[E]_Watermain_Replacement_Technical_Specification_7-2-25.pdf

PDF 4 MB Posted

Attached to
Collins Street Complete Street - Phase I
Solicitation number
25-014EN-FC-IFB
Issued by
Hillsborough County, Florida

About this file

This document is a comprehensive technical specification for the Collins Street Potable Water Main Replacement project for the Utilities Department of Plant City, Florida. The specification details the technical requirements for installing new potable water mains along Collins Street, between Alabama Street and Laura Street, involving 10", 6", and 4" ductile iron pipes and high-density polyethylene (HDPE) pipe relocations. The project includes various associated infrastructure work such as connections to existing water mains, valve installations, fire hydrant assemblies, service connections, and full surface restoration. The technical specifications are prepared by Dewberry Engineers and represent a 100% design set dated June 2025, with comprehensive details across multiple technical divisions including general conditions, site construction, concrete, electrical, and mechanical/plumbing specifications.

The specification provides extensive technical details for bidders, including specific requirements for materials, installation methods, testing protocols, and quality control measures. The project involves careful coordination with a concurrent streetscape project and requires adherence to Florida Department of Transportation (FDOT) standards and Hillsborough County Health Department regulations. Contractors will be responsible for obtaining necessary permits, maintaining traffic control, managing erosion and sedimentation, and ensuring all water main installations meet stringent disinfection and testing requirements. The technical specifications outline precise measurement and payment procedures, with detailed bid items covering various aspects of the water main replacement, and emphasize the importance of manufacturer certifications, installation testing, and comprehensive documentation throughout the project lifecycle.

View the file

Other files

File Type Posted
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#6_Revision).pdf PDF
[Z]_Approved_Products_List-July2024.pdf PDF
[C]_General_Specifications_10-29-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[A]_Project_Specifications-Index_10-29-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#4_Revision).pdf PDF
Collins_Street_Complete_Street_-_Phase_I_(Addendum_#2_Revision).pdf PDF
2025-02-07_-_Collins_Street_Complete_Street_Improvements_-_Phase_1_Contract.pdf PDF
[O]_611_Collins_Street_Site_Exhibit_7-2-25.pdf PDF
[M]_Plans_1.28.22_-_Collins_St_Watermain_7-2-25.pdf PDF
[L]_2025.02.11_-_Collins_Street_Landscape_SS_7-2-25.pdf PDF
[K]_2025.02.10_Collins_Lighting_Phase1_Signed_7-2-25.pdf PDF
[J]_2025.02.10_Collins_Signals_S&S_7-2-25.pdf PDF
[I]_2025.02.10_Collins_SPM_Phase1_Signed_7-2-25.pdf PDF
[H]_2025.02.10_Collins_Rdwy_Phase1_Signed_7-2-25.pdf PDF
[G]_Project_Exhibits-Index_7-2-25.pdf PDF
[E]_Watermain_Replacement_Technical_Specification_7-2-25.pdf PDF
[D]_General_Requirements_7-2-25.pdf PDF
[C]_General_Specifications_7-2-25.pdf PDF
[B]_Scope_of_Work_7-2-25.pdf PDF
[A]_Project_Specifications-Index_7-2-25.pdf PDF
Outside_Consultant_List_REV12-20-24.pdf PDF
RW_Use_Permit_Application_Form.pdf PDF
CSX_RR_TROE_Locations.pdf PDF
UWS_Charter.pdf PDF
NOA_-_PWS_General_Permit.pdf PDF
UWS_Frontier.pdf PDF
H4185018_Collins_Street_Core_Report_S&S.pdf PDF
UWS-TECO.pdf PDF
H4185018_Collins_St_Mast_Arms_S&S.pdf PDF
Soil_&_Groundwater_Management_Plan.pdf PDF
ERP_Exemption.pdf PDF
Traffic_Cabinet_-_Special_Requirements.pdf PDF
Bid_Form_-_Watermain_Replacement.xlsx XLSX spreadsheet
Worksheet_for_Construction_Agreement_11-8-24.docx DOCX document
Bid_Form_-_Road_&_Drainage.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COLLINS STREET POTABLE WATER MAIN REPLACEMENT

UTILITIES DEPARTMENT

PLANT CITY, FL

TECHNICAL SPECIFICATIONS

BID SET

JUNE 2025

DEWBERRY ENGINEERS

800 NORTH MAGNOLIA AVE., SUITE 1000

ORLANDO, FL 32803

CERTIFICATE OF AUTHORIZATION NO. 8794

Prepared By:

(THIS PAGE INTENTIONALLY LEFT BLANK)

