AKDOT135(5)_Earthwork_Geopak_Fill_and_Select_Borrow_Correction.pdf
PDF 59 KB Posted
- Attached to
- AK DOT 135(5), Glenn Highway Rehabilitation West Chickaloon Grade Section: MP 77. 4 to 78. 2
- Solicitation number
- DTFH7016B00007
About this file
AKDOT135(5)_Earthwork_Geopak Fill and Select Borrow Correction
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
D Sheet Station Cut (cu yd) D Sheet totals Fill (cu yd) D Sheet totals
Geopak EW Run Layer 5 (cu yd)
Layer 5 Corrected (sq ft)
Fill Corrected (sq ft) Layer 5 Corrected (cu yd) Fill Corrected (cu yd)
CORRECT
ED FILL
(cu yd)
3 1008305.07 0 0 0
1008350.00 8.97 0 0
1008359.75 8.94 0 0
1008360.00 0.77 0.04 0.04
1008375.00 71.18 12.11 12.11
1008400.00 119.41 39.91 39.91
1008410.00 48.19 20.95 20.95
1008425.00 72.82 32.54 32.54
1008450.00 123.1 44.1 44.1
1008465.09 75.42 19.71 19.71
1008475.00 50.23 11.29 11.29
1008500.00 129.08 26.78 26.78
1008525.00 131.59 25.41 25.41
1008550.00 133.93 24.44 24.44
1008575.00 134.38 23.19 23.19
1008600.00 131.17 28.31 28.31
1008615.09 76.7 22.86 22.86
1008625.00 49.43 17.49 17.49
1008650.00 128.17 43.43 43.43
1008675.00 138.39 36.98 36.98
1008700.00 145.96 32.25 32.25
1008725.00 149.77 28.95 28.95
1008750.00 153.75 27.39 27.39
1008775.00 155.79 27.36 27.36
1008800.00 158.72 27.87 27.87
1008825.00 164.26 30.19 30.19
1008850.00 166.67 35.34 35.34
1008875.00 167.98 47.42 47.42
1008900.00 173.25 71.33 71.33
1008925.00 181.19 75 75
1008925.36 2.67 0.9 0.9
1008950.00 220.9 30.53 30.53
1008975.00 247.67 0 0
1009000.00 236.35 3957 13.56 878 13.56
4 1009001.48 14.24 1.77 1.77
1009025.00 228.67 26.6 26.6
1009039.52 141.33 18.82 18.82
1009039.77 2.43 0.59 0.59
1009050.00 94.39 30.37 30.37
1009051.70 14.73 4.83 4.83
1009069.70 147.07 42.2 42.2
1009075.00 40.71 9.5 9.5
1009100.00 187.94 35.83 35.83
1009125.00 171.27 27.76 27.76
1009150.00 147.27 29.31 29.31
1009151.70 9.25 2.19 2.19
1009175.00 105.91 55.29 55.29
1009200.00 85.83 108.85 108.85
From Geopak Earthwork Run Manually corrected due to Geopak Earthwork Error totals
Geopak EW Run Layer 5 (cu yd)
Layer 5 Corrected (sq ft)
Fill Corrected (sq ft) Layer 5 Corrected (cu yd) Fill Corrected (cu yd)
CORRECT
ED FILL
(cu yd)
From Geopak Earthwork Run Manually corrected due to Geopak Earthwork Error
1009225.00 73.92 153.36 153.36
1009250.00 63.42 194.3 194.3
1009275.00 54.48 225.51 225.51
1009300.00 46.08 258.68 258.68
1009325.00 37.01 281.96 281.96
1009350.00 26.86 283.65 283.65
1009375.00 17.71 293.7 293.7
1009400.00 11.05 322.55 322.55
1009425.00 5.72 353.01 353.01
1009450.00 1.81 378.95 378.95
1009475.00 0.22 417.08 417.08
1009490.00 0.05 252.62 252.62
1009500.00 0.03 183.71 183.71
1009525.00 0 597.04 192.15 725.67 597.04
1009550.00 0 652.41 169 173.22 678.05 169.15 649.87 649.87
1009575.00 0 314.3 485 173.22 707.65 160.39 641.53 641.53
1009600.00 0 347.58 485 173.22 751.07 160.39 675.33 675.33
