This solicitation requests proposals for the continued operation of the Air Force Primary Standards Laboratory located in Heath, Ohio. Proposals are due by March 31, 2020 and the contract is expected to be awarded by September 30, 2020.
The solicitation seeks a contractor to perform calibration and technical order development services at the AFPSL. Key requirements include calibrating Air Force customer standards, specialized testing, developing and revising calibration technical orders, and providing technical assistance and laboratory scheduling. Pricing includes fixed price, fixed price incentive, and cost reimbursement CLINs for various contract activities. The Department of the Air Force Materiel Command Lifecycle Management Center is the issuing agency. Proposals shall address staffing, quality plans, technical order development, and measurement capabilities. Relevant past performance and price data must also be submitted.
View the file
Other files for this federal contract opportunity
Show all 50
AFPSL Recompete has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number FA2263-20-R-0002 RFP Attachment
SECTION L
Instructions, Conditions, and Notices to Offerors or Respondents
1 PROGRAM INFORMATION
1.1 Program Structure and Objectives
This acquisition is for the continued operation of the Air Force Primary Standards Laboratory (AFPSL) located in Heath, Ohio, and the development and distribution of calibration technical manuals for the Air Force Metrology Calibration Program (AFMETCAL). The AFPSL is the highest echelon metrology and calibration laboratory in the Air Force. It provides a critical link between the National Institute of Standards and Technology (NIST) and Air Force Precision Measurement Equipment Laboratories (PMELs) and houses a measurement capability in practically every measurement discipline with a precision and accuracy unequalled in the Air Force. The AFPSL complex consists of laboratories with rigid environmental controls necessary for precise measurements in many measurement disciplines. The AFPSL provides calibration services and exchange standards to Air Force PMELs. It is the sole source of Air Force measurement standards, base reference standards, and other highly specialized calibration services. The AFPSL’s functions ensure Air Force measurements are accurate, uniform, reliable, and traceable to NIST. Supplies, services, and tasks required for sustainment of calibration services by the AFPSL and technical order developments are listed below.
A. Major Tasks The successful offeror shall perform calibration and calibration technical order development services.
a. Calibrate Air Force customer standards.
b. Perform specialized testing in support of Air Force Program Offices, Research and Development Laboratories, item managers, single managers, and AFMETCAL.
c. Develop, revise, and distribute calibration technical orders (TOs).
d. Provide technical assistance.
e. Perform laboratory scheduling and inventory actions.
f. Comply with AFMETCAL quality and facility requirements and maintain laboratory certification.
B. Support Tasks
a. Maintain storage areas with protection against loss, damage, and adverse environmental conditions to meet requirements of a Government approved bond room.
b. Maintain classified storage for end items and technical data with security classifications up to and including Secret.
c. Conduct inventory and property management.
d. Provide preservation, packaging, and transportation.
The pricing arrangement for this contract can be seen in the included table. This table shows the CLIN structure for the first six month period of the contract. The remaining basic and option years are the same structure minus the Transition CLIN. The structure is firm fixed price for contract transition; fixed price with an incentive fee for exceptional performance for the operation of the AFPSL to include acceptance testing, RADIAC calibration services, and fixed price with an incentive fee for the development and distribution of calibration technical manuals. Cost reimbursable for FMS calibration services and external calibration and repair services. Cost will be provided for all cost reimbursable CLINs associated with the contract. The pricing arrangement was selected based upon the risk assessments and the nature of the contracting effort.
| Item # |
| Name |
| Type |
| 0001 |
| AFPSL Transition Activities |
| FFP |
| 0002 |
| Calibration Services, AFPSL Operations |
| FFP w/Incentive |
| 0003 |
| Radiac Calibration Services |
| FFP w/Incentive |
| 0004 |
| External Calibration & Repair Services |
| Cost |
| 0005 |
| Calibration Services FMS |
| Cost |
| 0006 |
| Calibration Technical Orders |
| FFP w/Incentive |
| 0007 |
| Special Calibration Services - Project Plans |
| FFP |
| 0007AA |
| Training |
| FFP |
| 0007AB |
| Contractor Travel |
| FFP |
Lease Cost Cost
| Cost Reimbursable Workloads |
| Cost |
| 0010 |
| Data Requirements |
| NSP |
2 GENERAL INSTRUCTIONS
The offeror's proposal must include all data and information requested by this Information to Offerors (ITO) and must be submitted IAW these instructions. The offer shall be compliant with the requirements as stated in the Performance Work Statement (PWS), Contract Data Requirements List (CDRL), and RFP. Non-conformance with the instructions provided in this ITO may result in an unfavorable proposal evaluation. Any proposal, modification, or revision that is received at the designated government office after the exact time specified for receipt of proposals will be handled in accordance with Federal Acquisition Regulation (FAR) 15.208(b)(1).