TOC-2

TABLE OF CONTENTS

ADDENDUM

NONE

DIVISION 01 – GENERAL CONDITIONS

SECTION NO. TITLE

01110 SUMMARY OF WORK

01140 WORK RESTRICTIONS

01150 MEASUREMENT AND PAYMENT

01312 PROJECT MEETINGS

01324 PROGRESS SCHEDULES AND REPORTS

01330 SUBMITTAL PROCEDURES

01340 PHOTOGRAPHIC AND VIDEOGRAPHIC DOCUMENTATION

01355B STORMWATER POLLUTION PREVENTION CONSTRUCTION ACTIVITY

01424 ABBREVIATIONS AND ACRONYMS

01450 QUALITY CONTROL

01500 TEMPORARY FACILITIES AND CONTROLS

01600 PRODUCT REQUIREMENTS

01756 COMMISSIONING

01757 DISINFECTION

01770 CLOSEOUT PROCEDURES

01782 OPERATION AND MAINTENANCE DATA

01783 WARRANTIES AND BONDS

DIVISION 02 - SITE CONSTRUCTION

SECTION NO. TITLE

02050 SOILS AND AGGREGATES FOR EARTHWORK

02224 PROTECTING EXISTING UNDERGROUND UTILITIES

02240 DEWATERING

02261 TEMPORARY EXCAVATION SUPPORT SYSTEMS

02282 CONNECTIONS TO EXISTING BURIED PIPELINES

02318 TRENCHING

02810 SODDING

DIVISION 03 – CONCRETE AND STRUCTURAL

03102 CONCRETE FORMWORK

03200 CONCRETE REINFORCING

03250 CONCRETE JOINTS AND JOINT ACCESSORIES

TOC-3

03300 CAST-IN-PLACE CONCRETE

DIVISION 04 – MASONRY

SECTION INTENTIONALLY NOT USED

DIVISION 05 – METALS

DIVISION 06 – WOODS AND PLASTICS

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

DIVISION 08 – DOORS AND WINDOWS

DIVISION 09 – FINISHES

09900 PAINTING AND COATING

DIVISION 10 – SPECIALTIES

DIVISION 11 – EQUIPMENT

DIVISION 12 – FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

DIVISION 14 – CONVEYING SYSTEMTS

DIVISION 15 – MECHANICAL / PLUMBING

TOC-4

15052 COMMON WORK RESULTS FOR GENERAL PIPING

15075 EQUIPMENT, PIPING, DUCT, VALVE IDENTIFICATION

15115 VALVES AND PIPING APPURTENANCES

15240 DUCTILE-IRON PIPE

15297 HIGH DENSITY POLYETHLEYNE PIPE (HDPE)

15956 PIPING SYSTEMS TESTING

DIVISION 16 – ELECTRICAL

APPENDICES

Appendix – A APPROVED PRODUCTS LIST: CITY OF PLANT CITY

TOC-5

(THIS PAGE INTENTIONALLY LEFT BLANK)

The following Sections of the Specifications issued for bidding the Plant City Collins Street Potable Water Main Replacement September 2021 were prepared under my direction and supervision.

Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.

CERTIFICATIONS BY PROJECT PROFESSIONALS

Project:

City of Plant City

Collins Street Potable Water Main Replacement

Responsible for Specification Sections:

Division – 01

Division – 02

Division – 03

Division – 09

Division – 15

91010

Signature Registration No.

6/24/2025

Date Seal

Colson Marsh., Florida P.E. No. 91010, Dewberry Engineers, 800 N. Magnolia Ave., Suite 1000, Orlando, FL 32803. Certificate of Authorization No. 8794 cmarsh Image

THIS PAGE LEFT BLANK INTENTIONALLY

100% Design 01110-1

SECTION 01110

SUMMARY OF WORK

PART 1 GENERAL

1.01 GOVERNING PROVISIONS

A. Contractor shall refer the technical specifications requirements. In the event of a conflict, the specifications shall prevail.

B. Contractor shall refer to the General Conditions for contract provisions. In the event the technical specifications and General Conditions conflict, the General Conditions shall prevail.

C. Contractor shall defer to the FDOT latest standards and specifications for roads, drainage, erosion control, sodding, and site restoration requirements.

1.02 SUMMARY

A. Work and Coordination Under this Contract:

1. Work included under this contract generally includes but is not limited to the following:

a. Construct a new potable water main of various size (10”, 6”, and 4”) within the asphalt limits of Collins Street, connecting to existing potable water main at the south end of the project limits. All associated piping, fittings, valves, hydrants, equipment, testing, cleaning, disinfection and other appurtenances complete as shown in the drawings and specified herein.

b. Reconnection to existing branch water mains, and all water services connections.

c. Two potable water main relocations of various size (14” and 2”) to avoid storm structures installed under separate cover south of Alabama Street.

d. Vertical and horizontal adjustment of services and branch water mains to avoid future construction not part of this contract.

e. Restoration of driveway, asphalt roads, sidewalk, landscape, and hardscape associated with pipeline construction.

f. Maintenance of traffic associated with pipeline construction.

g. All project permitting, site survey and clearing required.

h. In addition to the requirements for Substantial Completion contained in the

Contract and General Conditions, Contractor shall complete the commissioning and functionality testing requirements prior to achieving the Substantial Completion.

i. Develop close out documents and provide surveyed as-built drawings.

2. Work under this contract will precede or run concurrent to a Streetscape

Project that includes Stormwater, Landscape, Hardscape, and Roadway improvements. It is expected that detailed coordination between work performed under this Contract and work performed under separate contract will be administered by the Contractors. The potable water relocations under this Contract may require additional coordination with proposed stormwater improvements throughout the construction phase.

100% Design 01110-2

1.03 LOCATION OF PROJECT

A. The work for Collins Street Water Main Replacement is located along Collins St., between Alabama St. north to Approximately Laura St. in Plant City, Florida, 33566.

1.04 ACTIVITIES BY OTHERS

A. Coordination:

1. Other phases of construction may begin before this contract is completed which will interface with this work. Additionally, other projects will be constructed adjacent to the Work during the life of this contract. Coordinate your activities with the other Contractors and/or City Personnel to allow orderly and timely completion of all the work.

2. When access through interfacing and/or overlapping construction areas must be disrupted, provide alternate acceptable access for other contractors.

Coordinate your activities in the interface or common areas with these other contractors. Submit to the Engineer a description and schedule as to how the common areas will be utilized, recognizing the required coordination with other contractors.

B. Utilities:

1. Coordinate the activities of all utility companies with equipment in the construction area with the Contractor's and subcontractors' work.

C. Cutting and Patching:

1. No cutting and patching of new work will be accepted. All work must be new and continuous in its final form.

1.05 SUBCONTRACTORS

A. Contractor shall not employ any subcontractors against who the City or the Engineer may have reasonable objection. The name, address, and experience of the proposed subcontractors shall be submitted at the time of the Bid as part of the Contractors Bid.

1.06 WORKING HOURS

A. Refer to the City Supplementary Conditions.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

END OF SECTION

100% DESIGN 01140-1

SECTION 01140

WORK RESTRICTIONS

1.01 SUMMARY

A. Section includes: Requirements for sequencing and scheduling the Work affected by existing site and facility, work restrictions, and coordination between construction operations and Owner operations.

1.02 GENERAL CONSTRAINTS ON SEQUENCE AND SCHEDULING OF WORK

A. Sequence of Work

1. The potable water relocation project will precede or be concurrent with a Street

Scape Project (Under Separate Contract) the includes landscape, hardscape, stormwater imporovements, and roadway restoration. It is expected the Contractor of this potabale water relocation project will coordinate with other Contractors including utility placement, work zones, and public safety.

