 | | | | | | | | | | | 18 | | 19 |
| COMM 2-4 | LR SIM | | 1 | 2 | 3 | | 4 | 5 | 6 | 7 | 8 | 9 | | | | | | | 10 | | | | | | | | 11 | 12 | 13 | 14 | 15 | | 16 | | | 17 | | | | | | | | | | | 18 | | 19 |
| COMM 2-6 | LR COORD-1 | | 1 | 2 | 3 | | 4 | 5 | 6 | 7 | 8 | 9 | | | | | | | 10 | | | | | | | | 11 | 12 | 13 | 14 | 15 | | 16 | | | 17 | | | | | | | | | | | 18 | | 19 |
| BLDG 1645 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| STA 468 | 5 SLS | | 1 | 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 3 | |
| STA 1074 | 5 SLS | | 1 | 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 3 | |
| MOC/MCR #2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| B-1 | LCG COMM | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | 30 | | 31 | | 32 | | 33 | | | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
| B-34 | GPS SV | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| B-35 | GPS SV | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| B-36 | GPS SV | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| B-37 | GPS SV | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| MOC/MDC | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| B-39 | 45 LCSS RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 19 | 20 | 21 |
| B-40 | ASD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 19 | 20 | 21 |
| B-41 | AFSD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | | | | | | | | 19 | 20 | 21 |
| B-42 | GPS RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | 18 | | | | | | | 20 | 21 | 22 |
| B-43 | GP-3 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | 18 | | | | | | | 20 | 21 | 22 |
| B-44 | GP-4 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | 18 | | | | | | | 20 | 21 | 22 |
| B-45 | AERO 3 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | 13 | | | | | | | | | | | 15 | 16 | 17 |
| B-46 | GPS RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| B-47 | BOEING RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| B-48 | SVVP | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | 11 | 12 | 13 | 14 | 15 | | | | | 16 | | | | | | | | | | | 18 | 19 | 20 |
| MOC/CAB | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| C-9 | LCG / APD | | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | | | | | | | | | | | | | | | 36 | 37 | 38 | 39 | 35 | | | 26 | | 25 | 48 | | 27 | | | | | | 28 | | 40 | 32 | |
| NPF/CTRL RM 1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| S103 | QA | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | 12 | 13 | | | | | | | | | | | | | | | | 14 | 15 | 16 |
| S104 | GSAT | | 1 | 2 | 3 | | 4 | 5 | 6 | 7 | 8 | 9 | | | | | | | | | | | | | | | | | 10 | 11 | 12 | | | | | | | | | 13 | | | | | | | 14 | 15 | 16 |
| S105 | GPS RE | | 1 | 2 | 3 | | 4 | 5 | 6 | 7 | 8 | 9 | | | | | | | | | | | | | | | | | 10 | 11 | 12 | | | | | | | | | 13 | | | | | | | 14 | 15 | 16 |
| S106 | SVCE | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | 12 | 13 | | | | | | | | | 14 | | | | | | | 15 | 16 | 17 |
| S107 | SVCE | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | 12 | 13 | | | | | | | | | 14 | | | | | | | 15 | 16 | 17 |
| S108 | AERO 5 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | 12 | 13 | | | | | | | | | 14 | | | | | | | 15 | 16 | 17 |
| NPF/CTRL RM 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| S109 | STE1/2 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | | | | | | | | | | | | 13 | 14 | 15 |
| S110 | RSVD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | | | | | | | | | | | | 13 | 14 | 15 |
| S111 | AFQS | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | | | | | | | | | | | | 13 | 14 | 15 |
| S112 | FPM | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | | | | | | | | | | | | | 12 | 13 | 14 | 15 | 16 | | | | | 17 | | | | 18 | | | | | | | 19 | 20 | 21 |