The proposal shall be clear, concise, and shall include sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposal should not simply rephrase or restate the Government's requirements but, rather, shall provide convincing rationale to address how the offeror intends to meet these requirements. Offerors shall assume that the Government has no prior knowledge of their facilities or experience and will base its evaluation on the information presented in the offeror's proposal.
Elaborate brochures or documentation, binding, detailed art work, or other embellishments are unnecessary and are not desired.
The proposal acceptance period will be the date of RFP release to 31 March 2020, 2 pm EDT. Proposals shall be valid through 30 September 2020. The offeror shall make a clear statement in Section A of the Contract Documentation Volume IV that the proposal is valid through this date.
IAW FAR Subpart 4.8 (Government Contract Files), the Government will retain one electronic copy of all unsuccessful proposals. The Government will destroy extra copies of such unsuccessful proposals.
2.1 Point of Contact
The Contracting Officer (CO) is the sole point of contact for this acquisition. Address any questions or concerns you may have to the CO. Written requests for clarification may be sent to the CO at the address located in Section A of the model contract/solicitation.
2.2 Debriefings
The CO will promptly notify offerors of any decision to exclude them from the competitive range; whereupon, they may request and receive a debriefing IAW FAR 15.505. Offerors excluded from the competitive range may request a pre-award debriefing within 3 days of exclusion. The CO will notify unsuccessful offerors in the competitive range of the source selection decision IAW FAR 15.506. Upon such notification, unsuccessful offerors may request and receive a debriefing. Offerors desiring a debriefing must make their request IAW the requirements of FAR 15.505 or 15.506, as applicable.
2.3 Discrepancies
If an offeror believes that the requirements in these instructions contain an error, omission, or are otherwise unsound, the offeror shall immediately notify the CO in writing with supporting rationale, as well as, the remedies the offeror is asking the CO to consider as related to the omission or error.
2.4 Electronic Reference Documents
All referenced documents for this solicitation are available on the Contract Opportunities on the Beta SAM website at https://www.beta.sam.gov. Potential offerors are encouraged to subscribe for real-time e-mail notifications when information has been posted to the website for this solicitation. This is a public access site, no special permissions are required to access the Bidder's Library. The point of contact for the library content is the Contracting Officer, Michael Hickey, AFLCMC/WNM, 740-788-5043. The library will be available online, 24 hours a day through the receipt of proposals.
2.5 Communications
Exchanges of source selection information between the Government and offerors will be controlled by the CO, Michael Hickey, email: michael.hickey.2@us.af.mil. Source Selection information will be transmitted via direct mailing or DoD SAFE at https://safe.apps.mil. Email through DoD SAFE may be used to transmit such information and must include “Source Selection Information - See FAR 2.101 and FAR 3.104, For Official Use Only (FOUO)” in the subject line of the email.
3 PROPOSAL PREPARATION INSTRUCTIONS
3.1 Organization/Number of Copies/Page Limits
The offeror shall prepare the proposal as set forth in the Proposal Organization Table (Table 3.1). The titles and contents of the volumes shall be as defined in this table, all of which shall be within the required page limits and with the number of copies as specified in Table 3.1. The attachments identified in the table should be separately bound in three-ring, loose-leaf binders, as necessary. The contents of each proposal volume are described in the ITO paragraph as noted in the table below:
Table 3.1 - Proposal Organization
| VOLUME |
| ITO Paragraph |
Number
| VOLUME TITLE |
| COPIES * |
| PAGE LIMIT |
| I |
| 4.1 |
| Executive Summary |
| 3 Hard |
1 Electronic
| II |
| 4.2 |
| Technical |
| 8 Hard |
1 Electronic
| II - Attach |
| 4.2.2 |
| Transition Plan (as described in PWS Section 7) |
Draft Quality Plan (in contractor format)
Draft Technical Manual Production Plan (in contractor format)
Draft Measurement Area Capabilities Document (in contractor format) 8 Hard 1 Electronic 200 Total
| III |
| 5.0 |
| Relevant Past and Present Performance |
| Submitted in PPI Tool |
| See 5.0 |
| IV |
| 6.0 |
| Price |
| 3 Hard |
1 Electronic Unlimited
| V |
| 7.0 |
| Contract Documentation |
| 3 Hard |
1 Electronic Unlimited
3.1.1 Page Limitations
Page limitations shall be treated as maximums. If exceeded, the excess pages will not be read or considered in the evaluation of the proposal. Page limitations shall be placed on responses to evaluation notices (ENs). The specified page limits for EN responses will be identified in the letters forwarding the ENs to the offerors. When both sides of a sheet display printed material, it shall be counted as two pages. Additionally, each volume shall contain a table of abbreviations used, with their respective explanations. Tab indexing shall be used to identify all sections. The tables of contents, tab indexes that contain no information other than section information, and tables of abbreviations, glossaries (as required), are excluded from the total page count.