2. The existing facilities are active and provide potable water to local and adjacent customers.

3. Work shall be conducted as to not impair the Owner's ability to maintain permitted operational capacity. Do not impair the operational capabilities of the existing potable water mians, or operations of local customers.

1.03 SHUTDOWN, WET TAP, AND CONSTRUCTION CONSTRAINTS

A. General shutdown constraints: No shutdowns shall be allowed unless approved by the Owner.

B. Owner approved shutdown constraints:

1. Organize work in order to minimize the potential number of shutdowns.

2. Provide thorough advanced planning, including having required equipment, materials, and labor on hand at time of shutdown.

3. Where required to minimize facility operations interruptions while complying with specified sequencing constraints, provide temporary pumping, power, lighting, controls, instrumentation, and safety devices.

4. Coordinate all shutdown activities with the Owner and Engineer in writing a minimum of 14 calendar days prior to the event execution.

5. Final determination of the permitting of shutdowns will be the sole judgment of the Owner. Owner maintains the ability to abort on the day of the scheduled shutdown.

6. Include necessary constraints and identify anticipated shutdown events within the construction schedule

7. Unplanned shutdowns due to emergencies are not defined in this Section.

C. Unit process availability work limitations:

1. Tie-ins to the existing potable water lines shall occur as part of the project construction. No shutdowns shall be allowed unless approved by the Ower

100% DESIGN 01140-2

D. General Wet Tapping Constraints

1. Organize work in order to minimize the potential number of wet taps.

2. Provide thorough advanced planning, including having required equipment, materials, and labor on hand at time of wet tapping.

3. Where required to minimize operations interruptions while complying with specified sequencing constraints, provide temporary pumping, power, lighting, controls, instrumentation, and safety devices.

4. Coordinate all wet tapping activities with the Owner and Engineer in writing a minimum of 5 business days prior to the event execution.

5. Final determination of the permitting of wet tapping will be the sole judgment of the Owner. Owner maintains the ability to abort on the day of the scheduled wet tap.

6. Include necessary constraints and identify anticipated wet tap events within the construction schedule.

1.04 COMPLIANCE WITH DRINKING WATER PERMIT

A. The existing and proposed facilities shall maintain and meet Hillsborough County Health Department regulations, new facilities must pass sampling requirements set forth by the Health Department.

B. Bear the cost of penalties imposed on the Owner for water quality violations caused by actions of the Contractor.

1.05 ANTICIPATED REQUIRED PERMITS

A. It is expected the following permits will be required by the CONTRACTOR to obtain prior to work taking place. It shall be the responsibility of the CONTRACTOR to obtain all local, state and jurisdicaitonal permits required to perform the construction activities as described in the Contract Documents.

1. Local Right-of-Way permit.

2. Temporary Traffice Control Permit.

B. The following permits have been completed and approved by the Engineer and will be provided to the Contractor prior to consturciton.

1. Hillsborough County Department of Health

a. Notice of Acceptance; General Use Permit

1.06 OPERATIONS AND MAINTENANCE ACCESS

A. Provide safe, continuous access to City personnel.

1.07 UTILITIES

A. Provide advance notice to and utilize services of Sunshine State One Call system for location and marking of underground utilities operated by utility agencies other than the Owner.

B. Maintain electrical, telephone, water, gas, sanitary facilities, and other utilities within existing facilities in service. Provide temporary utilities when necessary.

C. Proposed utilities within the Right-of-Way were designed using existing facility drawings.

100% DESIGN 01140-3

1. Field verification of utilities locations was not performed during design.

2. Services crossed or located nearby proposed potable water main may require relocation and possible shutdowns.

3. Pipe alignments as indicated on the Drawings.

1.08 WORK SEQUENCE

A. Provide a detailed outline of work sequence to Engineer and Owner to review and approval/acceptance before the start of work. The following are items to consider for the work sequence to accomplish the proposed improvements.

1. Staging Area

2. Immediate Construction Site, equipment and materials shall remain secure at all times during the duration of the project.

3. Site access.

4. Provide final site clean up and restoration to pre-construction condition.

PART 2 PRODUCTS

Not Used.

100% DESIGN 01140-4

100% DESIGN 01150-1

SECTION 01150

MEASUREMENT AND PAYMENT

1.01 SUMMARY

A. Section includes: Procedures for measurement and payment of Work performed on a unit price basis as outlined on the Bid Form.

B. Separate payment will be made only for the items of work described herein and listed on the Bid Form. Any related work not specifically listed, but required for satisfactory completion of the work, shall be considered to be included in the scope of the appropriate listed work items.

C. Unless specifically called out as a separate Pay Item, no separate payment will be made for the following items and the cost of such work shall be included in the applicable Pay Items or work:

1. Clearing and grubbing

2. Excavation, including necessary surface improvements removal

3. Sheeting, shoring and/or dewatering

4. Backfill materials, except as specified hereinafter

5. Grading

6. Clean-up and restoration

7. Refill materials except as specified hereinafter

8. Testing and placing system in operation

9. Protection, repair, and replacement of existing utilities facilities not shown on the plans to be relocated

D. Related sections:

1. The Contract Documents are complementary; what is called for by one is as binding as if called for by all.

2. It is the Contractor’s responsibility for scheduling and coordinating the Work of subcontractors, suppliers, and other individuals or entities performing or furnishing any of Contractor’s Work.

3. The following Sections are related to the Work described in this Section. This list of Related Sections is provided for convenience only and is not intended to excuse or otherwise diminish the duty of the Contractor to see that the completed Work complies accurately with the Contract Documents.

a. Bid Form

b. Plant City Standards

1.02 ESTIMATED QUANTITIES

A. All estimated quantities stipulated in the Bid Form or other Contract Documents are approximate and are to be used only (a) as a basis for estimating the probable cost of the Work and (b) for the purpose of comparing the bids submitted for the Work.

The actual amounts of work done and materials furnished under unit price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and materials furnished.