| S113 | AERO 4 | | 1 | 2 | 3 | | | 4 | 5 | 6 | 7 | 8 | 9 | | | | | | | | | | | | | | 10 | | 11 | | 12 | | | | | | | | | 13 | | | | | | | 14 | | 15 |
| S114 | SV RAT | | 1 | 2 | 3 | | | 4 | 5 | 6 | 7 | 8 | | | | | | | | | | | | | | | | | 9 | | 10 | | | | | | | | | | 11 | 12 | | | | | 13 | 14 | 15 |
| S115 | TD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | | | | | | 13 | 14 | | | | | 15 | 16 | 17 |
| S116 | SD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | | | | | | | | | | | | | | | | | 11 | | 12 | | | | | | | | | | | | | | | | 13 | 14 | 15 |
| S117 | TE2 | | 1 | 2 | 3 | | | 4 | 5 | 6 | 7 | 8 | | | | | | | | | | | | | | | | | 9 | | 10 | | | | | | | | | | | | | | | | 11 | 12 | 13 |
| SOSF | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| S302 | 45 LCSS | | 1 | 2 | | | | | | | 3 | 4 | 5 | | | | | | | | | | | | | | | | 6 | | 7 | | | | | | | | | | | | | | | | 8 | 9 | 10 |
| S303 | Ops Mgr | | 1 | 2 | | | | | | | 3 | 4 | | | | | | | | | | | | | | | | | 5 | | 6 | | | | | | | | | | | | | | | | 7 | 8 | 9 |
| S304 | Site Mgr | | 1 | 2 | | | | | | | 3 | 4 | | | | | | | | | | | | | | | | | 5 | | 6 | | | | | | | | | | | | | | | | 7 | 8 | 9 |
| S308 | 45 LCSS | | 1 | 2 | | | | | | | 3 | 4 | 5 | | | | | | | | | | | | | | | | 6 | | 7 | | | | | | | | | | | | | | | | 8 | 9 | 10 |
| TSF/LV LSC | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2102A1 | Trng Observer | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | | | 33 | | | | | | | | | | | 35 | 36 | 31 |
| 2102A2 | AM-1 / AFM-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102A3 | AGO Cent / SPO Cent | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | 34 | | | | | | | | | | | | | | | 36 | 31 |
| 2102A4 | AP-2 / AFP-2 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102A5 | AM-2 / AFM-2 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102A6 | AM-3 / AFM-3 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102B1 | AGO Elec / SPO Elec | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | 34 | | | | | | | | | | | | | | | 36 | 31 |
| 2102B2 | AFE-3 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102B3 | AE-1 / AFE-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102B4 | AE-2 / AFE-2 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102B5 | AG-1 / AFG-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | | | | | | | | | | | | | | | | 36 | 31 |
| 2102B6 | AGO GC3 / SPO GC3 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | | 28 | | | 34 | | | | | | | | | | | | | | | 36 | 31 |
| 2102C1 | AERO MIM / LRGI | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | | | | | | | | 35 | 36 | 31 |
| 2102C2 | GMM / GMIM | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | | | | | | | | 35 | 36 | 31 |
| 2102C3 | SPO CE | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | | | | | | | | 35 | 36 | 31 |
| 2102C4 | DCC | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | | | | | | | | 35 | 36 | 31 |
| 2102C5 | MSL / MSL-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | | 41 | 33 | | 38 | | 40 | | | | | | | 35 | 36 | 31 |
| 2102C6 | LSC SPT / LSC SPT-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | | 41 | 33 | | 38 | | 40 | | | | | | | 35 | 36 | 31 |
| 2102D1 | FML / FML-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | | | 33 | | | | 40 | | | | | | | 35 | 36 | 31 |
| 2102D2 | FMLA / FMLA-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | 40 | | | | | | | 35 | 36 | 31 |
| 2102D3 | AFLC / AFLC-1 | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | 40 | | | | | | | 35 | 36 | 31 |
| 2102D4 | CEA / FTL | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | 34 | | | 33 | | | | 40 | | | | | | | 35 | 36 | 31 |