3.1.2 Page Size and Format
(a) A page is defined as each face of a sheet of paper containing information. When both sides of a sheet display printed material, it shall be counted as two pages. Page size shall be 8.5 x 11 inches, not including foldouts. Pages shall be double spaced. Except for the reproduced sections of the solicitation document, the font shall be Times New Roman and the text size shall be no less than 12 point. Tracking, kerning, and leading values shall not be changed from the default values of the word processing or page layout software. Use at least 1-inch margins on the top and bottom and 3/4-inch side margins. Pages shall be numbered sequentially by volume. These page size and format restrictions shall apply to responses to ENs. These limitations shall apply to both electronic and hard copy proposals. For Past Performance Information Tool printouts, use the default page size and format from the tool.
(b) Legible tables, charts, graphs, and figures shall be used wherever practical to depict organizations, systems and layout, implementation schedules, plans, etc. These displays shall be uncomplicated, legible, and shall not exceed 11 by 17 inches in size. Foldout pages shall fold entirely within the volume, and count as a single page. Foldout pages may only be used for large tables, charts, graphs, diagrams, and schematics not for pages of text. For tables, charts, graphs and figures, the text shall be no smaller than 8 point.
3.2 Pricing Related Data
All pricing information shall be addressed ONLY in the Price Proposal and Contract Documentation Volumes. Cost trade off information, work hour estimates and material kinds and quantities may be used in other volumes only as appropriate for presenting rationale for alternatives or design and trade off decisions.
3.3 Classified Information
The proposal shall not contain Classified information.
3.4 Cross-Referencing
To the greatest extent possible, each volume shall be written on a stand-alone basis so that its contents may be evaluated with a minimum of cross referencing to other volumes of the proposal. Information required for proposal evaluation which is not found in its designated volume will be assumed to have been omitted from the proposal.
Cross-referencing within a proposal volume is permitted where its use would conserve space without impairing clarity.
The offeror shall provide a cross reference matrix indicating, by ITO or PWS paragraph number, the corresponding proposal paragraph in that section which addresses the referenced item.
3.5 Indexing
Each volume shall contain a detailed table of contents to delineate the subparagraphs within that volume. Tab indexing shall be used to identify sections.
3.6 Glossary of Abbreviations and Acronyms
Each volume shall contain a glossary of all abbreviations and acronyms used, and with an explanation for each. Glossaries do not count against the page limitations for their respective volumes.
3.7 Binding and Labeling
Each volume of the proposal should be separately bound in a three-ring, loose leaf binder permitting the volume to lie flat when open. Staples shall not be used. A cover sheet should be bound in each book, clearly marked as to volume number, title, copy number, solicitation identification, and the offeror's name. The same identifying data should be placed on the spine of each binder. All unclassified document binders shall have a color other than red or other applicable security designation colors. Be sure to apply all appropriate markings including those prescribed IAW FAR 52.215-1(e), Restriction on disclosure and use of data, and FAR 3.104-4, Disclosure, Protection, and Marking of Contractor Bid or Proposal Information and Source Selection Information.
