Contract Att12 - Daily Site Report.xlsx

XLSX spreadsheet 101 KB Posted

Attached to
Security Equipment Deployment Services - Checkpoint
Solicitation number
70T04020R9AP4050
Issued by

About this file

This document contains eight daily site reports and a solicitation for security equipment deployment services. The daily site reports provide status updates for airport security equipment installation projects, including accomplishments, risks, issues, milestones, and key contacts. They use a standardized template to report progress across multiple airport locations. The solicitation seeks proposals for checkpoint screening equipment deployment services for the Transportation Security Administration. Offerors are asked to refer to the attached request for proposal for details on requirements, response process, and evaluation criteria. Services include installation, configuration, and lifecycle maintenance of security screening technologies at airports nationwide.

View the file

Other files

File Type Posted
CP RFP_Amendment 04_revised.pdf PDF
CP RFP_Amendment 04.pdf PDF
CP RFP_Amendment 04_SF30.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 04.xlsx XLSX spreadsheet
Q_and_A amendment 4.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 03 updated.xlsx XLSX spreadsheet
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 03.xlsx XLSX spreadsheet
CP RFP_Amendment 03_SF30.pdf PDF
CP RFP_Amendment 02.pdf PDF
CP RFP_Amendment 02_SF30.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 02.xlsx XLSX spreadsheet
CP_SEDS QandA_Amendment 02.pdf PDF
CP RFP_Amendment 01.pdf PDF
CP RFP_Amendment 01_SF30.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 01.xlsx XLSX spreadsheet
Solicitation Attachment 04-DHS Subcontracting Plan Review Checklist.pdf PDF
CP RFP QA_Amendment 01.pdf PDF
CP RFP 70T040R9AP4050 SEDS.pdf PDF
Contract Att07 - ETD - 500DT De-Installation Checklist.pdf PDF
Contract Att02 - BLS - CEIA EMA-MS Decommission Checklist.pdf PDF
Contract Att05 - WTMD - CEIA Decommission Checklist.pdf PDF
Contract Att06 - ETD - QSB220 De-Instal - Instal Checklist.pdf PDF
Solicitation Att3-Checkpoint PM Task Order.pdf PDF
Contract Att11 - Weekly Status Report.xlsx XLSX spreadsheet
SEDS Q and A Template.xls XLS spreadsheet
Contract Att04 - BLS - Responder Decomm Checklist.pdf PDF
Contract Att01 - AIT-1 and AIT-2 - L3 Decommission Checklist.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet .xlsx XLSX spreadsheet
Contract Att09 - PSP Site Survey Template.xlsx XLSX spreadsheet
Contract Att03 - AT Decommission Checklist.pdf PDF
Solicitation Att1-SF1449 Checkpoint.pdf PDF
Contract Att10 - PSP Site Survey Report Template.pdf PDF
Contract Att08 - Checkpoint IDIQ SIP Template.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00000000

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000001

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000002

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000003

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000004

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000005

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000006

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000007

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built

00000008

CDRL 01- DAILY SITE REPORT
CDRL Purpose:The Contractor shall deliver daily site progress and status reports for each site detailing accomplishments, risks and issues. These reports are critical to the Program Office’s ability to update program status reports accurately. Reports are due No Later Than 7AM Local time for all Regions. Daily reports are to begin once the IPT calls have commenced unless otherwise directed by the Regional Deployment Manager.
System Integrator:System Integrator POC:
Airport InformationTechnology Information
SystemOEMAllocatedInstall/Remove/RelocatationSite Prep
Airport Code:
Airport Name:
Task Order:

Date: 00/00/0000

Site Points of Contact
Company/PositionNameE-mail AddressOfficeCell

ReMAG Number Need Date Ordered Date Received Date Status Date Started Date Completed

Days Activities/Accomplishments
CompanyNo. of PersonnelStart TimeEnd TimeActivities Performed

Activities Planned for Tomorrow

Specific Deployment Site Risks
Date IdentifiedRisk ItemDescriptionRecommendationStatus
Issues and Variances to SIP
Date IdentifiedTask OwnerDescriptionContributing Factors
Cumulative System Installation
Location (Ckpt/Ln)TechnologySerial NumberTSA BarcodeSupporting AncillarySAT DateRAD DateComments
Key Milestones
Key MilestoneScheduled Completion DateCompletion DateComments
Notice to Proceed
Concept Drawing Approval
100% Construction Drawings
Permit Application Submission
ReMAG Submittal
Sub-Contractor SOW
Sub-Contract Award
SIP Submittal
Pre-Construction Meeting
Permit Approval
Start Site Work
Close out
Warehouse Close Out
Sign off on CAS As-Built