| 2102D5 | TDA / CE | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | | | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | | | 33 | | | | 40 | | | | | | | 35 | 36 | 31 |
| 2102D6 | LCG / LCGTD | | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | | | | | 33 | | | | 40 | | | | | | | 35 | 36 | 31 |
| TSF/TSR | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2106C1 | COMM CORD | | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | | 63 | 85 | 75 | 76 | | 77 | | 62 | | | | | | 74 | 61 | 80 | 73 |
| 2106C2 | COMM CORD | | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | | 63 | 85 | 75 | 76 | | 77 | | 62 | | | | | | 74 | 61 | 80 | 73 |
| 2106C3 | NEMO | | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | | 63 | 85 | 75 | 76 | | 77 | | 62 | | | | | | 74 | 61 | 80 | 73 |
| 2106C4 | NEMO | | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | | 63 | 85 | 75 | 76 | | 77 | | 62 | | | | | | 74 | 61 | 80 | 73 |
| TSF/TECH COMM | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2300 LDS | | | | | | | | | | | 9 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2300 VOICE | TSF COMM | | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | | 63 | 64 | 75 | 65 | | 66 | | 62 | | | | | | | 61 | 69 | 70 |
Inf&Fac Ops
| ITEM | TIME | ELEMENT | SUPPORT TASK | |
| F-10 | 0800E | CCAFS | Provide or service Port-O-Lets as indicated at the following sites no later than F-3 Day. Support Contractor/Contractor Cape Support Office notifies AFLIO @ 476-4046 when complete. | |
| | Water & Waste | | |
| | Support Contractor | LEOC fallback area (2 units) | S-1 North |
| | | UCS-23 / 19110 | deliver by F-5 |
| | POC: | ITL Causeway (near old guard shack) | |
| | Cape Support Office | ITL Causeway (4 units)* | |
| | 853-5211 | AF viewing area (4 units)* | CCAFS South Gate |
| | | AF viewing area (4 units)* | NASA Causeway |
| F-10 | 0800E | CCAFS Power Production | Contact 1) 45 SFS and verify the requirement to provide light carts at posted roadblocks; 2) Emergency Management for light cart at fallback area if required; and 3) NASA for light cart at Building AE. Have in place no later than F-1 day. Support Contractor Cape Support notifies AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
| F-10 | 0800E | CCAFS Power Production | Prepare to deliver and set up searchlights at Complex 41 and light banks at specific locations as described in Cape Support Request. Coordinate with 45 LRS Fuels (494-1365) to ensure searchlight fueling to support max run time of ~ 24 hours. Support Contractor/ Contractor Cape Support notify AF Launch Integration Office at 476-4046 when ready to support. |
| | Support Contractor | NOTE – no fueling operations within 500 ft. of the VIF and SLC 41 fan intakes from 48 hours prior to SC mate until after launch unless coordinated with ULA ECS Engineering (476-5097 / 98) |
| POC: |
| Cape Support Office |
| 853-5211 |
| F-10 | 0800E | CCAFS Power Production | Checkout 36kw generator at Communications Shop (Bldg. 36665), prior to F-1 day. Start generator on Launch Day prior to pick-up of the Range Count. Respond to problems within 1 hour of notification. |
| | Support Contractor | |
| | | Support Contractor/Contractor Cape Support Office notifies AFLIO upon completion. |
| | POC: | |
| | Cape Support Office | |
| | 853-5211 | |
F-10 0800 E Support Contractor PAO Schedule PAO support requirements with Support Contractor/Contractor Cape Support Office as needed. For launches during hours of darkness, ensure lighting units are in place and ready to operate at LEOC fallback area and AF viewing areas* before F-1 day. Support Contractor/Contractor Cape Support Office notify AF Launch Integration Office (AFLIO) @ 476-4046 that all support is scheduled.