3.8 Electronic Offers
The content and page size of electronic copies must be identical to the hard copies. For electronic copies, indicate on each CD the volume number and title. Use separate files to permit rapid location of all portions, including subfactors, exhibits, annexes, and attachments, if any. The offeror shall submit volumes I, II, IV, and V in electronic format, using recordable CDs. Each volume shall be in a different directory on a CD. If files are compressed, the necessary decompression program must be included. In the event that hard copies and electronic copies of a proposal are submitted and if there are any discrepancies between the hard copies and the electronic copies of the proposal, the hard copies will be used for evaluation. The electronic copies of the proposal shall be submitted only using Microsoft Office 2010 or newer, and Adobe Acrobat or newer:
1. Word documents - Set "Save as type" to "Word Document (*.docx)" only.
2. Excel spreadsheets - Set “Save as type” to “Microsoft Excel Workbook (*.xlsx).”
3. Submit any Microsoft Project files in Microsoft Project 2010 or newer. There are no special “save” functions required for later versions of Project.
4. Offerors shall submit PDF documents using only Adobe Acrobat 9.0 or later. Do NOT submit any documents in PDF format that are copied as “images.” When creating PDF files always create to enable textual search and copy functions.
3.9 Distribution
The "original" hard copy proposal shall be identified. All hard and electronic proposals shall be addressed to the Contracting Officer and mailed to:
AFLCMC/WNMK
Attn: Mr. Michael Hickey, PCO Solicitation #FA2263-20-R-0002 813 Irving-Wick Dr. W.
Heath, OH 43056-6116
Be sure to advise the Administrative Contracting Officer (ACO) and the Defense Contract Audit Agency (DCAA) for prime and subcontractors that the proposal is "For Official Use Only" and "Source Selection Information--See FAR 2.101 and FAR 3.104".
4 PROPOSAL ORGANIZATION
4.1 Volume I Executive Summary
In the executive summary volume, the offeror shall provide the following information:
4.1.1 Narrative Summary
The narrative summary of the entire proposal should be concise, to include addressing the significant risks, and highlighting any key or unique features, excluding price. The salient features should tie in with Section M evaluation factors/subfactors. Any summary material presented here shall not be considered as meeting the requirements for any portions of other volumes of the proposal.
4.1.2 Table of Contents
Include a master table of contents of the entire proposal.
4.2 Volume II - Technical Volume
4.2.1 General
The Technical Volume should be specific and complete, include only the requested narrative and proposed manning. DO NOT include price figures. All price information must be in the price proposal. Legibility, clarity, and coherence are very important. Your responses will be evaluated against the Technical subfactors defined in Section M, Evaluation Factors for Award. Using the instructions provided below, provide as specifically as possible the actual methodology you would use for accomplishing/satisfying these subfactors. All the requirements specified in the solicitation are mandatory. By your proposal submission, you are representing that your firm will perform all the requirements specified in the solicitation. It is not necessary or desirable for you to tell us so in your proposal. Do not merely reiterate the objectives or reformulate the requirements specified in the solicitation.
4.2.2 Technical
In the technical volume, address your technical solution for meeting the Government’s minimum performance or capability requirements of each technical subfactor.
4.2.2.1 Technical Risk
Address Technical Risk associated with those aspects of your proposed technical approach you consider to have the potential for disruption of schedule, increased costs, degradation of performance, the need for increased Government oversight, or the likelihood of unsuccessful contract performance. Classify each risk IAW DoD Source Selection Procedures Table 3, Technical Risk Rating. Provide the rationale for each risk and its rating, including quantitative estimates of the impact on cost, schedule, and performance. Describe the impact of each identified risk in terms of its potential to interfere with or prevent the successful accomplishment of other contract requirements (for example: PWS or specification requirements), whether or not those requirements are identified as subfactors. Propose a realistic "workaround" or risk mitigation for identified risks that will eliminate or reduce risk to an acceptable level. Identify and classify any new risks introduced by such risk mitigation.
4.2.3 Volume Organization
The Technical volume shall be organized according to the following general outline:
(1) Table of Contents
(2) List of Table and Drawings
(3) Glossary
(4) Cross Reference Matrix
(5) Subfactor One: Staffing Approach
(6) Subfactor Two: Recruitment, Training, and Retention
(7) Subfactor Three: Quality Plan
(8) Subfactor Four: Calibration Technical Orders Quality Plan
(9) Subfactor Five: Measurement Area Assurance (10)Technical Volume Attachments
- Transition Plan
- Draft Quality Plan
- Draft Technical Manual Production Plan
- Draft Measurement Area Capabilities Assessment
4.2.4 Subfactor One: Staffing Approach
The offeror shall provide a staffing approach to include the quantity of personnel, US Department of Labor labor category, and qualifications of personnel required in each area of the organizational structure, refer to Technical Exhibit 2A. For example, calibration technicians capable of performing at the Air Force’s highest echelon calibration laboratory, technical writers, schedulers, lab supervisors, quality assurance personnel, engineers, health physicist, etc.