100% DESIGN 01150-2

Contractor agrees that he will make no claim for damages, anticipated profits, or otherwise on account of any difference between the amounts of work actually performed and materials actually furnished and the estimated amounts thereof, as described in the supplementary conditions.

1.03 TAXES AND PERMITS

A. The Bidder’s attention is directed to the fact that the tax laws of the State of Florida, including but not limited to Chapter 212, Florida Statutes, apply to this bid matter and that all applicable taxes and fees shall be deemed to have been included in Bidder’s proposal.

1.04 MEASUREMENT OF QUANTITIES

A. Measurement of lump sum items shall be based on the percent of actual completion as determined by the Contractor and agreed upon by the Engineer.

B. Where applicable, work paid at a unit price times number of units measured will be measured by Engineer/Owner in accordance with United States Standard Measures.

C. Measurement of volumes shall be the actual "as-built" volume pertinent to payment items.

D. Payment will start only after material is delivered to the project site and verified by the Construction Manager.

1.05 PAY ITEMS

A. General:

1. The pay items are included in Bid Form.

2. Payment procedures as specified in the Plant City General Conditions.

3. All pay items are included in bid section “Watermain Replacement” unless noted otherwise.

B. Mobilization and Demobilization (Included in Bid Line 1 of Road and Drainage Bid)

1. Description: The work specified in this item consist of the preparatory work and operations in mobilizing for beginning and ending work on the Project, including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies, and incidentals to and from the project site, and for the establishment of temporary offices, buildings, safety equipment, project sign, and first aid supplies, sanitary and other facilities as required by these Specifications, the submittal of all required insurance certificates and bonds, posting of all OSHA required notices and establishment of safety programs at the jobsite, any additional requirements of the Supplementary Conditions, and state and local laws and regulations. The costs of any other preconstruction expense necessary for the start of the work, excluding the cost of construction materials, shall be included in this item. This Bid Item will include mobilization and demobilization for all parts of phases of the total project.

C. Maintenance of Traffic (Included in Bid Line 2 of Road and Drainage Bid)

1. Description: Work shall include furnishing all labor, materials and equipment required to implement the MOT plan and to cover the required work from

100% DESIGN 01150-3

commencement to final closeout. The work includes all items of work necessary for complete maintenance of traffic including, but not limited to, traffic control devices, warning devices, safety devices, barricading, signing, lighting, removal of existing pavement markings, installation and removal of temporary pavement striping (paint), markings and reflective markers, traffic signal relocation and adjustments for MOT phasing, and all materials and construction necessary to create temporary connections for street, driveways and pedestrian traffic. The pay item for “Maintenance of Traffic” shall include all work necessary for maintenance of vehicular traffic and pedestrian traffic, unless otherwise specified to be paid under other bid items.

D. Erosion and Sedimentation Control (Included in Bid Line 3 of Road and Drainage Bid)

1. Description: The work consists of all labor, equipment, material, installation, maintenance, replacement and removal of approved erosion control devices from commencement to final acceptance. The pay item for Erosion Control (Lump Sum) shall include all erosion control devices necessary to control erosion on the project unless otherwise specified to be paid for under other items of work.

E. BID ITEM NO. 1 – 10” Ductile-Iron Pipe(DIP) (Open-Cut)

1. Description: The work consists of furnishing all labor, equipment and materials and installing DIP pipe by open cut. The unit price shall include all costs necessary to install the pipe including survey layout; materials; clearing and grubbing; tree removal; root pruning; asphalt cutting, removal, hauling;

excavation; backfilling; dewatering; sheeting; bracing; temporary fencing;

utility crossings; identification and locating appurtenances; electronic marker balls; clearing of the right-of-way; protection of property; protection, repair and replacement of utilities; protection, repair and replacement of sprinklers;

temporary leakage test plugs; temporary blow-offs; backfill; pressure testing, and disinfection. Fittings and Surface restoration shall be paid for under separate Bid Items.

2. Measurement: The quantities of pipe to be paid for under this Item shall be the horizontal length in linear feet of pipe measured along the centerline of the pipe through valves and fittings in place, completed and accepted. Whether a particular pay item is for restrained joint pipe or unrestrained joint pipe is indicated in the proposal.

3. Payment: Payment will be made at the unit price bid per linear foot of the various pipe sizes for restrained or unrestrained joint pipe.

F. BID ITEM NO. 2 – 6” Ductile-Iron Pipe(DIP) (Open-Cut)

1. Description: The work consists of furnishing all labor, equipment and materials and installing DIP pipe by open cut. The unit price shall include all costs necessary to install the pipe including survey layout; materials; clearing and grubbing; tree removal; root pruning; asphalt cutting, removal, hauling;

excavation; backfilling; dewatering; sheeting; bracing; temporary fencing;

utility crossings; identification and locating appurtenances; electronic marker balls; clearing of the right-of-way; protection of property; protection, repair and replacement of utilities; protection, repair and replacement of sprinklers;

temporary leakage test plugs; temporary blow-offs; backfill; pressure testing, and disinfection. Fittings and Surface restoration shall be paid for under separate Bid Items.

100% DESIGN 01150-4

2. Measurement: The quantities of pipe to be paid for under this Item shall be the horizontal length in linear feet of pipe measured along the centerline of the pipe through valves and fittings in place, completed and accepted. Whether a particular pay item is for restrained joint pipe or unrestrained joint pipe is indicated in the proposal.

3. Payment: Payment will be made at the unit price bid per linear foot of the various pipe sizes for restrained or unrestrained joint pipe.

G. BID ITEM NO. 3 – 4” Ductile-Iron Pipe(DIP) (Open-Cut)

1. Description: The work consists of furnishing all labor, equipment and materials and installing DIP pipe by open cut. The unit price shall include all costs necessary to install the pipe including survey layout; materials; clearing and grubbing; tree removal; root pruning; asphalt cutting, removal, hauling;

excavation; backfilling; dewatering; sheeting; bracing; temporary fencing;

utility crossings; identification and locating appurtenances; electronic marker balls; clearing of the right-of-way; protection of property; protection, repair and replacement of utilities; protection, repair and replacement of sprinklers;

temporary leakage test plugs; temporary blow-offs; backfill; pressure testing, and disinfection. Fittings and Surface restoration shall be paid for under separate Bid Items.