| POC: | *NOTE: Work to be billed to 45 SW Institutional JON. |
| Cape Support Office | |
| 853-5211 | |
| F-5 | 0800E | CCAFS Power Production | Perform critical checks at the following facilities with completion no later than F-1 day. Verify PMIs are current, no open tasks are in work, and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. | |
| | Support Contractor | | |
| | | FACILITY | NUMBER |
| | POC: | XY Building | 1641 |
| | Cape Support Office | Power Dispatch Office (R&D) | 1708 |
| | 853-5211 | Generator Building | 54708 |
| | | UHF Timing Tower | 54715 |
| | | Building AE | 60680 |
| | | MOC Generator Plant1 | 81730 |
| | | NOTE: 1) On DOL, two (2) Generator Mechanics on standby at MOC Generator Plant L-90 minutes through T + 120 minutes or release by CSR personnel. | |
DATE: _____/_____/_____ TIME_________ NAME:________________________________
| F-5 | 0800E | CCAFS HVAC | Perform critical checks at facilities listed below with completion no later than F-1 day. Verify PMIs are current, no open tasks are in work, and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Support Contractor | |
| | | NOTES: 1. For GPS IIF-7, HVAC on-site support required at Building AE from 1830 until 0200 hours (L +1) day unless otherwise released by Building AE personnel. |
| | POC: | 2. Plus count support required for MOC, Building AE, and XY Bldg. until ~ T + 3h or until release by CSR personnel. Standby support at shop is sufficient. |
| | Cape Support Office | 3. HVAC/EMCS controls for CCAFS facilities maintained by 45 CES at 494-4477. Contractor HVAC trouble team can respond for HVAC issues. |
| | 853-5211 | FACILITY |
| | | Receivers |
| | | XY Building |
| | | Chiller Plant Building |
| | | Power Dispatch Office (R&D) |
| | | Weather Station |
| | | Communications Shop (N. Tip Shack) |
| | | UHF Timing Facility |
| | | Building AE |
| | | Command and Control |
| | | Emergency Power Bldg. |
| | | Electrical Power Station |
| | | Morrell Operations Center |
| | | Satellite Comm Grnd Trml |
| | | Satellite Comm Grnd Trml |
| | | BIDDS Telephone Bldg. |
| RADAR SITES |
| Radar 1.16 |
| 1.21 (Sea Surveillance Radar S.) |
| CABLE TERMINAL BUILDINGS |
| South Terminal Bldg. |
| East Terminal Bldg. |
| North Terminal Bldg. |
| Southwest Terminal Bldg. |
| Northwest Terminal Bldg. |
| F-5 | 0800E | CCAFS | Perform critical checks at facilities listed below with completion no later than F-1 day. Verify PMIs are current, no open tasks are in work, and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Interior Electric (L/V) | |
| | Support Contractor | NOTES : 1. For GPS IIF-7, LV on-site support required at Building AE from 1830 on launch day until 0200 hours (L + 1) unless otherwise released by Building AE personnel. |
| | | 2. Plus count support required for MOC, Building AE and XY Bldg. until ~ T + 3h or until release by CSR personnel. Standby support at shop is sufficient. |
| POC: | FACILITY | NUMBER |
| Cape Support Office | | |
| 853-5211 | Receivers | 1102 |
| XY Building | 1641 |
| Chiller Plant Building | 1646 |
| TV Operations | 1663 |
| Power Dispatch Office (R&D) | 1708 |
| Weather Station | 20185 |
| North Warning Device | 36606 |
| Communications Shop | 36665 |
| Skid Strip Tower | 50210 |
| UHF Timing Tower | 54714 |
| UHF Timing Facility | 54715 |
| Building AE | 60680 |
| South Warning Device | 63200 |
| Command and Control | 81550 |
| Emergency Power Bldg. | 81551 |
| Electrical Power Station | 81565 |
| Morrell Operations Center | 81900 |
| Satellite Comm Grnd Trml | 81905 |
| Satellite Comm Grnd Trml | 81906 |
| BIDDS Telephone Bldg. | 90400 |
| RADAR SITES | |
| Radar 1.16 | 50166 |
| SSR South 1.21 (Sea Surveillance Radar S.) | 46712 |
| CABLE TERMINAL BLDGS. | |
| S. Cable Terminal Bldg. | 1307 |
| E. Cable Terminal Bldg. | 1532 |
| N. Cable Terminal Bldg. | 1664 |
| NW Cable Terminal Bldg. | 70499 |
| SW Cable Terminal Bldg. | 78150 |
| F-5 | 0800E | CCAFS | Perform critical checks at facilities listed below no later than F-1 day. Verify PMIs are current, no open tasks are in work, and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Exterior Electric (HV) Support Contractor | |
| POC: | FACILITY | NUMBER |