4.2.5 Subfactor Two: Recruitment, Training, and Retention
The offeror shall provide their approach to recruit and retain a qualified workforce to meet competition/demand for on-site labor pool. The offeror shall address how newly hired employees will be trained and qualified to perform the work required. The offeror shall provide its approach for cross-training, advancement training, and continuing education of employees to ensure continuity of AFPSL operations.
4.2.6 Subfactor Three: Quality Plan
The offeror shall describe their approach to meet quality program requirements IAW PWS paragraph 1.4, and TO 00-20-14 Section 9 calibration laboratory quality standards.
4.2.7 Subfactor Four: Calibration Technical Orders Quality Plan The offeror shall describe their quality plan addressing technical order functions described in the PWS paragraph 5.2. The offeror shall describe their approach to develop and publish new, rewrite, and revision/change technical orders and distribution in the preliminary Technical Order Production Plan submitted.
4.2.8 Subfactor Five: Measurement Area Assurance
The offeror shall describe their approach to meeting Measurement Area Capability Document (MACD) requirements, PWS paragraph 5.1.8.8.1, to include approaches used to validate measurement uncertainty and ensure traceability; to record, maintain, and analyze historical data; provide statistical processes and analysis to validate measurement uncertainties; and processes to validate measurement uncertainties against other DoD services and industry.
4.2.9 Technical Volume Attachments
The transition plan will be addressed in the Technical volume, attachment section, along with the draft quality plan, draft technical manual production plan, and the draft measurement area capabilities document.
5 VOLUME III - PAST PERFORMANCE
5.1 Past Performance Information (PPI) Tool
Each offeror shall submit past performance via the Past Performance Information (PPI) Tool available on EZSource. Instructions for use of the PPI Tool are found in Attachment 2: Past Performance Information Tool Instructions.
5.2 Consent/Authorization Letters
Offerors shall submit a consent letter executed by each subcontractor, teaming partner, and/or joint venture partner, authorizing release of adverse past performance information to the offeror so the offeror can respond to such information. For each identified effort for a commercial customer, the offeror shall also submit a client authorization letter, authorizing release to the Government of requested information on the offeror's performance.
5.3 Early Proposal Information
Each offeror is requested to submit the past performance information using the PPI Tool for each relevant contract 10 calendar days prior to the date set for receipt of proposals. Failure to submit early proposal information will not result in offeror disqualification.
5.4 Recent and Relevant Contracts
Offeror shall submit past performance information on up to four (4) recent contracts that you consider most relevant in demonstrating your ability to perform the proposed effort. If the contract reference is from an IDIQ, each TO/DO counts as one contract reference. Offerors shall input all requested past performance data in the PPI Tool for each active or completed contract with at least one year of performance history in the past five (5) years, that the offeror considers relevant in demonstrating its ability to perform the proposed effort. Also include information on four (4) recent contracts performed by critical subcontractors that you consider most relevant in demonstrating their ability to perform the proposed effort. The Government considers a subcontractor to be “critical” if it will perform 10% or more of the work under the contract. For all submittals, the performance on efforts identified shall be restricted to those completed or ongoing during the past five (5) years from the issuance date of this RFP with at least one year of performance history. Include rationale supporting your assertion of relevance. For a description of the characteristics or aspects the Government will consider in determining recency and relevance, see Section M, paragraphs 2.3.2.1 and 2.3.2.2.
5.4.1 Specific Content
Offerors are required to explain what aspects of the contracts are deemed relevant to the proposed effort and to what aspects of the proposed effort they relate. This may include a discussion of efforts accomplished by the offeror to resolve problems encountered on prior contracts as well as past efforts to identify and manage program risk. Merely having problems does not automatically equate to an unacceptable/a limited or no confidence rating, since the problems encountered may have been on a more complex program, or an offeror may have subsequently demonstrated the ability to overcome the problems encountered. The offeror is required to clearly demonstrate management actions employed in overcoming problems and the effects of those actions in terms of improvements achieved or problems rectified. Categorize the relevant information into the specific Technical subfactors and Price factor used to evaluate the proposal.