2. Measurement: The quantities of pipe to be paid for under this Item shall be the horizontal length in linear feet of pipe measured along the centerline of the pipe through valves and fittings in place, completed and accepted. Whether a particular pay item is for restrained joint pipe or unrestrained joint pipe is indicated in the proposal.

3. Payment: Payment will be made at the unit price bid per linear foot of the various pipe sizes for restrained or unrestrained joint pipe.

H. BID ITEM NO. 4 – 14” High Density Polyethylene (HDPE) Relocation (Open-Cut)

1. Description: The work consists of furnishing all labor, equipment and materials and installing HDPE pipe, fittings, transition couplings, restraining of existing watermains by open cut. The unit price shall include all costs necessary to install the pipe segments, fittings and required transition couplings, including survey layout; materials; clearing and grubbing; tree removal; root pruning;

asphalt cutting, removal, hauling; excavation; backfilling; dewatering;

sheeting; bracing; temporary fencing; utility crossings; identification and locating appurtenances; electronic marker balls; clearing of the right-of-way;

protection of property; protection, repair and replacement of utilities;

protection, repair and replacement of sprinklers; temporary leakage test plugs;

temporary blow-offs; backfill; pressure testing, and disinfection. Surface restoration shall be paid for under separate Bid Items.

2. Measurement: The quantities of 14” HDPE pipe to be paid for under this Item shall be the horizontal length in linear feet of pipe measured along the centerline of the pipe through valves and fittings in place, completed and accepted. Whether a particular pay item is for restrained joint pipe or unrestrained joint pipe is indicated in the proposal.

3. Payment: Payment will be made at the unit price bid per linear foot of the pipe installed.

I. BID ITEM NO. 5 – 2” High Density Polyethylene (HDPE) Relocation (Open-Cut)

1. Description: The work consists of furnishing all labor, equipment and materials and installing HDPE pipe, fittings, transition couplings, restraining of existing

100% DESIGN 01150-5

watermains by open cut. The unit price shall include all costs necessary to install the pipe segments, fittings and required transition couplings, including survey layout; materials; clearing and grubbing; tree removal; root pruning;

asphalt cutting, removal, hauling; excavation; backfilling; dewatering;

sheeting; bracing; temporary fencing; utility crossings; identification and locating appurtenances; electronic marker balls; clearing of the right-of-way;

protection of property; protection, repair and replacement of utilities;

protection, repair and replacement of sprinklers; temporary leakage test plugs;

temporary blow-offs; pressure testing, and disinfection. Surface restoration shall be paid for under separate Bid Items.

2. Measurement: The quantities of 2” HDPE pipe to be paid for under this Item shall be the horizontal length in linear feet of pipe measured along the centerline of the pipe through valves and fittings in place, completed and accepted. Whether a particular pay item is for restrained joint pipe or unrestrained joint pipe is indicated in the proposal.

3. Payment: Payment will be made at the unit price bid per linear foot of the pipe installed.

J. BID ITEM NO. 6 through 15 – Fittings

1. Description: Furnishing all labor, equipment and materials and installing ductile iron fittings and not included in other items. The unit price shall cover the cost of furnishing the fittings, bends and sleeves, cement lining, transportation, jointing materials, glands, bolts, and gaskets. All fittings shall be installed with restrainers.

2. Measurement: The quantities of fittings to be paid for under these Items shall be the number of each measured in place, completed and accepted

3. Payment: Payment will be made at the unit price bid for each type fitting of the various sizes.

K. BID ITEM NO. 16 – Connection to Existing 10-inch Gate Valve

1. Description: The work consists of furnishing all labor, equipment and materials, including excavation, hardware, dewatering, water evacuation, plug, valve box, polywrap, shoring if required, dewatering and performing connection to existing valve. A pressure test of the completed installations is required.

2. Measurement: The quantities of connections to be paid for under this Item shall be the actual number of each size measured in place, completed and accepted.

3. Payment: Payment will be made at the unit price bid for each size of tap listed in the Bid Form.

L. BID ITEM NO. 17 – 10”x12” Tapping Sleeve and Valve

1. Description: The work consists of furnishing all labor, equipment and materials, including tapping sleeve, tapping valve, valve box, polywrap, shoring if required, dewatering and performing taps on existing PVC, C.I. and D.I. mains.

A pressure test of the completed installations is required.

2. Measurement: The quantities of taps to be paid for under this Item shall be the actual number of each size measured in place, completed and accepted.

3. Payment: Payment will be made at the unit price bid for each size of tap listed in the Bid Form.

M. BID ITEM NO. 18 – 6” Cut-In Tee and Sleeve

100% DESIGN 01150-6

1. Description: The work consists of furnishing all labor, equipment and materials, including sleeve, valve, valve box, polywrap, shoring if required, dewatering and performing cut-in tee, sleeve and plug on existing PVC, C.I. and D.I.

mains. A pressure test of the completed installations is required.

2. Measurement: The quantities of taps to be paid for under this Item shall be the actual number of each size measured in place, completed and accepted.

3. Payment: Payment will be made at the unit price bid for each size of tap listed in the Bid Form.

N. BID ITEM NO. 19, 20, and 21 – Service Saddles Connections

1. Description: The Contractor shall provide all labor, equipment and material to connect newly installed mains and service saddles to existing. These connections shall include, but is not limited to: All necessary excavations;

maintaining the excavation, which shall include dewatering, bracing, and sheeting where required; making all necessary taps, which are required to affect and construct the tie-in connection; furnishing and installing all valves and valve box, curb and corporation stops; and, backfilling, compacting, regrading, and restoration.

2. Measurement: The quantities of service saddle connections to be paid for under this Item shall be the actual number of each size, completed and accepted. Bid Item shall be broken down by size.

3. Payment shall be made for each service saddle connection furnished and installed into the piping system complete and working to the satisfaction of the Owner.