| Cape Support Office | | |
| 853-5211 | SUBSTATIONS | |
| CCAFS Substation Yard | 49775 |
| North Substation | 60302 |
| Titan Substation | 63805 |
| Command Control Substation | 81567 |
| South Substation | 85300 |
| SWITCH STATIONS | |
| Switch Station #7 | 81727 |
| Switch Station #37 | 38221 |
Patrol Overhead Lines
| F-5 | 0800E | CCAFS Compressed Air | Perform critical checks at the following facilities complete by F-1 day. Verify PMIs are current; no open tasks are in work and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. | |
| | Facility Systems | | |
| | Support Contractor | | |
| | | FACILITY | NUMBER |
| | POC: | | |
| | Cape Support Office | South Cable Terminal Building | 1307 |
| | 853-5211 | XY Building | 1641 |
| | | North Cable Terminal Bldg. | 1664 |
| | | SW Cable Terminal Bldg. | 78150 |
| F-5 | 0800E | CCAFS | Perform system checks at the following facilities by F-1 day. Verify PMIs are current; no open tasks are in work and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. | |
| | Support Contractor | | |
| | | FACILITY | NUMBER |
| | POC: | | |
| | Cape Support Office | XY Bldg. | 1641 |
| | 853-5211 | Building AE | 60680 |
| | | Command and Control | 81550 |
| | | Morrell Operations Center | 81900 |
| F-5 | 0800E | Florida Annexes HVAC, LV, | Perform critical checks at the following facilities by F-1 day. Verify PMIs are current; no open tasks are in work and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. | |
| | Support Contractor | | |
| | | NOTE – generators to be on line at L-480 minutes on day of launch. | |
| | POC : | | |
| | Cape Support Office | FACILITY | NUMBER |
| | 853-5211 | | |
| | | JDMTA | |
| | | Instrumentation Building | 28001 |
| | | Powerhouse Building | 28002 |
| | | Bore Sight Building | 28010 |
| | | TLM Antenna Mount #5 (TAA-50-5) | 28012 |
| | | TLM Antenna Mount #3 (TAA-50-3) | 28014 |
| | | Command Radome #2 | 28015 |
| | | Command Radome #1 | 28016 |
| | | TLM Antenna Mount # 2 | 28018 |
| | | TLM Antenna Mount #1 | 28019 |
| Stuart Microwave Relay Site | 28101 |
| Fort Pierce Microwave Relay Site | 28201 |
| Wabasso Microwave Relay Site | 28301 |
| F-5 | 0800E | Florida Annexes Gen Power | Perform critical checks at the following facility by F-1 day. Verify PMIs are current; no open tasks are in work and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Support Contractor | |
| POC: | JDMTA | |
| Cape Support Office | Powerhouse Building (include generators) | 28002 |
| 853-5211 | | |
| F-5 | 0800E | Florida Annexes ESS-F/A | Perform critical checks at the following facilities by F-1 day. Verify PMIs are current; no open tasks are in work and identify any non-standard configuration. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Support Contractor | |
| POC: | JDMTA | |
| Cape Support Office | Instrumentation Building | 28001 |
| 853-5211 | Bore Site Building | 28010 |
| F-5 | CCAFS Cape Support Office | CAPE SUPPORT OFFICE WILL BROADCAST MESSAGE 1, SCHEDULED LAUNCH ANNOUNCEMENT, VIA THE CAPE AURAL WARNING SYSTEM STARTING AT L-48 HOURS AND REPEATING EVERY 4 HOURS. On launch day, Cape Support will broadcast at L-242 minutes and L-182 minutes. |
| Support Contractor | |
| | ANNOUNCEMENT: “A Launch from Complex 41 is scheduled for (date). We will use the Cape Aural Warning System to advise you of required actions. Launch Toxic Shelters may be required for your protection. Approved Launch Toxic Shelters are identified with a brown sign at the main facility entrance. Your cooperation is essential to avoid personal risk or injury. “ (REPEAT) |
| POC: 853-5211 | |
| Roll Out | 1000 | CCAFS Power Production | Deliver and set up (6) self-powered light banks as follows: |
| | Support Contractor | |
| | | - One (1) on Transporter Road at security checkpoint on the west side at the “Y”; |
| | POC: | - Three (3) at the ITL Warehouse north parking lot; and |
| | Cape Support Office | - Two (2) at ASOC west side of east parking lot entrance and east side of west parking lot entrances. |
| | 853-5211 | |
| | | NOTE: light banks will be activated before dark on 31 Jul and will be deactivated at sunrise on DOL. |
Notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete.