1009625.00 0 738.33 160 173.22 839.72 160.39 736.48 736.48
1009650.00 0 390.75 589 173.22 920.53 160.39 814.93 814.93
1009675.00 0 461.79 589 173.22 999.15 160.39 888.74 888.74
1009700.00 0 461.79 669 173.22 1102.1 160.39 972.80 972.80
1009725.00 0 562.19 669 173.22 1213.82 160.39 1072.19 1072.19
1009750.00 0 562.19 743 173.22 1257.65 160.39 1144.20 1144.20
1009775.00 0 587.31 743 173.22 1268.6 160.39 1169.56 1169.56
1009800.00 0 1191.43 160 173.22 1305.06 160.39 1191.51 1191.51
1009825.00 0 1138.35 160 173.22 1154.01 160.39 1138.46 1138.46
1009850.00 0 963.29 963.29
1009875.00 0 815.91 815.91
1009900.00 0 733.17 733.17
1009925.00 0 694.98 694.98
1009950.00 0 667.59 667.59
1009975.00 0 618.29 618.29
1010000.00 0 604.04 604.04
1010025.00 0 618.93 618.93
1010050.00 0 629.32 173.22 690.11 629.32
1010075.00 263.64 623.15 160 173.22 665.43 160.39 627.56 627.56
1010100.00 1225.44 308.07 424 173.22 568.23 160.39 571.14 571.14
1010125.00 2677.5 262.41 424 173.22 565.49 160.39 524.87 524.87
1010139.00 2153.93 278.07 90 173.22 512.33 89.82 279.43 279.43
1010150.00 2016.41 186.9 72 178.72 411.77 71.69 188.24 188.24
1010175.00 5394.26 190.63 347 191.22 380.58 171.27 366.83 366.83
1010190.00 3667.96 103.2 214 198.72 371.49 108.32 208.91 208.91
1010199.75 2528.96 133.08 72 198.72 365.34 71.76 133.04 133.04
1010200.00 66.31 3.35 Total = 7424 2927 3.35 totals
Geopak EW Run Layer 5 (cu yd)
Layer 5 Corrected (sq ft)
Fill Corrected (sq ft) Layer 5 Corrected (cu yd) Fill Corrected (cu yd)
CORRECT
ED FILL
(cu yd)
From Geopak Earthwork Run Manually corrected due to Geopak Earthwork Error
1010225.00 6975.77 326.42
Difference to be subtracted from grand total of Layer 5 = 4497 cu yd 326.42
1010250.00 7609.4 343.5 Difference checks out = 4502 343.50
1010275.00 8244.3 363.27 363.27
1010300.00 9141.94 352.75 352.75
1010325.00 10330.64 331.45 331.45
1010350.00 11637.84 306.29 306.29
1010375.00 13027.17 294.96 294.96
1010376.88 1037.6 22.4 22.40
1010400.00 13405.99 281.52 281.52
1010425.00 15405.4 318.14 318.14
1010450.00 15727.44 336.06 336.06
1010475.00 15695.72 358.72 358.72
5 1010500.00 15296.62 165,260 382.06 28,952 382.06
1010525.00 14886.22 399.48 399.48
1010526.96 1159.13 31.75 31.75
1010540.00 7693.71 210.61 210.61
1010550.00 5862.69 161.65 161.65
1010575.00 14656.95 404.77 404.77
1010600.00 14658.31 405.14 405.14
1010610.00 5822.51 162.33 162.33
1010625.00 8687.04 243.96 243.96
1010650.00 14224.49 404.02 404.02
1010675.00 13746.74 431.32 431.32
1010700.00 13586.42 482.44 482.44
1010725.00 13895.46 523.87 523.87
1010750.00 14499.81 535.18 535.18
1010775.00 15304.82 536.5 536.50
1010800.00 16031.49 521.34 521.34
1010825.00 16847.4 474.91 474.91
1010850.00 17779.62 416.96 416.96
1010875.00 18333.66 356.62 356.62
1010900.00 18638.02 323.34 323.34
1010925.00 18757.46 317.79 317.79
1010950.00 18423.69 312.22 312.22
1010975.00 18050.1 304.75 304.75
