AK DOT 135(5), Glenn Highway: West Chickaloon Grade, Matanuska Susitna Borough, Alaska
The work consists of grading, base, paving, safety features, minor bridge work, and other small items of work. Bridge work includes finishing the construction of a three span, 353-foot long concrete girder bridge. The work includes finishing the bridge railing, transitions to guardrail, approach slabs and expansion joints, and a membrane waterproofing seal followed by a 4-inch asphalt overlay on the bridge deck. The work includes demolition of the existing steel girder bridge upon completion of the new structure.
Project length: 0.82 miles
Tentative Fixed Completion Date: Summer 2018 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Tentative Advertisement Date: Spring 2016
Estimated Price Range: Between $15 million and $20 million
Location: Approximately 30 miles NE of Palmer, AK
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
Base Schedule A
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance (yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion & Sediment Control, Temporary Turf Establishment, ACRE 17.2 157 Soil Erosion Control, Silt Fence, LNFT 16,000 157 Soil Erosion Control, Fiber Roll, LNFT 12,000 157 Storm Water Pollution Prevention Plan LPSM Yes 157 Storm Water Pollution Prevention Plan, Inspection, LPSM Yes 158 Watering for Dust Control, MGAL 100
DIVISION 200 – Earthwork
201 Clearing & Grubbing, ACRE 18 203 Removal of Bridge, EACH 1 203 Removal of Delineator, EACH 69 203 Removal of Sign, EACH 5 203 Removal of Guardrail, LNFT 2,573 204 Roadway Excavation 700,000 204 Select Borrow 42,000 205 Rock Blasting (subsidiary to Roadway Excavation) 205 Blasting Consultant (Subsidiary to Roadway Excavation if necessary) (yes/no) Yes 207 Separation-Stabilization Geotextile, Class 2, Type B, SQYD 1,100
208 Structure Excavation, CUYD 140 211 Roadway Obliteration, Method 2, SQYD 7,040
DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap Ditch, Method A, Class 2, LNFT 705
DIVISION 300 – Aggregate and Base Courses 302 Roadway Aggregate, Method 2, TON 14,000 303 Ditch Reconditioning, LNFT 1,000
DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete Pavement, Type 1, TON 6,500 412 Asphalt Tack Coat, TON 23
DIVISION 550 – Bridge Construction 552 Structural Concrete, Class A (AE), CUYD 41 552 Structural Concrete, Class D (AE), CUYD 2 552 Structural Concrete, Class D (AE), For Approach Slabs, Type 2, CUYD 160 552 Expansion Joints, LNFT 78 554 Reinforcing Steel, LB 7,550 554 Reinforcing Steel, Epoxy Coated, LB 450 556 Bridge Railing, Steel, Two-Rail, LNFT 43 559 Membrane Waterproofing, SQYD 1,890
DIVISION 600 – Incidental Construction
617 GUARDRAIL SYSTEM G4, TYPE 2, CLASS A STEEL
OR WOOD POSTS, LNFT 2,000
617 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS A, LNFT 82
617 TERMINAL SECTION, TYPE G4-CRT, EACH 2
617 TERMINAL SECTION TYPE TANGENT, EACH 5
617 TERMINAL SECTION, TYPE LST, EACH 3
617 STRUCTURE TRANSITION RAILING, LNFT 99
622 Rental Equipment (yes/no) Yes 623 General Labor (yes/no) Yes 624 Placing Conserved Topsoil, 4-inch depth, ACRE 10 625 Turf Establishment, ACRE 10 633 Permanent Traffic Control, Sign System, SQFT 80 633 Permanent Traffic Control, Remove and Reset, EACH 18 634 Permanent Pavement Markings, MMA Solid White, LNFT 10,000 634 Permanent Pavement Markings, MMA Broken Double Yellow, LNFT 1,200 634 Permanent Pavement Markings, MMA Solid and Broken Double Yellow, LNFT 1,350 634 Permanent Pavement Markings, MMA Solid Double Yellow, LNFT 2,600 634 Permanent Pavement Markings, MMA Stop Bar, LNFT 60 635 Temporary Traffic Control, Traffic Control Supervisor, LPSM All 635 Temporary Traffic Control, Cone, EACH 135 635 Temporary Traffic Control, Warning Light Type B, EACH 3 635 Temporary Traffic Control, Concrete Barrier, LNFT 7,000 635 Temporary Traffic Control, Pavement Markings, LNFT 10,000 635 Temporary Traffic Control, Construction Sign, SQFT 250 635 Temporary Traffic Control, Pilot Car, DAY 100 635 Temporary Traffic Control, Flagger, FXHR 8,000 646 Fixture, Mailbox, EACH 3