| Roll Out | Prior to | CCAFS Power Production | Coordinate with ULA Launch Conductor (853-5961) to place and activate nine (9) 10 kW searchlight units (including generators) on SLC 41 at locations defined per drawing 41-0110011, Sheet T-004 provided earlier. Activate searchlights in the afternoon prior to leaving for the day and bore sight as follows: |
| Roll Out | Leaving for the day | Support Contractor | |
| | | 1) Lighting to provide 360 degree evenly dispersed coverage of the launch vehicle and Mobile Launch Platform (MLP) from the base of the MLP to the top of the payload fairing (overall height of 200’). |
| | POC: | |
| | Cape Support Office | 2) Lighting to be placed between 350’ and 550’ from the launch vehicle. |
| | 853-5211 | |
| | | Ensure generators are fueled and lights configured for continuous use from evening of Roll Day until after launch. Maximum run time between fueling will be ~ 24 hours. Support Contractor Cape Support notifies AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| F-1 | 800 | CCAFS | Verify launch complex is on preferred feeder through launch. Verify derrick digger and high rangers are operational and ready. Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | Exterior Electric Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
F-1 1200 ALL AREAS Report completion of all critical checks / preventive maintenance inspections, disposition any open tasks that are in work and identify any non-standard configuration or anomalies to AF Launch Integration Office (AFLIO) @ 476-4046.
| F-1 | 1523 E | L - 480 | Florida Annexes (L/V., GEN., HVAC) | Trouble teams on duty at JDMTA. Ensure generators are on-line and verifications completed. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 1923 Z | T - 430 | Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
| Day of | 1723 E | L - 360 | CCAFS Power Production | Generator Rover Team on standby at shop through launch until released. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| Day of | 2123 Z | T - 310 | Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
| Day of | 1723 E | L - 360 | CCAFS Logistics Services | Logistic Coordinator on site at Building 1621 through launch until released. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2123 Z | T - 310 | Support Contractor | |
| POC: | |
| Cape Support Office | |
| 853-5211 | |
| TIME: __________ NAME: ___________________________________ |
| Day of | 1723 E | L - 360 | CCAFS HVAC | HVAC trouble team to standby at A/C shop and second HVAC trouble team to standby at the MOC through launch until released. Shop team will rove XY Bldg as needed. |
| 2123 Z | T - 310 | Support Contractor | |
| | | | Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| | | POC: | |
| | | Cape Support Office | |
| | | 853-5211 | |
| | | | TIME: ________ NAME: __________________________________(MOC) |
TIME: ________ NAME: __________________________________(SHOP)
| Day of | 1723 E | L - 360 | CCAFS | Fire Alarm Tech on standby at Hangar D shop through launch until released. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2123 Z | T - 310 | Fire Alarm/ESS (Siemens) | |
| POC: |
| Cape Support Office |
| 853-5211 |
TIME: __________ NAME: ___________________________________
| Day of | 1723 E | L - 360 | CCAFS | Low voltage rover teams on standby at MOC and at the shop through launch. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when ready to support. |
| 2123 Z | T - 310 | Rover Team (LV) | |
| | | Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
| Day of | 1723 E | L - 360 | CCAFS | High Voltage trouble team on standby at shop through launch until released. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2123 Z | T - 310 | Exterior Electric Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
TIME: __________ NAME: ___________________________________
| Day of | 1723 E | L - 360 | CCAFS | Power Dispatcher at Hangar R&D on standby through launch until released. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2123 Z | T - 310 | Power Dispatcher Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