5.4.2 Organizational Structure Change History
Many companies have acquired, been acquired by, or otherwise merged with other companies, and/or reorganized their divisions, business groups, subsidiary companies, etc. In many cases, these changes have taken place during the time of performance of relevant past efforts or between conclusion of recent past efforts and this source selection. As a result, it is sometimes difficult to determine what past performance is relevant to this acquisition. To facilitate this relevancy determination, include in this proposal volume a "roadmap" describing all such changes in the organization of your company. A pamphlet or other commercial document describing such reorganizations may suffice. As part of this explanation, show how these changes impact the relevance of any efforts you identify for past performance evaluation/performance confidence assessment. Since the Government intends to consider past performance information provided by other sources as well as that provided by the offeror(s), your "roadmap" should be both specifically applicable to the efforts you identify and general enough to apply to efforts on which the Government receives information from other sources.
6.0 VOLUME IV - PRICE
6.1 General Instructions
6.1.1 Price Reasonableness
This section is to assist you in submitting data other than certified pricing data that is required to evaluate the reasonableness and balance of your proposed price. Compliance with these requirements is mandatory and failure to comply may result in rejection of your proposal. Note that the Government will not conduct a price realism analysis but offerors should consult the Department of Labor wage determination and collective bargaining agreement attached in the solicitation. Additionally, unbalanced pricing poses an unacceptable risk to the Government and may be a reason to reject an offeror’s proposal. Offers should be sufficiently detailed to demonstrate their reasonableness and balance. The burden of proof for credibility of proposed prices rests with the offeror.
6.1.2 Banding
The CLIN structure in the solicitation provides banding on CLINs that are associated with a Firm Fixed Price w/Incentive. Offerors shall provide separate proposed prices on each band where designated in the solicitation. Offerors must provide pricing for all three bands in each FFP w/Incentive CLIN. For evaluation purposes and figuring Total Evaluated Price, the number for band 2 and the maximum possible incentive (8%) will be used as it covers the majority of the workload.
6.1.3 Price Data
Data beyond that required by this instruction shall not be submitted, unless you consider it essential to document or support your price position. All data relating to the proposed price, including all required supporting documentation, must be included in the section of the proposal designated as the Price volume. Data to includes CDRLs and DiDs are anticipated to be NSP, however, the labor hours to produce the data should be billed under the AFPSL Operations labor hour CLIN for each year. Under no circumstances shall this data and documentation be included elsewhere in the proposal.
6.1.4 Pricing Data Requirements
IAW FAR 15.403-1(b) and 15.403-3(a), data other than certified pricing data may be required to support a determination of price reasonableness. Data shall be provided IAW FAR 15.403-5. If, after receipt of proposals, the CO determines that there is insufficient data available to determine price reasonableness and none of the exceptions in FAR 15.403-1 apply, the offeror shall be required to submit additional pricing data, potentially to include certified cost or pricing data.
6.1.5 Rounding
All dollar amounts provided shall be rounded to the nearest dollar. All loaded labor rates shall be rounded to the nearest penny.
6.2 Volume Organization
The Price volume shall consist of the following sections:
SECTION 1 - Table of Contents; summary descriptions of estimating, purchasing, and accounting systems; changes to estimating, accounting practices, or Cost Accounting Standards (CAS) Disclosure Statement.
SECTION 2 - Pricing information and supporting data, to include estimating methodology.
SECTION 3 - Other information such as Government Furnished Property/Government Furnished Equipment (GFP/GFE), base support, long lead costs, termination costs, development/production schedule, inflation rate summary and explanation, and special tooling/test equipment. List each exception to the ground rules and assumptions provided in the solicitation and each qualification of the Price volume, if any. Provide complete rationale for any exceptions.
7.0 VOLUME V CONTRACT DOCUMENTATION
7.1 RFP/Representations and Certifications
The purpose of this volume is to provide information to the Government for preparing the contract document and supporting file. The offeror's proposal shall include a signed copy of the RFP, and Sections A through K. This includes:
7.1.1 Section A - Solicitation/Contract Form
Completion of block 15-16 and signature and date for block 17 of the SF 33. Signature by the offeror on the SF 33 constitutes an offer, which the Government may accept. The "original" copy should be clearly marked under separate cover and should be provided without any punched holes.
7.1.2 Section B - Supplies or Services and Prices
Completed pricing information in Section B of the model contract.