1011000.00 17475.08 311.71 311.71
1011025.00 16875.19 309.81 309.81
1011050.00 16794.39 291.51 291.51
1011075.00 16617.62 263.92 263.92
1011100.00 16036.13 232.62 232.62 totals
Geopak EW Run Layer 5 (cu yd)
Layer 5 Corrected (sq ft)
Fill Corrected (sq ft) Layer 5 Corrected (cu yd) Fill Corrected (cu yd)
CORRECT
ED FILL
(cu yd)
From Geopak Earthwork Run Manually corrected due to Geopak Earthwork Error
1011120.00 12257.88 175.8 175.80
1011125.00 2975.87 44.41 44.41
1011140.00 8675.35 150.79 150.79
1011150.00 5560.12 109.26 109.26
1011175.00 13195.48 272.36 272.36
1011200.00 11769.23 276 276.00
1011225.00 9880.79 307.83 307.83
1011250.00 8000.57 312.13 312.13
1011270.87 4870.47 204.73 204.73
1011275.00 720.93 34.62 34.62
1011300.00 3401.75 186.16 186.16
1011315.00 1340.56 89.61 89.61
1011325.00 612.88 51.25 51.25
1011350.00 974.02 129.19 129.19
1011375.00 634.67 141.52 141.52
1011400.00 454.12 144.96 144.96
1011401.31 16.15 7.11 7.11
1011412.67 135.07 59.12 59.12
1011420.82 89.12 45.79 45.79
1011425.00 41.03 24.72 24.72
1011431.14 36.47 37.44 37.44
1011439.00 20.05 24.27 24.27
1011445.80 16.45 0 0.00
Bridge 1011449.82 7.79 471,031 0 12,200 0.00 Bridge 1011802.50 0.01 0 0.00
1011816.32 1.59 0 0.00
1011821.16 0.28 0 0.00
1011825.00 0.24 4.83 4.83
1011840.00 27.99 18.98 18.98
1011846.94 33.35 0.08 0.08
1011850.00 18.42 0.03 0.03
1011875.00 151.45 0.15 0.15
1011900.00 135.35 0.54 0.54
1011925.00 121.37 14.3 14.30
1011950.00 135.2 27.53 27.53
1011964.23 83.4 16.98 16.98
1011975.00 62.81 19.16 19.16
1012000.00 171.3 943 83.13 186 83.13
7 1012013.18 106.67 67.82 67.82
1012025.00 100.38 60.67 60.67
1012027.26 19.71 9.62 9.62
1012043.19 149.62 55.7 55.70
1012050.00 68.09 19.57 19.57
1012075.00 256.88 74.42 74.42
1012100.00 269.08 75.94 75.94
1012125.00 278.66 72.21 72.21 totals
Geopak EW Run Layer 5 (cu yd)
Layer 5 Corrected (sq ft)
Fill Corrected (sq ft) Layer 5 Corrected (cu yd) Fill Corrected (cu yd)
CORRECT
ED FILL
(cu yd)
From Geopak Earthwork Run Manually corrected due to Geopak Earthwork Error
1012150.00 287.12 66.25 66.25
1012175.00 292.38 64.39 64.39
1012200.00 290.76 73 73.00
1012225.00 275.28 135.25 135.25
1012250.00 253.11 247.29 247.29
1012275.00 235.46 254.88 254.88
1012300.00 218.76 145.24 145.24
1012325.00 216.27 235 235.00
1012350.00 220.13 399.07 399.07
1012375.00 211.04 408.19 408.19
1012400.00 200.34 434.33 434.33
1012425.00 191.3 507.77 507.77
1012450.00 187.02 611.44 611.44
1012475.00 181.49 729.97 729.97
1012500.00 173.73 822.24 822.24
1012525.00 171.45 794.78 794.78
1012550.03 171.69 740.25 740.25
1012566.70 116.69 476.56 476.56
1012575.00 58.96 219.25 219.25
1012600.00 174.12 577.3 577.30
1012605.59 38.09 111.97 111.97
1012625.00 127.86 337.37 337.37
1012650.00 156.21 309.17 309.17
1012663.50 81.27 63.49 63.49
1012665.00 4.45 5,784 0 9,200 0.00
0.00 Totals 646,974.24 646,974.24 46913.7 51415.39 51415.39