O. BID ITEM NO. 22 – Fire Hydrant Assembly

1. Description: The Contractor shall provide all labor, equipment, and materials to completely install fire hydrant assemblies with gate valves and valve boxes, including all accessories and incidentals. The fire hydrant assembly installation shall include, but not be limited to:

a. Excavating the trench;

b. Maintaining the excavation, which shall include dewatering, bracing, and sheeting where required;

c. Pouring the concrete support pad for the fire hydrant;

d. Installing a fire hydrant assembly and gate valve with valve box;

e. Setting the fire hydrant and valve box flush to proposed grade or as directed by the Owner; and,

f. Backfilling and compacting the trench.

2. Measurement: The quantities of fire hydrants to be paid for under this Item shall be the actual number of each, completed and accepted. Bid Item shall be shown as each.

3. Payment shall be made for each fire hydrant assembly and valve and valve box installed and incorporated into the piping system complete and working to the satisfaction of the Owner.

P. BID ITEM NO. 23, 24, and 25 - Valves

1. Description: The Contractor shall provide all labor, equipment, and materials to completely install gate valves and valve boxes, including all accessories and incidentals. This bid item does not cover valves that are installed as part of a tapped connection to an existing or new main. The valve installation shall include, but is not limited to:

a. Excavating the trench;

100% DESIGN 01150-7

b. Maintaining the excavation, which shall include dewatering, bracing, and sheeting where required;

c. Installing the valve;

d. Setting the valve box flush to proposed grade or as directed by the

Owner; and,

e. Backfilling and compacting the trench.

2. Measurement: The quantities of valves to be paid for under this Item shall be the actual number of each size, completed and accepted. Bid Item shall be shown as each.

3. Payment: Payment shall be made for each valve and valve box installed and incorporated into the piping system complete and working to the satisfaction of the Owner.

Q. BID ITEM NO. 26 – Air Release Valve (ARV) Assembly

1. Description: The Contractor shall provide all labor, equipment, and materials to completely install ARV’s, valve boxes, piping isolation valves, gravel, concrete, fittings, including all accessories and incidentals for a complete assembly. The ARV installation shall include, but is not limited to:

a. Excavating the trench;

b. Maintaining the excavation, which shall include dewatering, bracing, and sheeting where required;

c. Installing the air release valve, piping, appurtenances;

d. Setting the valve box flush to proposed grade or as directed by the

Owner; and,

e. Backfilling and compacting the trench.

2. Measurement: The quantities of ARV’s to be paid for under this Item shall be the actual number of each size, completed and accepted. Bid Item shall be shown as each.

3. Payment: Payment shall be made for each ARV assembly installed and incorporated into the piping system complete and working to the satisfaction of the Owner

R. Surface Restoration for water main utility shall be included in the Road and Drainage bid.

1. Final restoration items include but are not limited to asphalt pavement, concrete drives, sidewalks, landscaping, irrigation, seeding, sodding, road base and sub-base materials, etc., that are included in the road and drainage project.

PART 2 PRODUCTS

Not used.

Not used.

100% DESIGN 01150-8

100% DESIGN 01312-1

SECTION 01312

PROJECT MEETINGS

1.01 SUMMARY

A. Section includes: Requirements for conducting conferences and meetings for the purposes of addressing issues related to the Work, reviewing and coordinating progress of the Work and other matters of common interest, and includes the following:

1. Qualifications of Meeting Participants.

2. Preconstruction Conference.

3. Progress Meetings.

4. Pre-Installation Meetings.

5. Schedule Update Meetings.

6. Quality Control Meetings.

7. Pre-Shutdown Meetings.

8. Pre-Process Start-up Meetings.

9. Electrical and Instrumentation Coordination Meetings.

10. Close-out meeting.

11. Post Construction Meeting.

1.02 QUALIFICATIONS OF MEETING PARTICIPANTS

A. Representatives of entities participating in meetings shall be qualified and authorized to act on behalf of entity each represents.

1.03 PRECONSTRUCTION CONFERENCE

A. Upon issuance of Notice to Proceed, or earlier when mutually agreeable, Owner and Engineer will arrange preconstruction conference at the Owner's facility in Plant City, FL. address and location to be determined.

B. Preconstruction Conference invitees: Contractor's project manager and superintendent, Owner, Engineer, representatives of utilities, major subcontractors and others involved in performance of the Work, and others necessary to agenda.

C. Contractor will preside at conference.

D. Purpose of conference: To establish working understanding between parties and to discuss Construction Schedule, shop drawing and other submittals, cost breakdown of major lump sum items, processing of submittals and applications for payment, and other subjects pertinent to execution of the Work.

E. Agenda will include:

1. Adequacy of distribution of Contract Documents.

2. Distribution and discussion of list of major subcontractors and suppliers.

3. Proposed progress schedules and critical construction sequencing.

4. Major equipment deliveries and priorities.

100% DESIGN 01312-2

5. Project coordination.

6. Designation of responsible personnel.

7. Procedures and processing of:

a. Field decisions.

b. Proposal requests.

c. Submittals.

d. Change Orders.

e. Request for Information/Interpretations.

f. Applications for Payment.

g. Record Documents.

8. Use of premises:

a. Office, construction, and storage areas.

b. Owner's requirements.

9. Construction facilities, controls, and construction aids.

10. Temporary utilities.

11. Safety and first aid procedures.

12. Security procedures.

13. Housekeeping procedures.

F. Contractor will provide a summary of meeting and distribute electronic copies of minutes within 3 business days of meeting to participants and interested parties.

1.04 PROGRESS MEETINGS

A. Monthly meetings scheduled on days as mutually agreed upon in the preconstruction conference held at Plant City, FL. address and location to be determined.

B. Contractor will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance required: Owner, Engineer, Contractor, Contractor’s Project Manager, superintendent, quality control manager, project scheduler, major subcontractors and suppliers as appropriate to agenda topics for each meeting.