7.1.3 Section K - Representations, Certifications, and other Statements of Offerors Include completed representations, certifications, acknowledgments and statements.
7.2 Exceptions to Solicitation Requirements
Offerors are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or subfactors. Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. Each exception shall be specifically related to each paragraph and/or specific part of the solicitation to which the exception is taken. Provide rationale in support of the exception and fully explain its impact, if any, on the performance, schedule, price, and specific requirements of the solicitation. This information shall be provided in the format and content of Table 7.2.
Table 7.2 - Solicitation Exceptions
Solicitation Document Page/ Paragraph Requirement/ Portion Rationale
| SOO, SOW, PWS, SPEC, Model Contract, ITO, etc. |
| Applicable Page and Paragraph Numbers |
| Identify the requirement or portion to which exception is taken |
| Describe why the requirement can/will not be met |
7.3 Other Information Required
7.3.1 Authorized Offeror Personnel
Provide the name, title, and telephone number of the company/division point of contact regarding decisions made with respect to your proposal and who can obligate your company contractually. Also, identify those individuals authorized to negotiate with the Government. Also provide the name, title and telephone number of the CEO and Division President.
7.3.2 Government Offices
Provide the mailing address, telephone and fax numbers and facility codes for the cognizant Contract Administration Office, DCAA, and Government Paying Office.
7.3.3 Company/Division Address, Identifying Codes, and Applicable Designations Provide company/division's street address, county and facility code; CAGE code; DUNS code; TIN; size of business (large or small); and labor surplus area designation. This same information must be provided if the work for this contract will be performed at any other location(s). List all locations where work is to be performed and indicate whether such facility is a division, affiliate, or subcontractor, and the percentage of work to be performed at each location.
7.3.4 Attachments to the RFP
The offeror shall provide the following as attachments to the model contract:
7.3.4.1 Subcontracting Plan - Participation of Small Businesses (SB), Veteran-owned small business concerns (VOSB), Service disabled veteran-owned small business concerns (SDVOSB), HUBZone small business concerns, small disadvantaged business concerns (SDB), and women-owned small business concerns (WOSB). If the offeror is other than a small business, the offeror shall submit a Small Business Subcontracting Plan IAW FAR 52.219-9 that also identifies and specifies the extent of offeror's commitment to the participation of the small business concerns listed above, whether as joint venture members, teaming arrangement partners, or subcontractors. If applicable, submit a copy of your approved Master Plan. In the event the offeror has negotiated a comprehensive subcontracting plan pursuant to DFARS 219.702, the offeror must submit the information that identifies and specifies the extent of its commitment to the participation of SB, VOSB, SDVOSB, HUBZone, SDB, and WOSB.
7.3.4.2 Make-or-Buy
A make or buy program is not applicable to the proposed effort. The offerors will not be required to submit a make or buy plan because the proposed contract is a service contract for the operation of the AFPSL.
7.3.4.3 GFE
The Government plans to provide the items listed in Tech Exhibit 5b (GFE List) of the solicitation as GFE. If the offeror requires the use of Government furnished items other than those specified, the offeror shall provide a listing including quantity, federal stock number, nomenclature, date needed and duration of availability, rental value per FAR 45.1 and FAR 45.2, reason for need, and cross reference to cost/price volume paragraphs which pertain to GFP and/or base support. The offeror shall also provide the written authorization from the cognizant CO, as applicable. The offeror shall supply this information in the format shown in Table 7.3.4.3. The Government will eliminate any competitive advantage resulting from an offeror's proposed use of Government-furnished property (GFP) beyond what this solicitation offers.
Table 7.3.4.3 - Required Information for Using GFP/Base Support
| Quantity |
| Federal Stock # |
| Nomen-clature |
| Duration of Need |
| Rental Value |
| Reason |
for Need Cross Ref to Cost Prop
| 2 EA |
| FS156-09-234 |
| ACG-1372 Time Counter |
| 1 Oct 20 - 30 Dec 21 |
| $1,000 |
| Needed to calibrate our |
5 mhz/1pps SATCOM simulator offset Volume III-23-27
7.3.4.4 Associate Contractor Agreements
The offeror shall be required to enter into a lease agreement with the local Port Authority, as well as with the Inertial Guidance Contractor at the facility.
8.0 List of Attachments: Section L attachments listed below are provided as separate files.
Attachment 1: Cross Reference Matrix Attachment 2: Past Performance Information Tool Instructions