| Day of | 1815 E | CCAFS Power Production | Reactivate searchlights at SLC 41. Contact the ULA Launch Conductor for re-entry to SLC 41 post launch. Slips or scrubs will be handled on a case-by-case basis. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2215 Z | Support Contractor | |
| POC: |
| Cape Support Office |
| 853-5211 |
| 24 | 1830 E | CCAFS HVAC | Provide on-site at Building AE until 0200 hours or release by AE personnel on DOL. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2230 Z | Support Contractor | |
| Cape Support Office |
| 853-5211 |
| Day of | 1830 E | CCAFS | Provide on-site support at Building AE until 0200 hours or release by AE personnel on DOL. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| 2230 Z | Interior Electric (LV) | |
| | Support Contractor | |
| Cape Support Office |
| 853-5211 |
| Day of | 1921 E | L - 242 | CCAFS Cape Support Office | Broadcast the following announcement via the Cape Aural Warning System: |
| 2321 Z | T - 192 | Support Contractor | |
| | | | " A launch from Complex 41 is scheduled for _______________. We will use the Cape Aural Warning System to advise you of required actions. Launch Toxic Shelters may be required for your protection. Approved Launch Toxic Shelters are identified with a brown sign at the main facility entrance. Your cooperation is essential to avoid personal risk or injury." |
| | | POC: | |
| | | Cape Support Office | NOTE: Before each broadcast, contact the ISRO to avoid conflicting with countdown announcements. |
| | | 853-5211 | |
| Day of | 1930 E | CCAFS Power Production | Activate light banks at the “Y” on Transporter Road, ITL Warehouse parking lot and ASOC entrances prior to dusk. Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when complete. |
| 2330 Z | Support Contractor (Contractor) | |
| POC: |
| Cape Support Office |
| 853-5211 |
| Day of | 2021 E | L - 182 | CCAFS Cape Support Office | Broadcast the following announcement via the Cape Aural Warning System: |
| 0021 Z | T - 132 | Support Contractor (Contractor) | |
| POC: | |
| Cape Support Office | |
| 853-5211 | |
| " A launch from Complex 41 is scheduled for today, ___________. We will use the Cape Aural Warning System to advise you of required actions. Launch Toxic Shelters may be required for your protection. Approved Launch Toxic Shelters are identified with a brown sign at the main facility entrance. Your cooperation is essential to avoid personal risk or injury." |
NOTE: Before each broadcast, contact the ISRO to avoid conflicting with countdown announcements.
TIME: __________ NAME: ___________________________________
| Day of | 2153 E | L - 90 | CCAFS Power Production | (2) Generator mechanics on site at the MOC Generator Plant in support of MOC and Receivers Bldg through launch until T + 120 minutes or release by CSR personnel. |
| 0153 Z | T - 70 | Support Contractor (Contractor) | |
| | | | Support Contractor/Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396 when on site. |
| | | POC: | |
| | | Cape Support Office | |
| | | 853-5211 | |
| Day of | 2243 E | L - 40 | ALL AREAS | Report mission capability status (FMC/PMC/NMC) to AF Launch Integration Office (AFLIO) @ Console B15 (853-8081); LAN Line 853-8396. |
| 0243 Z | T - 20 | | ORGANIZATION STATUS POC |
| Day of | 2259 E | L - 24 | | START OF PLANNED 20 MINUTE BUILT-IN HOLD. |
| 0259 Z | T - 4 | ALL AREAS | |
| 2319 E | L - 4 | | |
| Day of | 0319 Z | T- 4 | ALL AREAS | END OF PLANNED 20 MINUTE BUILT-IN HOLD. RESUME COUNT. |
| | Support Contractor | | |
| Contractor | | ____________________________/_______________ | |
NOTES:
| 1) HVAC and LV on-site support for Hangar AE from 1830 until 0200 hours unless otherwise released by AE personnel. |
| 2) Plus count support for MOC, XY Bldg. and Hangar AE required through ~ T + 3h or end of plus count. CSR Network Ops (853-9555) will notify Cape Support Office that plus count is terminated. |
| L+1 | 800 | L + 1 Day | CCAFS Power Production | Remove all generators, light banks and searchlights used in support of launch. Contact ULA Atlas Launch Conductor |