D. Additional invitees: Owner utility companies when the Work affects their interests, and others necessary to agenda.

E. Agenda:

1. Review minutes of previous meeting/minutes.

2. Safety and security.

3. Construction schedule summary.

4. Review of 6 weeks schedule.

5. Review of off-site fabrication and delivery schedules.

6. Review of submittals schedule and status of submittals.

7. Request for information (RFI’s) status.

8. Shutdown coordination.

9. Change order management status.

10. Maintenance of quality standards (QA/QC).

11. Field observations, problems, and conflicts.

12. Commissioning and process start-up.

13. Partnering recognition status (optional).

14. General Items.

100% DESIGN 01312-3

15. Action items.

16. Next meeting.

F. Contractor will provide a summary and distribute electronically within 5 calendar days after meeting to participants, with copies to Contractor, Owner, and those affected by decisions made.

1.05 PRE-INSTALLATION MEETINGS

A. When required in individual specification sections or requested by Engineer, convene pre-installation meeting at Project site before commencing work of specific section.

B. Require attendance of parties directly affecting, or affected by, Work of specific section.

C. Notify Owner and Engineer 7 calendar days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of installation, preparation and installation procedures.

2. Review coordination with related work.

E. Contractor will record minutes and distribute electronic copies within 7 calendar days after meeting to participants, with copies to Engineer, Owner, and those affected by decisions made.

1.06 QUALITY CONTROL MEETINGS

A. Contractor will schedule and administer meetings throughout progress of the Work at maximum weekly intervals.

B. Contractor will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Construction Engineer and staff, Contractor’s Quality Control Manager and staff.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress and schedule.

3. Review of out-of-compliance inspection or test results.

4. Field observations, problems, and decisions.

5. Review of offsite fabrication and delivery schedules.

6. Planned progress during succeeding work period.

7. Coordination of required inspections and tests.

8. Review 6-week schedule report with upcoming inspections and special tests.

9. Maintenance of quality and work standards.

10. Other business relating to Work.

E. Contractor will record minutes and distribute electronic copies within 5 calendar days after meeting to participants, and those affected by decisions made.

100% DESIGN 01312-4

1.07 PRE-SHUTDOWN MEETINGS

A. Shutdowns and other tie-ins require a pre-shutdown meeting at Project site prior to commencing shutdown for tie-in or modification of specific facility systems.

B. Require attendance of parties directly affecting, or affected by shutdown, including Engineer, specific work crews, Owner’s construction, operations, and maintenance staff.

C. Notify Owner and Engineer 5 calendar days in advance of meeting date in writing.

D. Prepare agenda and preside at meeting:

1. Review accepted Method of Procedure (MOP) including conditions of shutdown, preparation, and installation procedures.

2. Review timelines and sequences.

3. Review responsibilities.

4. Review dry run plan and schedule, as necessary.

5. Review coordination with related work.

E. Contractor will record minutes and distribute copies within 5 calendar days after meeting and prior to scheduled shutdown to participants, with copies to Engineer, Owner, and those affected by decisions made.

1.08 PRE-PROCESS START-UP MEETINGS

A. Processes and equipment that requires testing and process start-up also requires a pre-startup meeting at Project site before commencing process start-up of specific systems.

B. Require attendance of parties directly affecting, or affected by process start-up and testing, including Engineer, specific work crews, Owner’s construction operations, and maintenance staff.

C. Notify Owner and Engineer 5 calendar days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review accepted MOP including conditions of process start-up and testing, preparation, and installation procedures.

2. Review timelines and sequences.

3. Review responsibilities.

4. Review dry run plan and schedule, as necessary.

5. Review coordination with related work.

E. Contractor will record minutes and distribute electronic copies within 5 calendar days after meeting and prior to scheduled process start-up to participants, with copies to Engineer, Owner, and those affected by decisions made.

1.09 CLOSE-OUT MEETING

A. Contractor will schedule close-out meeting.

B. Contractor will make arrangements for meeting, prepare agenda with copies for participants, and preside at meeting.

100% DESIGN 01312-5

C. Attendance required: Owner, Engineer, Contractor, Contractor’s Project Manager, and Superintendent.

D. Agenda:

1. Review deficiency list completion.

2. Transfer of record documents.

3. Finalize payment.

E. Contractor will record minutes and within 5 business days after meeting distribute electronic copies to participants.

PART 2 PRODUCTS

Not Used.

100% DESIGN 01312-6

100% DESIGN 01324-1

SECTION 01324

PROGRESS SCHEDULES AND REPORTS

1.01 SUMMARY

A. Section includes: Preparation, submittal, and maintenance of computerized progress schedule and reports, Contract time adjustments, and payment requests, including the following:

1. Preliminary Schedule.

2. Baseline Schedule.

3. Monthly Schedule Updates.

4. Schedule of Submittals.

5. Commissioning and Process Start-up Schedule.

6. As-built Schedule.

B. Refer to General Conditions for additional scheduling requirements, where a conflict between the General Conditions and these specifications, the General Conditions will prevail.

1.02 SCHEDULER

A. Designate, in writing and within 5 calendar days after Notice of Award, person responsible for preparation, maintenance, updating, and revision of all schedules.

B. Qualifications of scheduler:

1. Authority to act on behalf of Contractor.

2. 5 years verifiable experience in preparation of complex construction schedules for projects of similar value, size, and complexity.

3. Knowledge of critical path method (CPM) scheduling utilizing Primavera

Project Planner or SureTrak or Microsoft Project software.

1.03 SCHEDULING FORMAT

A. Schedule format: Utilize CPM format.

B. Prepare computerized schedule utilizing Primavera P6 Professional or Microsoft Project, most current version.

1. At the request of the City or Engineer submit an electronic version of the schedule in the original format.

2. Provide submittal copies for review in hardcopy or electronic Adobe (pdf) format.

1.04 SCHEDULE PREPARATION

A. Preparation and submittal of Progress Schedule represents Contractor's intention to execute the Work within specified time and constraints. Failure to conform to requirement may result in termination for cause as specified in the General Conditions.

100% DESIGN 01324-2

B. Contractor's bid covers all costs associated with the execution of the Work in accordance with the Progress Schedule.

C. During preparation of the preliminary Progress Schedule, Engineer will facilitate Contractor's efforts by being available to answer questions regarding sequencing issues, scheduling constraints, interface points, and dependency relationships.