| | | Support Contractor (Contractor) | (853-5961) for pad re-entry. Slips or scrubs will be handled on a case by case basis. |
| | | POC: | Support Contractor / Contractor Cape Support notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| | | Cape Support Office | |
| | | 853-5211 | |
| | | | DATE: ____/____/____ TIME: _____ NAME: ________________________ |
| | | | Remove all port-o-lets used in support of this mission. Support Contractor / Contractor Cape Support Office notify AF Launch Integration Office (AFLIO) @ 476-4046 when complete. |
| L+1 | 800 | L + 1 Day | CCAFS | |
| | | Water & Waste | |
| | | Support Contractor (Contractor) | |
| POC: |
| Cape Support Office |
| 853-5211 |
| CCAFS Cape Support Office | MESSAGE 2, Launch Toxic Shelter Identification Announcement. If directed by 45 SW/SE, this announcement is made to affected aural warning zones via the CAWS at L-122 minutes, L-97 minutes and L-72 minutes. (REPEAT) |
| Support Contractor (Contractor) | |
| NOTE: Before each broadcast, contact the ISRO to avoid conflicting with countdown announcements. |
| POC: 853-5211 | |
| CCAFS Cape Support Office | MESSAGE 3, Risk Mitigation Announcement. If directed by 45 SW/SE, this announcement (3A (Toxic Dispersion), 3B (Distant Focusing Overpressure [DFO], or both) is made to affected aural warning zones via the CAWS at L-57 minutes, L-32 minutes and L-17 minutes. (REPEAT) |
| Support Contractor (Contractor) | |
| NOTE: Before each broadcast, contact the ISRO to avoid conflicting with countdown announcements. |
| POC: 853-5211 | |
| CCAFS Cape Support Office | MESSAGE 4, Accident Announcement. If directed by 45 SW/SE following a catastrophic launch abort in the launch area, broadcast this announcement across all aural warning zones via the CAWS: |
| Support Contractor (Contractor) | 4A – toxic dispersion, DFO and debris risk are not a concern. |
| 4B – toxic dispersion risk is a concern. |
| POC: 853-5211 | 4C – when debris risk is a concern (within the FCA/FHA). |
| 4d – when toxic dispersion and debris risk (within the FCA/FHA) are concerns. |
| (REPEAT) |
NOTE – 45 SW/SE will provide specific, detailed messages by L-10 minutes.
| 4 | CCAFS Cape Support Office | MESSAGE 5, Toxic Plume Announcement. If directed by 45 SW/SE when specific areas of CCAFS are affected by the exhaust plume, broadcast this announcement to affected aural warning zones via the CAWS. Repeat 10 minutes before the toxic plume arrives; 5 minutes before the toxic plume arrives; and as the toxic plume arrived. (REPEAT) |
| Support Contractor (Contractor) | |
POC: 853-5211
| 5 | CCAFS Cape Support Office | MESSAGE 6, All Clear Announcement (For Personnel Outside Identified Affected Areas). If directed by 45 SW/SE, broadcast this announcement across all aural warning zones via the CAWS. (REPEAT) |
| Support Contractor (Contractor) | |
| | NOTE: upon agreement between 45 SW/SE, the Launch EOC Director, and 45 AMDS/SGGB, personnel outside of the affected area may be able to resume normal activities prior to the “All Clear” for the entire Cape. |
| POC: 853-5211 | |
| 6 | CCAFS Cape Support Office | MESSAGE 7, All Clear Announcement. If directed by 45 SW/SE, broadcast this announcement across all aural warning zones via the CAWS. (REPEAT) |
| Support Contractor (Contractor) | |
| | NOTE: upon agreement between 45 SW/SE, the Launch EOC Director, and 45 AMDS/SGGB, personnel may resume normal activities. |
| POC: 853-5211 | |
| 7 | CCAFS Cape Support Office | Cape Support personnel may be directed to operate the radios monitoring the situation and assisting with any actions required by the Launch EOC Team. |
| Support Contractor (Contractor) | |
POC: 853-5211
DATE: ____/____/____ TIME: _____ NAME: ________________________
| 8 | CCAFS Cape Support Office | Recall additional Support Contractor Cape Support personnel as needed. |
| Support Contractor (Contractor) | |
POC: 853-5211
DATE: ____/____/____ TIME: _____ NAME: ________________________
| 9 | CCAFS Cape Support Office | Relay all pertinent information to PAFB Command Post (494-7001). |
| Support Contractor (Contractor) | |
POC: 853-5211
Sheet1