D. Prepare schedule utilizing Precedence Diagramming Method (PDM).

E. Prepare schedule utilizing activity durations in terms of working days. Do not exceed 15 working day duration on activities except concrete curing, submittal review, and equipment fabrication and deliveries. Where duration of continuous work exceeds 15 working days, subdivide activities by location, stationing, or other sub-element of the Work. Coordinate holidays to be observed with the Owner and incorporate them into the schedule as non-working days.

F. Failure to include an activity required for execution of the Work does not excuse Contractor from completing the Work and portions thereof within specified times and at price specified in Contract. Contract requirements are not waived by failure of Contractor to include required schedule constraints, sequences, or milestones in schedule. Contract requirements are not waived by Owner’s acceptance of the schedule. In event of conflict between accepted schedule and Contract requirements, terms of Contract govern at all times, unless requirements are waived in writing by the Owner.

G. Reference schedule to working days with beginning of Contract Time as Day "1."

H. Contract float is for the mutual benefit of both Owner and Contractor. Changes to the project that can be accomplished within this available period of float may be made by Owner without extending the Contract time, by utilizing float. Time extensions will not be granted nor delay damages owed until Work extends beyond currently accepted Contract completion date. Likewise, Contractor may utilize float to offset delays other than delays caused by Owner. Mutual use of float can continue until all available float shown by schedule has been utilized by either Owner or Contractor, or both. At that time, extensions of the Contract time will be granted by Owner for valid Owner-caused or third party-caused delays which affect the planned completion date and which have been properly documented and demonstrated by Contractor.

I. Non-sequestering of float: Pursuant to float sharing requirements of Contract, schedule submittals can be rejected for use of float suppression techniques such as preferential sequencing or logic, special lead or lag logic restraints, extended activity durations or imposed dates.

J. Interim milestone dates, operational constraints. In event there are interim milestone dates and/or operational constraints set forth in Contract, show them on schedule.

Do not use Zero Total Float constraint or Mandatory Finish Date on such Contract requirements.

K. Schedule windows for Contractor-installed equipment or materials: Immediately after Award of Contract.

100% DESIGN 01324-3

1.05 SUBMITTAL OF PROGRESS SCHEDULES

A. Submit preliminary and baseline schedule.

B. Submit, on a monthly basis, updated schedules and pay applications as specified.

C. Submit final schedule update as specified.

D. Submit revised schedules and time impact analyses as specified.

E. Submit schedules in the media and number of copies as follows:

1. 3 sets of the CPM network and/or bar chart (as specified by the Owner) on

D-size sheets. Color-coding to be specified by the Owner.

2. 3 sets of Tabular reports listing all activities sorted numerically identifying duration, early start, late start, early finish, late finish, total float, and all predecessor/successor information.

3. 2 sets of CPM Schedule data electronic files in a native backed-up file (.xer) stored on CD/DVD.

1.06 PRELIMINARY SCHEDULE

A. Refer to General Conditions.

1.07 BASELINE SCHEDULE

A. Refer to General Conditions.

1.08 WEATHER DAYS ALLOWANCE

A. Refer to the Supplementary Conditions.

1.09 REVIEW AND ACCEPTANCE OF SCHEDULES

A. Engineer will review Baseline Schedule, Schedule Updates, Schedule Revisions, and Time Impact Analyses to ascertain compliance with specified project constraints, compliance with milestone dates, reasonableness of durations and sequence, accurate inter-relationships, and completeness.

B. Engineer and Owner will issue written comments following completion of review of Baseline Schedule within 20 calendar days after receipt.

C. Written comments on review of Schedule Updates and Schedule Revisions and Time Impact Analyses will be returned to Contractor within 14 calendar days after receipt by Engineer.

D. Revise and resubmit schedule in accordance with Engineer's comments within 5 calendar days after receipt of such comments, or request joint meeting to resolve objections.

E. If Engineer requests a meeting, the Contractor and all major subcontractors must participate in the meeting with Engineer.

1. Revise and resubmit schedule within 5 calendar days after meeting.

100% DESIGN 01324-4

F. Use accepted schedule for planning, organizing, and directing the work and for reporting progress.

G. Engineer’s submittal review response:

1. When schedule reflects Owner's and Contractor's agreement of project approach and sequence, schedule will be accepted by Owner.

2. Engineer’s submittal review response for schedule submittal will be “Receipt

Acknowledged – Filed for Record” including applicable comments.

H. Acceptance of the schedules by the Owner is for general conformance with the Contract Documents and for Owner’s planning information, and does not relieve the Contractor of sole responsibility for planning, coordinating, and executing the Work within the contract completion dates. Omissions and errors in the accepted schedules shall not excuse performance less than that required by the Contract Documents. Acceptance by the Owner in no way constitutes an evaluation or validation of the Contractor’s plan, sequence or means, methods, and techniques of construction.

1.10 SCHEDULE UPDATES

A. Any update:

1. Prepare update using most recent accepted version of schedule including:

a. Actual start dates of activities that have been started.

b. Actual finish dates of activities that have been completed.

c. Percentage of completion of activities that have been started but not finished.

d. Actual dates on which milestones were achieved.

e. Update activities by inputting percent complete figures with actual dates.

f. Use retained logic in preparing Schedule Updates.

g. When necessary, input remaining durations for activities whose finish dates cannot be calculated accurately with a percent complete figure only.

h. Revisions to the schedule may be included that have been previously approved as specified in this Section under Revisions to Schedule.

B. Monthly updates:

1. Submit written narrative report in conjunction with each Schedule Update including descriptions of the following:

a. Activities added to or deleted from the schedule are to adhere to cost and other resource loading requirements.

1) Identify added activities in manner distinctly different from original activity designations.

b. Changes in sequence or estimated duration of activities.

c. Current or anticipated problems and delays affecting progress, impact of these problems and delays and measures taken to mitigate impact.

d. Assumptions made and activities…

This is the start of the file's text. The full file is on GovTribe.